S. No.क्र. सं. | Name of Workकार्य का नाम | Date of Startकार्य आरम्भ करने की तिथि | Date of Completionकार्य समाप्त करने की तिथि | Cost (In Lac) |
Expenditure (In Lac) |
Progress | Agency | Status | Viewदेखें |
---|---|---|---|---|---|---|---|---|---|
1 | Construction of District Court Complex at Sector-26, Rohini, Delhi | 2024.06.10 | 2026.02.09 | 43055.92 | 0.00 (Jul'24) | Roshan Real Estate Pvt Ltd. | Work is recently awarded. Contractor is making arrangement for mobilizing his Tools & plants and labourers. |
Detail Report
Graph / Photo |
|
2 | C/O Integrated campus of G.B. Pant Engineering College and Polytechnic at Okhla delhi. | 2024.03.22 | 2026.11.21 | 42361.79 | 1048.09 (Jul'22) | 0.00 (Jul'24) | Som Projects Pvt. Ltd. | work is under progress. |
Detail Report
Graph / Photo |
3 | setting up of Semi permanent/temporary i.c.u at CNBC (G+4)(1912 beds) and GTB Hospital complex (G+4 ) (1912 Beds) Package-II (Electrical) | 2021.09.23 | 2022.02.22 | 40775.18 | 12389.92 (Jun'23) | 0.00 (Jan'24) | SAM India Builtwell | GTB : The erection of PEB structure and deck slab in main ward block nearing completion, while the same in Arrival & Diagnostic blocks in progress. The fire paint, internal partition etc. are in progress. The work is delayed due to revision in drawings by consultant, ban on construction works due to pollution during November-December followed by covid wave. CNBC : The erection of PEB structure and deck slab are nearing completion. The fire paint, internal partition, external wall etc. are in progress. The work is delayed due to revision in drawings by consultant as per requirement of MS, CNBC, ban on construction works due to pollution during November-December followed by covid wave. |
Detail Report
Graph / Photo |
4 | Construction of Hospital at Madipur, New Delhi | 2020.11.11 | 2022.11.10 | 26970.58 | 10425.19 (Jun'23) | 0.00 (Aug'24) | Ramacivil India Construction Private Limited | Physical Progress- 92 % Financial Progress - 144.10 Cr. |
Detail Report
Graph / Photo |
5 | Construction of Hospital Block at Guru Gobind Singh Govt. Hospital located at Raghubir Nagar, New Delhi | 2019.10.18 | 2021.04.10 | 13447.15 | 5225.16 (Jun'23) | 0.00 (Aug'24) | Roshan Real Estate Pvt Ltd. | All work completed only false ceiling work in Block-A & final painting work are under progress. |
Detail Report
Graph / Photo |
6 | Construction of Additional Court at New Plot at Karkardooma in Front Of existing Karkardooma Court Complex, Delhi (SH: C/o Main Block, External Development, Internal electrical installation, External lighting, Lift, Fire Fighting System, Fire Alarm with PA System, D.G. Sets, Electrical Sub-Station, HVAC works, Horticulture work & allied works.) | 2024.06.10 | 2026.02.09 | 12402.76 | 0.00 (Aug'24) | Abhilasha Enterprises | Site logistic setup and mobilization at site is under progress. |
Detail Report
Graph / Photo |
|
7 | C/o District Court Complex at Shastri Park, Near Usmanpur Police Station, Delhi. (SH: C/o Main Block, External Development, Internal Electrical Installation, External lighting, Lift, Fire Fighting System, Fire Alarm with PA System, D.G. Sets, Electrical Sub-Station, HVAC works, Horticulture work & allied works.) | 2024.06.10 | 2026.02.09 | 12052.77 | 0.00 (Jul'24) | Abhilasha Enterprises | Work recently awarded |
Detail Report
Graph / Photo |
|
8 | Construction of proposed New Buildings for expansion of Rao Tula Ram Memorial Govt. Hospital at Jaffarpur, Delhi. | 2019.08.06 | 2020.10.29 | 6563.40 | 2087.72 (Jul'23) | 0.00 (Aug'24) | PNSC Infrastructure Pvt. Ltd | All work completed except External development, entrance canopy and internal finishing works which are under progress. |
Detail Report
Graph / Photo |
9 | Construction of Pucca School Buildings (G+3) with Ancillary Facilities including internal water supply, sanitary installation, internal electrical installation and development of site at Sector-16, Dwarka ,New Delhi. (SH: Civil and Electrical Composite Work). | 2021.07.18 | 2022.07.17 | 5058.13 | 255.98 (Jul'23) | 0.00 (Aug'24) | PNSC Infrastructure Pvt. Ltd | Initial Delay was due to delay in receiving local body approval. DUAC approval received on 19.09.2022. Building Plans approved by SE (Bldg.), MCD vide file No. 10106691 dt. 03.04.2023. All local body approval has been received. Structural drawing prepared & proof checking from DTU Delhi is completed. Architectural & Structural drawing is issued to the agency. Building work started on 19.05.2023. Foundation work completed. Superstructure work started, RCC slab for floor-2 level is under progress. RPE amounting to Rs.47.52 Cr. sent to DoE vide this office letter 23(49)/23/CE(Proj.)/PWD/ Estimate/501 dated: 21.03.2024 for accord of Revised A/A & E/S. |
Detail Report
Graph / Photo |
10 | (a) C/o 76 Nos. Equivalent rooms SPS type (i.e. classrooms, Labs and Principal rooms), 12 Nos. toilets with ancillary facilities like pumping, sanitary and electrical installation like Lift, Fire Fighting work and development of site at Plot No.-1B, Sector-41, Rohini, Delhi. (b) C/o 72 Nos. Equivalent rooms SPS type (i.e. classrooms, Labs and Principal rooms), 1MP Hall, 08 Nos. toilets with ancillary facilities like pumping, sanitary and electrical installation like Lift, Fire Fighting work and development of site at Plot No.-2,C.F.-3, Sector-41, Rohini, Delhi. | 2024.01.20 | 2025.01.19 | 3527.47 | 0.00 (Sep'24) | RKMT BUILDCON PRIVATE LIMITED | Work in progress |
Detail Report
Graph / Photo |
|
11 | Construction of Pucca School Building (G+3) with ancillary facilities including internal water supply, sanitary installation, electrical installation and development of site etc. at Vacant land of F1 & F2 Block Sunder Nagri, Delhi. | 2022.10.17 | 2023.10.16 | 3000.18 | 1296.26 (Oct'23) | 0.00 (Aug'24) | Jai Bhagwan | RCC work completed, stone work 98% completed, Some repair work is going on. The paint putty, fixing of doors & windows in progress and development work in progress and same will be completed by 31.07.2024. |
Detail Report
Graph / Photo |
12 | Construction of DTC Bus Depot in resettlement colony at Sawada Ghevra, Delhi | 2022.04.05 | 2022.12.04 | 2915.78 | 1077.04 (Mar'23) | 0.00 (Jul'24) | SVK Infrastructures | Building Work: is in advance stage. Revised sanction awaited because of which work is hindering. If the santion is not received work will have to be foreclosed. |
Detail Report
Graph / Photo |
13 | Expansion / Remodeling of Deep Chand Bandhu Govt. Hospital at Kokiwala Bagh, Ashok Vihar, Delhi. Including water supply, sanitary, drainage and electrical works etc. | 2019.06.28 | 2020.06.22 | 2806.33 | 381.24 (Mar'23) | 0.00 (Mar'24) | Roshan Real Estate Pvt Ltd. | Work in progress (Civil 98% progress) (Electrical 95%) |
Detail Report
Graph / Photo |
14 | C/o 100 Nos. Equivalent SPS Classrooms in addition to Swimming Pool, Boundary Wall, 1 No. MP Hall, i/c Internal & External Water Supply, Sanitary Installation and Electrical Installation, RWH, UGT, Septic Tank, Development of site and Fire Fighting Systemetc. for New School Building at Naseerpur, New Delhi | 2022.02.12 | 2022.11.09 | 2800.59 | 1318.22 (Jun'23) | 0.00 (Aug'24) | SVK Infrastructures | Initially site was encroached by local people. Encroachment on the major part of land was removed with help of education department and Delhi Police on 22.03.2022. Partly site handed over to the agency for boundary wall and building construction on 23.03.2022. Due to High Court stay order dated 30.08.2022, work was stopped in disputed area. SDM Dwarka issued his order on 21.03.2023. After which work also started in the area which was earlier under dispute. Both Blocks of school building have been completed. Work of swimming pool is in progress. |
Detail Report
Graph / Photo |
15 | Construction of conventional Bus Depot no. I & II on ground floor at Sector A-1, A-4, Narela, Delhi | 2021.08.23 | 2022.05.22 | 2373.12 | 1117.89 (Mar'23) | 93.00 % (Jun'24) | M/s PK Gupta & Co. | Building Work: RCC work and Brickwork of Admin cum Rest Room, Toilet Block have been completed. Finishing work completed in Admin cum Rest room has been completed. Workshop Building-All the Structural work has been completed and finishing work is in progress. Hard standing/CC Pavement: All the work related to hardstanding has been completed except for the area occupied by TPDDL equipments and Labour camps. The progress of the work is being affected due to encroachment /non handing over of the land by TPDDL. The progress of work is hampered due to non availability of budget. |
Detail Report
Graph / Photo |
16 | Construction of Cluster Bus Depot at Kirari Village, Plot No.8 (PSP7), Sector-41, Rohini, Delhi. SH: Civil works and Electrical works. | 2023.05.24 | 2024.01.23 | 2107.18 | 30.00 % (Jun'24) | Kundu Nirma | The building work affected due to high water table. Matter of constructing the building on pile foundation was finalised. Casting of more than 440 piles has been completed. 80% of the Earth work has been completed. Casting of 1st Floor Columns of building are in progress. The progress of work is hampered due to non availability of budget. |
Detail Report
Graph / Photo |
|
17 | Construction of Govt Sr Sec Pucca School building G plus 3 with ancillary facilities including internal water supply internal electrical installation sanitary installations development of site STP and RWH etc at Sector 27 Rohini. | 2020.05.31 | 2021.05.30 | 1874.70 | 1644.00 (Jun'23) | 0.00 (Aug'24) | SSP Promoters and Builders Private Limited | Work in progress |
Detail Report
Graph / Photo |
18 | Construction of Residential Hostel at Chhattrasal Stadium, Model Town, Delhi. SH: C/o Hostel Building including External Development works, Internal Electrical Installation, External Lighting, lifts, fire fighting system, fire alarm with PA System, CCTV, Audio video system, HVAC works | 2023.02.27 | 2024.07.26 | 1839.86 | 217.20 (Jun'23) | 0.00 (Mar'24) | KALYAN CHANDRA GOYAL & CO. | In back portion of building, the casting of roof slab/beam for 5th floor level is completed and reinforcement work is in progress. In front portion of the building, the casting of 2nd floor (double height storey) is completed and reinforcement work for column frp, 3rd to 4th floor is in progress. The brick work and CC block masonry work in progress. The work is very slow progress due to lack of fund. (Physical progress upto date 40%) |
Detail Report
Graph / Photo |
19 | C/o 52 Nos. (G+3) equivalent SPS class rooms including stilt, 1 lift, 8 toilet blocks & 4 staircase at A C C GSBV at Jhilmil Colony, Delhi & 48 Nos. (G+3) equivalent SPS class rooms including 3 nos staircase, lift and 4 toilet blocks at Mustafabad School, Delhi including internal & external water supply, sanitary installations, melectrical installations, development of site, boundary wall, UGR, RWH, Fire Fighting system etc | 2022.04.01 | 2023.02.24 | 1798.93 | 374.04 (Jun'23) | 0.00 (Sep'24) | K. L. ARORA & SON | For 60% area work completed & for 30% area RCC work completed and finishing work just started and will be completed by 31.08.2024 & remaining 10% area could not start due to space constraints and branches of tree in building line and for the same application has applied for pruning to the forest department. |
Detail Report
Graph / Photo |
20 | Construction of SPS (4-Storey) for additional class rooms at Karampura Campus of Dr. B.R. Ambedkar University, Delhi. | 2023.03.24 | 2023.09.19 | 1729.05 | 0.00 (Jul'24) | SPS Infrabuild Pvt. Ltd. | 85% |
Detail Report
Graph / Photo |
|
21 | C/o 68 Nos. (G+3) Equivalent SPS classrooms in SKV (Ravindra Thakur), East Vinod Nagar, Delhi (School ID 1002028) including 5 nos. staircase, 8 nos toilets, 1 no. lift & 25 nos Class rooms over existing (G+1) SPS structure with Prefabricated fibre reinforced sandwich panel with Light Gauged Steel Framed Structure including internal & external water supply, sanitary installations, electrical. | 2023.03.27 | 2024.02.19 | 1554.26 | 307.14 (Jun'23) | 0.00 (Sep'24) | SWASTIC CONSTRUCTION CO | Block A Finishing work in progress and canopy structure work in progress. Block B Tile & granite work in progress along with plaster work back side of building. Development work in progress. |
Detail Report
Graph / Photo |
22 | C/o 48 nos. additional (G+3) SPS equivalent classrooms including 3 nos staircase, 2 nos lifts and 8 nos toilet block at St. Eknath SKV J&K Block Dilshad Garden and 36 nos. additional (G+3) SPS equivalent classrooms including 2 nos Staircase, 4 nos toilet blocks & 1 lift and 1 MP hall at DIET J&K block Dilshad Garden, Delhi including internal & external water supply, sanitary installations, electrical installations, development of site, UGR, RWH, Fire Fighting system etc | 2022.03.26 | 2023.02.19 | 1553.88 | 642.50 (Jul'23) | 0.00 (Sep'24) | K L Arora & Son | Tower A - Finishing & development work under progress and will be completed by the end of 30th June 2024 and will be handed over by 15.07.2024 Tower B - is not taken up due to existency of trees in the proposed building plan regarding the same this office has written a letter to HOS to not being taken up due to tree in building plan. MP Hall - Work completed. DIET Block - Structural work completed of 2/3 building portion and structural work of remaining 1/3 portion of 2nd floor under progress except 2 no. classrooms and 1 staircase held up as there are branches of tree in the building line for which approval is pending for prunning of trees from forest department. Tile work & finishing work under progress in structurally completed 2/3 building portion and will be completed by 31.08.2024 |
Detail Report
Graph / Photo |
23 | Composite Work : C/o Prefab structures office, trainee, staff accommodation, class room, kitchen, store, toilet block, parking shed, road work and other misc. civil work and various Electrical works | 2023.11.01 | 2024.04.30 | 1462.98 | Kalyan Chandra Goyal & Company |
Detail Report
Graph / Photo |
|||
24 | C/o 76 Nos. (G Plus 3) SPS equivalent classrooms at RSKV Mandawali No. 2 (School ID 1002023) including 5 staircase, 8 toilet blocks, 1 lift and internal & external water supply, sanitary installations, electrical installations, development of site, UGR, RWH, Natural STP & Fire Fighting System etc | 2022.04.02 | 2023.02.25 | 1359.28 | 613.77 (Jul'23) | 0.00 (Sep'24) | K. L. ARORA & SON | Work completed and cleaning and development work is in progress and will be completed by 15.07.2024 |
Detail Report
Graph / Photo |
25 | Construction of 72 Nos. equivallent classrooms (G+3) including internal electrical works sanitary installations, watter supply, fire fighting and external development works etc for Govt. Co-ed. Sr. Sec. School at PSP-10, Industrial area Phase-V, Rohini, Kirari, Delhi (Civil and Electrical) | 2022.03.12 | 2023.02.04 | 1275.84 | 476.42 (Jul'23) | 0.00 (Sep'24) | M/s SURENDRA KUMAR | Work in progress |
Detail Report
Graph / Photo |
26 | Comprehensive consultancy Services for Construction of Delhi Sports University at Village Ghevra Delhi | 2022.04.06 | 2025.04.05 | 1099.29 | 114.42 (Jul'23) | 0.00 (Jul'23) | SIKKA ASSOCIATES REGD. | 30 |
Detail Report
Graph / Photo |
27 | C/o 76 Nos (G+3) equivalent SPS Class Rooms including 2 nos stilt, 8 nos toilet, 4 nos staircase, 1 no lift, RWH & UGR in SKV Vishwamitra, Old Seemapuri, Delhi. (SH : SPS type building i/c internal & external water supply, sanitary installations, electrical installations, development of site, fire fighting system etc.) | 2022.04.18 | 2023.03.13 | 1090.67 | 699.55 (Jul'23) | 0.00 (Sep'24) | K. L. ARORA & SON | Work in progress. Internal work completed & cleaning in progress, some development work under progress. One block handed over and remaining one will be handed over by 15.07.2024. |
Detail Report
Graph / Photo |
28 | C/o 48 Nos. (G+3) SPS Eq. classroom including 3 staircase, 1 lift and 1 toilet block in Mustafabad School , Delhi Including internal & external water supply, sanitary installations, electrical installations, development of site, Boundary Wall, UGR, RWH & Fire Fighting system etc. | 2023.03.09 | 2024.02.01 | 1058.78 | 91.00 (Mar'23) | 0.00 (Sep'24) | AMOCON | 3rd Floor Level beam reinforcement work in progress, brick masonary at GF in progress The site approach is very narrow and no congested working space for material and labour at site. |
Detail Report
Graph / Photo |
29 | C/o Researcher Block and Residential Staff Quarters for Delhi Institute of Hotel Management and Catering Technology at Lajpat Nagar, New Delhi | 2020.08.09 | 2021.11.08 | 958.41 | 55.00 (May'22) | 0.00 (Feb'24) | Sushil Buildwell Pvt. Ltd. | Work Just Started |
Detail Report
Graph / Photo |
30 | Comprehensive Maintenance of Civil works for Day-to-day Maintenance and A/R & M/o Work, Special Repair etc of GTB Hospital, Campus Shahdara, Rajiv Gandhi Super Speciality Hospital, Campus Tahirpur, Dr. Hedgewar Arogya Sansthan, DGHS, Karkardooma, Hospital, Campus, AAPC Kanti Nagar & Various Dispensaries under CHMSD-V, Delhi during 2022-2023& 2023-24 | 2022.06.03 | 2024.06.02 | 721.25 | 351.65 (Aug'23) | 0.00 (Jun'24) | AZFARUDDIN | (Up to date progress of all Sub Divisions) Work is in progress. |
Detail Report
Graph / Photo |
31 | Civil and Electrical Work. | 2023.03.05 | 2023.11.29 | 617.03 | 16.00 (Sep'23) | 0.00 (Mar'24) | CHANDRA CONSTRUCTION COMPANY |
Detail Report
Graph / Photo |
|
32 | Strengthening of Roads Dr. Kundan Lal Marg, Rajouri Apartment Road, H.No. 14/35 to 13/101 Subhash Nagar (Near Shadley School), Shanti Devi Marg, Ayodhya Prasad Chopra Marg, R.No. 32 to 17/117 Subhash Nagar, DA-1, Hari Nagar to DB-1 Hari Nagar, BA-BB | 2022.09.25 | 2023.01.24 | 583.83 | 0.00 (Jun'24) | MAHAVIR PRASAD GUPTA AND SONS |
Detail Report
Graph / Photo |
||
33 | Construction of New Academic Block (G Plus 3) with Future Extention of One Floor at Lakshmibai College, Ashok Vihar, Delhi (Civil and Electrical) Composite work | 2022.01.28 | 2022.12.27 | 579.95 | 360.97 (May'23) | 0.00 (Aug'24) | Invalid | Work is in progress. |
Detail Report
Graph / Photo |
34 | Construction of Foot Over Bridge between Newly Constructed Court Building and Tis Hazari Court Complex at Boulevard Road under Sub Division-I of Division SRDP-I, Delhi (Sh:- Civil & Electrical Works). | 2023.02.20 | 2023.05.21 | 450.86 | 0.00 (Mar'24) | S S Chauhan & Sons | steel erection work is in progress |
Detail Report
Graph / Photo |
|
35 | Civil & Electrical Work. | 2023.03.30 | 2023.09.29 | 352.07 | 0.00 (Mar'24) | Engineers India Construction Ltd. |
Detail Report
Graph / Photo |
||
36 | Construction of 21 nos. Aam Aadmi Mohalla Clinic (Primary Health Centres) at various places in the jurisdiction of Shahdara Circle, PWD, Delhi (Civil and Electrical Work). | 2019.02.28 | 2019.06.27 | 294.21 | 58.25 (Feb'22) | 0.00 (Dec'23) | AASRA Martech Pvt.Ltd. | Work in progress. |
Detail Report
Graph / Photo |
37 | Construction of two storey Multipurpose Hall (SPS) at Sarvodaya Co-ed Vidyalaya, Shahpur Jat (School ID: 1925333) including internal and external water supply, sanitary installations, electric installations and fire fighting (Civil plus Elect. work). | 2022.08.09 | 2023.08.08 | 292.57 | 8.79 (Mar'23) | 0.00 (Sep'24) | Nand gopal Gupta |
Detail Report
Graph / Photo |
|
38 | Consultancy Services for Comprehensive Architectural Planning and Designing for Construction of Technical Campus at Village Bakkarwala Delhi | 2022.01.16 | 2024.10.15 | 288.00 | Arcop Associates Pvt. Ltd. | Preliminary Concept report submitted by Consultant has been submitted to DTTE vide letter dated 04.04.2022 for approval. |
Detail Report
Graph / Photo |
||
39 | Acoustic Interior, Audio, Video, Electrical, HVAC, Stage Lighting and Stage Furnishing and Misc. works for auditorium in Rouse Avenue District Court Complex, DDU Marg, New Delhi. | 2023.12.25 | 2024.03.23 | 224.63 | Vaibhav Constructions | Work in progress |
Detail Report
Graph / Photo |
||
40 | Construction of Boundary Wall of vacant Land at Madan Halwai Farm Loni, Johripur, Delhi. | 2023.09.01 | 2024.02.27 | 152.17 | 0.00 (Aug'24) | CBC and Sons | 90% Boundary wall brick & column work is completed. Grill work & GRC wall tile work in progress and will be completed by 15.07.2024 |
Detail Report
Graph / Photo |
|
41 | (1) Creation of Ahlmad Rooms on the terrace of Extension Block Tis Hazari Court Complex, Delhi. (SH:- E&M Works). (2) Renovation of 7 nos. court rooms at Tis Hazari Court, Delhi. (SH: Electrical Installation & HVAC Works). (3) Up-gradation and extension of Bosch make CCTV surveillance System for Newly constructed foot over bridge between Tis Hazari Court Complex and Extension Block Tis Hazari Court, Delhi. (4) Renovation of Annexure-II Building of Tis Hazari Court Delhi for Shifting of prosecution branch (SH:- Electrical Installation & HVAC Works). | 2024.04.18 | 2024.07.16 | 143.59 | 0.00 (Jul'24) | Shri Bankey Bihari Electrical | Work in progress |
Detail Report
Graph / Photo |
|
42 | Construction and Commissioning of Mohalla Clinics at various places in North-East Delhi under the Jurisdiction of PWD Sub- Division M-2221 (2nd call). | 2019.01.25 | 2019.05.24 | 140.44 | 216.46 (Oct'21) | 0.00 (Oct'21) | Uma Shankar | work in progress |
Detail Report
Graph / Photo |
43 | Remodeling of drain in opposite side of Mansarovar Park to Kendriya Vidhalaya along with G.T. Road under Sub Division M-2111 during 2022-23. | 2023.04.21 | 2023.10.17 | 136.64 | 0.00 (Mar'24) | Chaudhary Construction Company Pvt. Ltd. | in progress |
Detail Report
Graph / Photo |
|
44 | Construction of Migrant workers support centre at the office joint labour commissioner Vishwakarma Nagar Jhilmil colony Delhi (Civil and Electrical Work) | 2022.04.23 | 2023.01.22 | 124.05 | 9.97 (Feb'23) | 0.00 (Jun'24) | Dheeraj Singh & Company | In Progress. |
Detail Report
Graph / Photo |
45 | C/o Extention of MADI of Dental Sciences,Ph-II at Bahadur Shah Zafar Marg,ND.SH SITCof Medical Gas Pipeline System including 3 Years Comprehensive Maintenance | 2019.08.12 | 2019.11.09 | 115.37 | Med Freshe Pvt. Ltd. | work in progress by Med Freshe Pvt. Ltd |
Detail Report
Graph / Photo |
||
46 | Construction of RCC wall in place of existing boundary wall above ground level and Fencing work | 2022.12.21 | 2023.03.20 | 96.02 | 0.00 (Mar'24) | Work in progress. |
Detail Report
Graph / Photo |
||
47 | Designing Manufacturing Installation and Commissioning of ceiling mounted Facade Access System on external facade and inner facade in Atrium at S Block Delhi High Court New Delhi | 2022.12.16 | 2023.03.15 | 91.53 | 78.12 (Mar'23) | 0.00 (Mar'24) | M P BHATIA | Work in progress |
Detail Report
Graph / Photo |
48 | Construction of Extention of Maulana Azad Dental Institute of Dental Sciences, phaseII at Bahadur Shah Zafar Marg, New Delhi.SH Supplying, installation, testing and Commissioning of Modular Operation Theatre | 2019.08.12 | 2019.11.09 | 83.93 | 21.56 (Feb'22) | 0.00 (Dec'23) | MDD Medical System (INDIA) Pvt. Ltd | work in progress by MDD Medical System (I) Pvt.Ltd. |
Detail Report
Graph / Photo |
49 | Up-gradation of swimming pool and other misc. civil works including electrical work | 2021.08.11 | 2021.12.08 | 83.39 | 90.41 (Mar'23) | 0.00 (May'24) | M/s Tanishq Ions | In Progress. |
Detail Report
Graph / Photo |
50 | Replacement of Water Tanks & M.S. framed platform at various floors of Delhi Secretariat Building | 2022.05.21 | 2022.07.20 | 81.25 | 0.00 (Nov'23) | Work in progress.70% |
Detail Report
Graph / Photo |
||
51 | Renovation of gate no. 1 & 3 with GRC mouldings/cornices). (Civil & Electrical Works) | 2022.06.25 | 2022.08.23 | 78.59 | 135.99 (Jun'23) | 0.00 (Jun'24) | Uma Shankar |
Detail Report
Graph / Photo |
|
52 | A A to Karkardooma Court Complex Delhi SH Replacement of damaged Kota stone flooring into Granite stone flooring P F false ceiling and wall tiles in corridor and common area of ground floor including Electrical Work of A C and I block. | 2023.04.05 | 2023.07.03 | 75.02 | 0.00 (May'24) | Rakesh Kumar Rai | granite work at A block |
Detail Report
Graph / Photo |
|
53 | SH Work of UTCS Complex Employment exchange JJB Court Working Women Hostel HLTB Complex Sanskar Ashram, Department of Social Welfare and CDMO Shahdara KKD Court Division under SD M 2312 during 2022 23. | 2023.01.07 | 2024.01.06 | 64.35 | 26.08 (Aug'23) | 0.00 (Jun'24) | In Progress. |
Detail Report
Graph / Photo |
|
54 | Construction of 4 nos. Aam Aadmi Mohalla Clinic (Primary Health Centres) at various places in the jurisdiction of SRD Project Division-2, PWD, Delhi. (Civil & Electrical Work) | 2022.06.01 | 2022.11.27 | 63.68 | 0.00 (Nov'23) | R K Construction Co. |
Detail Report
Graph / Photo |
||
55 | Comprehensive maintenance of 310 DA staff qtrs. Supply of materials and providing services of manpower for day to day maintenance work of 310 DA staff qtrs. KKD Court Divn. under SD M-2313 Karkardooma Delhi dg. 2021 22 | 2022.02.07 | 2023.02.06 | 63.52 | 48.72 (Feb'23) | 0.00 (Mar'24) | JAI KALKA CONSTRUCTION COMPANY |
Detail Report
Graph / Photo |
|
56 | Supply, installation, testing and commissioning of Router at Rouse Avenue District Court Complex, DDU Marg, New Delhi. | 2023.06.01 | 2023.08.29 | 63.36 | 0.00 (Mar'24) | TRACOM ENTERPRISES | Work in progress |
Detail Report
Graph / Photo |
|
57 | Comprehensive maintenance, Supply of material and providing services of manpower for day to day maintenance work of lawyer’s chamber blocks (ie. D,E,F,G& H- Blocks) Under SubDivision M-2311, KKD Court, PWD, Delhi | 2022.01.22 | 2023.01.21 | 62.58 | 78.03 (Jun'23) | 0.00 (Jan'24) | JAI KALKA CONSTRUCTION COMPANY |
Detail Report
Graph / Photo |
|
58 | Providing of EI AC RO Water Cooler EPABX system and Fire Alarm System work including CIVIL works | 2021.12.19 | 2022.02.18 | 59.70 | 3.69 (Jul'23) | 0.00 (Jul'23) | V. S. ENTERPRISES |
Detail Report
Graph / Photo |
|
59 | Making casting of factory made modular cupboard with fire retardant and boiling water proof Boilo Board in Alhmad rooms of C Block of KKD Court Complex Delhi 2nd Recall | 2022.03.14 | 2022.06.11 | 59.19 | 70.85 (Jan'23) | 0.00 (Sep'23) | Srishti Assosiates |
Detail Report
Graph / Photo |
|
60 | Making casting of factory made modular cupboard with fire retardant and boiling water proof Board in Court rooms North East District of KKD Court Complex Delhi | 2021.11.21 | 2022.02.18 | 54.92 | 26.82 (Apr'23) | 0.00 (Mar'24) | Millennium Furniture |
Detail Report
Graph / Photo |
|
61 | Construction of shed for Gate No. 1, 2 and 3 at District Court Complex, Saket, New Delhi. | 2023.03.17 | 2023.06.16 | 51.74 | IZHAR AHMED |
Detail Report
Graph / Photo |
|||
62 | Construction of 100 Bedded Portable Hospital reserved for Covid 19 at A and U Tibbia College and Hospital, Karol Bagh, New Delhi (Electrical Works) | 2021.12.28 | 2022.02.20 | 51.44 | 52.14 (May'22) | 0.00 (May'22) | Jain Electric Works |
Detail Report
Graph / Photo |
|
63 | Construction of Lift well including civil work in Utility block from Basement to Top floor at District Court Complex, Saket, New Delhi-110017 Civil + Electrical Work. | 2023.04.07 | 2023.06.06 | 51.11 | Anand Electricals | Work in Progress 5% |
Detail Report
Graph / Photo |
||
64 | Replacement of Carpets in Courts of A block Extension block and wooden texture laminated flooring in Chambers of Extension block at Delhi High Court New Delh | 2017.06.27 | 2017.07.26 | 50.20 | Bansal Builder | Agreement closed PG forfeited |
Detail Report
Graph / Photo |
||
65 | False Ceiling, Granite and Wooden Flooring work in court rooms of Shahdara district Karkardooma Court Complex Delhi. Civil and Electrical Work. | 2023.03.16 | 2023.06.13 | 50.09 | 18.00 (Jun'23) | 0.00 (Feb'24) | M.N Construction | In progress |
Detail Report
Graph / Photo |
66 | Waterproofing treatment and Heat resistant tile work at terrace of A, C & I block | 2022.06.08 | 2022.09.05 | 50.04 | 55.78 (May'23) | 0.00 (Jun'24) | M. N. Construction Co. |
Detail Report
Graph / Photo |
|
67 | Provision for 1. Construction of front side boundary wall near main gate 2. Complete renovation of toilet blocks of old Building at Sarvodaya (Co-ed) Vidyalaya, Masjid Moth, New Delhi. (School ID: 1925246, Building ID: 19251141 & EOR ID: 20211430. | 2023.09.06 | 2024.02.05 | 49.74 | 0.00 (May'24) | Shamshad Ahmad |
Detail Report
Graph / Photo |
||
68 | Construction of new academic block (G+3) with future extention of one floor at Lakshmi Bai College, Ashok Vihar, Delhi. (SH:- SITC of Audio Video System for Classrooms, Labs and Conference Room). | 2024.02.13 | 2024.04.12 | 48.65 | 0.00 (Aug'24) | R J P ENTERPRISE |
Detail Report
Graph / Photo |
||
69 | A/A to Karkardooma Court Complex at Vishwas Nagar ,Shahdara Delhi During 2023- 24.(Renovation /Replacement of PTMT fittings into CP brass fittings in toilets at KKD Courts ,Delhi.) | 2024.05.11 | 2024.11.07 | 48.45 | 0.00 (Aug'24) | Uma Shankar |
Detail Report
Graph / Photo |
||
70 | Providing and fixing three seater stainless steel bench at ACI Block, Karkardooma Court Complex, Delhi | 2022.02.26 | 2022.03.27 | 48.15 | 0.00 (Oct'23) | GEEKEN SEATING COLLECTION PVT LTD |
Detail Report
Graph / Photo |
||
71 | Improvement of the existing bituminous road with granite stone block toward dedicated area from gate no. 1 to DJ parking toward C-Block and upto first face of B-Block toward gate no.1 and Renovation of corridor of court no-1 3rd floor C-Block KKD Court, Delhi | 2022.06.25 | 2022.08.23 | 47.61 | 55.48 (May'23) | 0.00 (Jan'24) | Manish Construction |
Detail Report
Graph / Photo |
|
72 | A R and M O Jagpravesh Chandra Hospital, Shastri Park, Lal Bahadur Shastri Hospital, Khichripur, Chacha Nehru Bal Chikitsalaya, Geeta Colony, Dr. Hedgewar Arogya Sansthan, Karkardooma, Aam Admi Polyclinic, Kanti Nagar an Delhi Govt. Dispensaries .... | 2019.08.19 | 2020.08.18 | 45.47 | Royal Construction | p |
Detail Report
Graph / Photo |
||
73 | Improvement and renovation works in 06 Nos. Type III/IV Quarters. | 2023.08.06 | 2023.11.05 | 43.58 | 0.00 (Jan'24) | Nasimuddin |
Detail Report
Graph / Photo |
||
74 | SITC of Building Management System | 2020.09.12 | 2021.03.11 | 43.49 | Digital Controls & Automation | Letter for final action under clause 3 given to working agency vide No. 23(32/7) /HEED(B-141)/ PWD/2024/ 475 dated 18.06.24 |
Detail Report
Graph / Photo |
||
75 | Construction of Oxygen Generator plant Hall at GIPMER, New Delhi. (Electrical works) | 2021.12.06 | 2022.01.19 | 43.31 | 0.11 (Jul'22) | 0.00 (Jul'22) | Jain Electric Works |
Detail Report
Graph / Photo |
|
76 | P/F Vitrified tile flooring, false ceiling, wall paneling and IRC Fabric, Construction of underground R.C.C water tank, installation of 01 no. Borewell and other miscellaneous works at DSEU, Vivek Vihar, Delhi dg. 2022-23). (Civil & Electrical Works). | 2022.06.13 | 2022.09.10 | 41.34 | 51.67 (Jun'23) | 0.00 (Jun'24) | Uma Shankar |
Detail Report
Graph / Photo |
|
77 | Strengthening of damaged slabs, chhajjas, replacement of damaged floor/wall tile, fixing doors & fittings incupboard, replacement of damaged doors, structural glazing in staircase area and painting/finishing work & renovation of E.I. & fans. (Civil & Electrical Works) | 2022.07.29 | 2022.09.11 | 41.32 | 40.40 (Mar'23) | 0.00 (Oct'23) | Engineers India Construction Co. |
Detail Report
Graph / Photo |
|
78 | Renovation of toilet blocks at post office and ATM side in Lawyers Chamber Block-I, Delhi High Court, New Delhi. | 2023.07.11 | 2023.10.08 | 41.13 | 0.00 (Mar'24) | SHREE PAL SINGH | Work in progress |
Detail Report
Graph / Photo |
|
79 | Toilets renovation works | 2021.07.09 | 2021.10.06 | 40.06 | 49.76 (Jan'23) | 0.00 (Jan'23) | Saeed Builders | In progress. |
Detail Report
Graph / Photo |
80 | Up gradation of Type V Judges flats No 402 Type IV Judges flats No 205 Type VI Judge s flats No 607 and Servant Qtrs. 402 607 and 102 at Karkardooma Court Complex Delhi Civil and Electrical Works | 2023.01.01 | 2023.03.31 | 38.79 | 0.00 (Jun'24) | Uma Shankar | In progress. |
Detail Report
Graph / Photo |
|
81 | Strengthening of damaged slabs, chhajjas, replacement of damaged floor/wall tile, fixing doors & fittings in cupboard, replacement of damaged doors, structural glazing in staircase area and painting/finishing work & renovation of E.I. & fans. (Civil & Electrical Works) | 2022.07.29 | 2022.09.11 | 35.17 | 34.64 (Apr'23) | 0.00 (Oct'23) | Engineers India Construction Co. |
Detail Report
Graph / Photo |
|
82 | CO of Toilet for primary wing support staff visitor and attached toilet to principal room renovation of water tank platform and toilet repairing of b wall and other misc civil works | 2020.08.15 | 2020.12.14 | 34.45 | 80.00 % (Dec'20) | CSM CONSTRUCTION |
Detail Report
Graph / Photo |
||
83 | Providing Roof mounted Solar Plant of capacity 19 kwp and VRV/VRF Air Conditioning system at DIET, Ghumanhera. (SH : VRV/VRF system). | 2023.11.18 | 2024.01.17 | 34.29 | 0.00 (Mar'24) | RefAir India Pvt. Ltd. |
Detail Report
Graph / Photo |
||
84 | Providing smoke extraction system from Ground floor to 4th floor for common corridors at Forensic Science Laboratory Building, Sector 14,Rohini, Delhi 110085. | 2023.11.28 | 2024.02.01 | 34.23 | R J P ENTERPRISE |
Detail Report
Graph / Photo |
|||
85 | Construction of Casualty Block at Lal Bahadur Shastri Hospital, Khichripur, Delhi. Sub Head Providing ductable type air conditioning system | 2019.07.09 | 2019.10.08 | 33.85 | 14.13 (Oct'22) | 0.00 (Oct'22) | SKYLINE AIRCONDITIONING ENGINEERS PVT.LTD. | work in Progress 6th RA 18182135 |
Detail Report
Graph / Photo |
86 | Providing, installation, testing, and commissioning of Code Blue System (NCS) for Old and New block at MAIDS, New Delhi | 2019.08.11 | 2019.11.10 | 33.77 | 19.85 (Mar'23) | 0.00 (Mar'23) | Med Freshe Pvt. Ltd. | Work in progress Med Freshe Pvt. Ltd. |
Detail Report
Graph / Photo |
87 | Providing Ongrid Solar Power Plant in Fir Station Sec-5, Rohini, Delhi. | 2023.12.21 | 2024.01.20 | 33.64 | 0.00 (Mar'24) | Yogesh Kumar Tyagi |
Detail Report
Graph / Photo |
||
88 | Construction of porta cabins Legal Aid Defence Counsel System office near facilitation centre for Legal Aid Defence Counsel System office Karkardooma Court Delhi. Civil Furniture and Electrical Works 2nd recall | 2022.08.31 | 2022.09.29 | 33.23 | 0.25 (Mar'23) | 0.00 (Mar'23) | MUZAMMIL ALI |
Detail Report
Graph / Photo |
|
89 | Construction of SAKHI- ONE STEP CENTRE at campus of GBSSS, Malviya Nagar, New Delhi. (Civil and Electrical Works) | 2021.12.16 | 2022.04.15 | 32.92 | 29.75 (Jan'23) | 0.00 (Mar'24) | AKSHAY KUMAR DAGAR | Work in Progress 80% |
Detail Report
Graph / Photo |
90 | Strengthening of damaged beams columns slabs during 2021 22 at SKV No 1 Mansarovar Park Shahdara Delhi 32 School ID 11061655 (Balance work) | 2022.04.05 | 2022.07.03 | 32.79 | 30.24 (Nov'22) | 0.00 (Aug'24) | Cembond Construction Pvt. Ltd |
Detail Report
Graph / Photo |
|
91 | C O Police Housing Complex at Mandoli Delhi. (SH Annual Comprehensive Maintenance Contract of Johnson Make lift installed at Police Housing Complex, Mandoli Delhi) | 2023.01.14 | 2024.01.13 | 32.49 | Invalid | Work in progress |
Detail Report
Graph / Photo |
||
92 | SITC of additional CCTV and allied equipment at GTB Hospital, Shahdara, Delhi | 2018.10.16 | 2018.12.15 | 30.64 | 15.29 (Feb'19) | 50.00 % (Feb'19) | San Infotech Services | work in progress 2nd RA 1696099 |
Detail Report
Graph / Photo |
93 | Supplying, Installation, Testing & Commissioning of high mast poles with Suitable LED fittings & fabrication of LT panel at FU-Block, Sports Complex, Pitampura, Delhi. | 2024.03.13 | 2024.06.12 | 30.19 | SUDHIR KUMAR |
Detail Report
Graph / Photo |
|||
94 | Strengthening work in various buildings M N O block in Judges Residential Complex at KKD Court Shahdara Delhi dg 2021 22 | 2021.12.17 | 2022.04.15 | 29.81 | 28.23 (Feb'23) | 0.00 (Aug'24) | Cembond Construction Pvt. Ltd | In Progress. |
Detail Report
Graph / Photo |
95 | Improvement / Up-gradation of defective /outdated of 2 nos. old lift into 2 nos. New Lifts along with EI works for foot over Bridge at Punjab Kesari, New Wazirpur Depot, Ring Road, Delhi | 2024.04.10 | 2024.07.09 | 28.19 | Techno Industries Pvt Ltd |
Detail Report
Graph / Photo |
|||
96 | Making Accessible approach. Balance Work 1st recall | 2022.09.24 | 2022.12.22 | 27.32 | 20.23 (Apr'23) | 0.00 (Feb'24) | Shobhit Kumar |
Detail Report
Graph / Photo |
|
97 | C/o Sheds at various places and other miscellaneous requisite works by Jail authority in Prison Complex Mandoli, Delhi110093. (SH: C/o shed at Gate No.1, Gate No.2, Gate No.3, Admin gate & Gate in front of CJ-14, CPRO, Canteen etc. and other miscellaneous works). | 2024.06.09 | 2024.09.09 | 26.96 | NM Construction Co. |
Detail Report
Graph / Photo |
|||
98 | Renovation of court no 51 & 53 B-Block at Karkardooma Court, Delhi | 2022.06.13 | 2022.08.11 | 26.85 | 27.90 (Jul'23) | 0.00 (Jun'24) | Uma Shankar |
Detail Report
Graph / Photo |
|
99 | Civil work, false ceiling, flooring and finishing work at Multilevel Car parking in Delhi High Court, New Delhi. | 2023.03.12 | 2023.06.10 | 25.91 | 0.00 (Nov'23) | Yameen | Work in progress |
Detail Report
Graph / Photo |
|
100 | Construction of 01 Nos. Clinical care centre under School Health Scheme on the vacant piece of land between Babu Ram Govt. SBV Bhola Nath Nagar and DIET Shahdara. (Civil, Furniture & Electrical Works). (4th Recall) | 2022.09.16 | 2022.11.14 | 25.77 | 30.48 (Feb'23) | 0.00 (Nov'23) | SUDHIR KUMAR SHARMA |
Detail Report
Graph / Photo |
|
101 | Renovation of electrical installation for lab no. 403 and 403 A at 4th floor of Forensic Science Laboratory, Rohini, Delhi | 2023.04.13 | 2023.07.02 | 25.26 | R J P ENTERPRISE | work in progress |
Detail Report
Graph / Photo |
||
102 | Repair and renovation of Veterinary Dispensary, Bankner, Animal Husbandry Unit of GNCT of Delhi-110040 | 2022.08.01 | 2022.10.30 | 24.62 | 31.73 (Jul'23) | 0.00 (Aug'24) | Ankur Bhardwaj | Work in Progress |
Detail Report
Graph / Photo |
103 | A/A to Karkardooma Court dg 2023-24 (SH: Renovation of Conference Hall at 3rd Floor at Karkardooma Court, Delhi) (Civil work). | 2024.05.19 | 2024.07.17 | 24.56 | 0.00 (Aug'24) | Mohd Azam |
Detail Report
Graph / Photo |
||
104 | SITC of Lifts. | 2023.02.21 | 2023.05.20 | 23.60 | 0.00 (Nov'23) | Techno Industries Limited | 2nd RA Bill Rs. 2242118/- CV No. 137 dt. 29.11.2023 |
Detail Report
Graph / Photo |
|
105 | EOR to Sports complex SU- Block, Pitampura, Delhi during 2021-2022 (SH: Electrical Works) | 2023.12.24 | 2024.03.23 | 22.48 | 0.00 (Mar'24) | R S ELECTRIC CO. |
Detail Report
Graph / Photo |
||
106 | Construction of some boundary wall after demolition of tilted existing boundary wall behind Principal office & construction of new boundary wall and construction of new stage on ground at Dr. Ambedkar Nagar, Sector-IV, No. 1- SBV (Yogi Arvind), New Delhi. (School ID: 1923005, Building ID: 19231163 & EOR ID: 20221410. | 2023.07.26 | 2023.09.25 | 22.00 | 0.00 (Mar'24) | Vision Construction |
Detail Report
Graph / Photo |
||
107 | Supply and Replacement of Hand rail belt for Escalators installed at New Court Block of Honorable Delhi High Court. | 2024.05.26 | 2024.08.25 | 21.98 | Johnson Lifts Pvt. Ltd. | Work in progress |
Detail Report
Graph / Photo |
||
108 | Strengthening of Judges Residential Complex Buildings M N and O Block at Karkardooma Court Delhi.(Repair of the external plaster) | 2023.08.05 | 2023.09.03 | 21.94 | 0.00 (Mar'24) | Sundriyal Construction - Closed |
Detail Report
Graph / Photo |
||
109 | Re-layering of Damaged Internal Bituminous Roads at Judges Flat including raising of manhole cover, laying of C.C. pavement, paver block & Kerb stone, at Karkardooma Court, Sahadara, Delhi-110032 | 2022.07.15 | 2022.08.13 | 21.86 | JAI KALKA CONSTRUCTION COMPANY |
Detail Report
Graph / Photo |
|||
110 | Renovation of toilet blocks & miscellaneous civil works- Balance work | 2022.06.26 | 2022.09.23 | 21.44 | 6.94 (Mar'23) | 0.00 (May'24) | Sanjeev Kumar |
Detail Report
Graph / Photo |
|
111 | SITC of 08 passengers lift -1 No. and 6 passengers lift -1 No. at Lakshmi Bai College, Ashok Vihar, New Delhi. | 2024.02.19 | 2024.05.18 | 21.39 | 0.00 (Aug'24) | EVAAN ELEVATORS PVT LTD |
Detail Report
Graph / Photo |
||
112 | Providing Tea Coffee vending machine, Air Purifier, Heat Convertor and Air Conditioners in Mediation Centre at District Court Karkardooma Delhi. | 2024.06.14 | 2024.07.13 | 21.29 | ELE MEC ENGINEERING CO | Work in progress |
Detail Report
Graph / Photo |
||
113 | Waterproofing treatment and Heat resistant tile work at terrace of J K and L block and replacement cum repairing of door and window of lift rooms at A C I J and L block Karkardooma Court Complex | 2022.06.08 | 2022.09.05 | 20.86 | 22.91 (May'23) | 0.00 (Aug'24) | Karan Walia |
Detail Report
Graph / Photo |
|
114 | Upgradation of existing analog CCTV system to IP based CCTV system in lockup rooms at District Court Dwarka Sector 10 New Delhi | 2022.04.17 | 2022.07.16 | 20.86 | YASH ENTERPRISES |
Detail Report
Graph / Photo |
|||
115 | A/R & M/O to AIT College Shakarpur Delhi dg 2023-24 (SH:- Addition and Alteration of Sub Division Office | 2023.10.20 | 2023.12.19 | 20.34 | 0.00 (Mar'24) | rajeev kumar |
Detail Report
Graph / Photo |
||
116 | Replacing tiles into cement concrete flooring and replacing old rusted grills, IRC fabrics in 13 kharjas, connection of drinking water, raising ramp from the gallery to kharjas, Porta cabin for computer operators in KKD Lockup, Delhi dg. 2023-24. | 2024.05.19 | 2024.07.17 | 19.97 | 0.00 (Aug'24) | Ikram Ali |
Detail Report
Graph / Photo |
||
117 | Repair Renovation of Gents Ladies Staff toilet general girls toilet and CWSN toilet block at Sarvodaya Kanya Vidyalaya Prahladpur Banger Delhi (School ID 1310032) | 2022.10.21 | 2022.12.05 | 19.90 | 0.00 (Feb'24) | M/s R M constrution | Work in progress |
Detail Report
Graph / Photo |
|
118 | Providing AC, Fan, Light Fitting, rewiring in Govt. Co-ed. SSS, Sec15, Rohini, Delhi. | 2023.08.19 | 2023.09.18 | 19.57 | 0.00 (Mar'24) | Kuldeep Traders | First RA Bill Rs. 1092671/- CV no. 17 dt. 12.10.2023 |
Detail Report
Graph / Photo |
|
119 | Operation and maintenance of compost machines installed in various jail at Prison Complex Mandoli Delhi (4th Call) | 2022.09.26 | 2023.09.25 | 19.02 | 10.89 (Jun'23) | 0.00 (Mar'24) | Clean India Ventures Pvt. Ltd. | Work is in progress |
Detail Report
Graph / Photo |
120 | SITC of CCTV in various Mohalla Clinic under sub division M3513 | 2022.04.13 | 2022.05.12 | 18.93 | YASH ENTERPRISES | 100% Work Completed |
Detail Report
Graph / Photo |
||
121 | Provision of chequrred tiles, raising of boundary wall and other misc civil work | 2022.06.26 | 2022.07.25 | 18.67 | 21.25 (Dec'22) | 0.00 (Dec'23) | Sanjeev Kumar |
Detail Report
Graph / Photo |
|
122 | SITC of VRV/ VRF Air Condition Plant | 2022.06.12 | 2022.07.11 | 18.55 | 12.64 (Sep'22) | 0.00 (Dec'23) | Airtemp Engineers | 100% Work Completed |
Detail Report
Graph / Photo |
123 | C/o recreation hall at PTS Wazirabad Delhi. (SH- Providing Electrical Installation) | 2019.02.12 | 2019.06.11 | 18.22 | S K Engineers |
Detail Report
Graph / Photo |
|||
124 | Renovation of toilets gutter fixing and barricading work. 1st recall | 2022.08.21 | 2022.12.18 | 18.07 | 0.24 (Mar'23) | 0.00 (Jun'24) | MOHAMMAD HUSSAIN |
Detail Report
Graph / Photo |
|
125 | Renovation of Ladies Bar Association Room at KKD Courts Delhi. Civil Furniture and Electrical Works 1st recall. | 2023.02.12 | 2023.03.28 | 18.05 | 6.15 (May'23) | 0.00 (Dec'23) |
Detail Report
Graph / Photo |
||
126 | Replacing of damaged G.S sheets with G.I profile sheets. (1st recall) | 2022.04.01 | 2022.06.29 | 17.32 | 19.11 (Dec'22) | 0.00 (Dec'22) | SABUR ALAM |
Detail Report
Graph / Photo |
|
127 | Construction of Godown for Horticulture Deptt. at Nursery and Store Room at Fire Station near Delhi Secretariat, Delhi. | 2023.02.06 | 2023.04.05 | 17.18 | RAJU | work in progress. 90% work has been done. |
Detail Report
Graph / Photo |
||
128 | Providing and Installation of Pump sets in newly constructed pump house in Road No. 320, Shalimar Bagh, Delhi. | 2024.03.26 | 2024.04.25 | 17.17 | 0.00 (Aug'24) | ASHISH SINGH |
Detail Report
Graph / Photo |
||
129 | Construction of Crèche in IGDTUW Campus, Kashmere Gate, Delhi. | 2023.03.09 | 2023.05.08 | 17.10 | KAMAAL CONSTRUCTION CO. |
Detail Report
Graph / Photo |
|||
130 | A/R & M/O GNEC, New Delhi. dg. 2016-17 (SH: Up-Keeping and maintenance of services of GNEC and providing and service of computer operator, Dak Messenger, plumber, carpenter, mason sewerman etc under HMD (Central) SD-3) | 2017.04.13 | 2017.10.12 | 16.04 | 7.45 (Mar'19) | 46.00 % (Mar'19) | Anup Enterprises |
Detail Report
Graph / Photo |
|
131 | Providing and installation of Audio Visual system in assembly ground with SITC of Public Address system and provision of smart classroom at GBSSS, U Block, Mangolpuri Delhi. (School ID:- 1412009) | 2023.12.27 | 2024.02.26 | 15.70 | 0.00 (Aug'24) | Dynamic Systems |
Detail Report
Graph / Photo |
||
132 | SITC of CCTV Cameras at Place of Safety, Majnu Ka Tila, Delhi | 2022.04.13 | 2022.05.12 | 15.40 | 15.10 (May'23) | 0.00 (May'23) | YASH ENTERPRISES | 100% Work Completed |
Detail Report
Graph / Photo |
133 | Construction of Rain Water Harvesting Pit inside ITI Campus and ITI Staff Quarter, Vivek Vihar, Delhi. | 2022.07.15 | 2022.10.12 | 15.37 | 0.00 (Jun'24) | Shivam Builders |
Detail Report
Graph / Photo |
||
134 | SH- Kota stone flooring, repair to boundary wall including grit plaster and concertina wire fencing, repair and maintenance of toilets, P F steel windows, renewing broken glass panes with polycarbonate sheet etc. | 2018.11.07 | 2019.02.04 | 15.26 | 17.61 (Apr'22) | 0.00 (Jul'23) | MOHAMMAD HUSSAIN | in progress. |
Detail Report
Graph / Photo |
135 | Annual comprehensive maintenance of existing Air conditioner and Replacement of fans, fittings, security lights , Distribution Boards along with allied switchgears at Laxmi Bai college, Ashok vihar, Delhi. | 2023.09.14 | 2024.09.13 | 15.18 | 0.00 (Dec'23) | SUDHIR KUMAR | First RA Bill Rs. 794141/- CV No. 11 dt. 15.12.2023 |
Detail Report
Graph / Photo |
|
136 | Accessibility works | 2022.08.06 | 2022.10.04 | 15.09 | 12.07 (Nov'22) | 0.00 (Jul'24) | M T Builders | In Progress. |
Detail Report
Graph / Photo |
137 | SITC of 6 passengers Hydraulic lift in Admin Block basement 1 to basement 2 at District Court Sector 10 Dwarka New Delhi | 2022.08.01 | 2022.10.30 | 14.92 | 0.00 (Aug'23) | Techno Industries Pvt Ltd |
Detail Report
Graph / Photo |
||
138 | Providing tactile pathway to Resource centre Separate stainless Steel main gate Providing and placing water storage tanks Distempering painting and finishing work and misc civil work | 2022.05.29 | 2022.08.26 | 14.87 | 18.56 (Dec'22) | 0.00 (Oct'23) | Sushil Kumar | Work not started by agency due to rain |
Detail Report
Graph / Photo |
139 | Renovation of O o Legal Aid Defence Counsel at Karkardooma Court, Delhi. (SH Electrical Works) | 2024.06.01 | 2024.06.30 | 14.43 | SHANWAJ | Work in progress |
Detail Report
Graph / Photo |
||
140 | Aluminium Works at Delhi Secretariat | 2022.07.01 | 2023.03.31 | 14.14 | 9.04 (Feb'23) | 0.00 (Oct'23) | Nasimuddin |
Detail Report
Graph / Photo |
|
141 | EOR to Govt. Sarvodaya Kanya Vidyalaya a S.P. Road, Nangloi, New Delhi. SH Providing new gate for main entrance, near activity room, providing and fixing grill in front of primary section providing shed for water through near primary section | 2018.04.02 | 2030.09.15 | 13.58 | L V Enterprises |
Detail Report
Graph / Photo |
|||
142 | Expansion of 8 no. Vulnerable Witness Courts at 5th and 6th floor, B-Block KKD Courts Delhi including Audio-Video System and other electrical installations. (Furniture work) | 2022.05.19 | 2022.06.17 | 13.23 | 19.43 (Dec'22) | 0.00 (Dec'22) | Jain Electric Works |
Detail Report
Graph / Photo |
|
143 | Setting up of Dining Hall at HLTB Complex, Tahirpur, Delhi under KKD Court Divn.. M-231 dg. 18-19. | 2019.02.10 | 2019.05.10 | 12.52 | 13.79 (Jan'20) | 0.00 (Jan'20) | Daya Sagar Sharma | work in progress |
Detail Report
Graph / Photo |
144 | Repair and AMC of Audio and PA system installed at SKV Sec-1 Avantika, School, Rohini, Delhi. | 2023.12.13 | 2024.12.12 | 12.17 | 0.00 (Aug'24) | CELTO ACOUSTIQUE LLP |
Detail Report
Graph / Photo |
||
145 | Construction of temporary shed at Community hall Welcome Delhi (Civil and Electrical work) | 2022.02.02 | 2022.03.03 | 12.04 | 0.12 (Mar'23) | 0.00 (Mar'23) | Sanjeev Kumar | In progress. |
Detail Report
Graph / Photo |
146 | Supplying, installation, testing and commissioning of fire fighting accessories and replacement of worn out/rusted accessories at Nav Kiran, Halfway/Longstay Home, Sector-03, Rohini, Delhi drg. 2023-24 | 2024.04.01 | 2024.04.30 | 12.01 | Kuldeep Traders |
Detail Report
Graph / Photo |
|||
147 | Providing new stainless steel gate at entry, internal painting of building, P/F signage board, wooden flooring and wall panelling in principal & conference room & misc. civil works in DIET, J & K pocket, Dilshad Garden, Delhi | 2021.12.26 | 2022.02.23 | 11.65 | 11.10 (Feb'23) | 0.00 (May'24) | Sanjeev Kumar | In progress. |
Detail Report
Graph / Photo |
148 | Providing Fans, Light Fitting, Water Cooler at SKV, Sector-1, Avantika, Rohini, Delhi. | 2023.07.11 | 2023.09.10 | 11.63 | 0.00 (Mar'24) | Adhiraj Construction |
Detail Report
Graph / Photo |
||
149 | Civil Work. | 2023.02.12 | 2023.05.12 | 11.21 | 12.63 (Apr'23) | 0.00 (Jan'24) | MOHAMMAD HUSSAIN | In Progress. |
Detail Report
Graph / Photo |
150 | Civil Electrical Works | 2021.12.10 | 2022.02.07 | 11.21 | 11.94 (Oct'22) | 0.00 (Oct'22) | Rainbow Constructions | In Progress. |
Detail Report
Graph / Photo |
151 | Providing and fixing down comer and manually operated electronic FA system | 2019.09.19 | 2019.10.18 | 11.18 | 0.00 (Mar'19) | 98.00 % (Jan'21) | M/s Royale Meridian India Pvt Ltd | Work completed. Final bill yet to be submitted by the agency. |
Detail Report
Graph / Photo |
152 | Replacement of Defective Burnt-out Air-Conditioning installed in Court Block at District Court Karkardooma Delhi. | 2024.04.10 | 2024.05.09 | 11.16 | 0.00 (Aug'24) | NAJ REFRIGERATION & AIR CONDITIONING WORKS | Work in Progress |
Detail Report
Graph / Photo |
|
153 | Repair and replacement of defective accessories of Addressable Fire Alarm System & Down comer Fire fighting system at Mangol Puri, ITI New Delhi. | 2023.04.27 | 2023.06.24 | 11.11 | 0.00 (Mar'24) | R J P ENTERPRISE |
Detail Report
Graph / Photo |
||
154 | Renovation of toilet blocks at G/F (02 nos.), F/F (02 nos.) & S/F (01 no.) | 2022.10.05 | 2022.12.03 | 10.79 | 0.00 (Jul'24) | MOHAMMAD HUSSAIN |
Detail Report
Graph / Photo |
||
155 | Miscellaneous Civil works | 2022.05.10 | 2022.07.08 | 10.73 | 8.62 (Jun'23) | 0.00 (May'24) | MOHAMMAD HUSSAIN |
Detail Report
Graph / Photo |
|
156 | Renovation of staff room toilets and pantry and other misc civil work in Chemistry Lab at Vivekanand College Vivek Vihar Delhi | 2022.05.29 | 2022.06.27 | 10.53 | 12.79 (Oct'22) | 0.00 (Aug'23) | Sundriyal Construction - Closed |
Detail Report
Graph / Photo |
|
157 | ARMO Various Electrical Installations and Mechanical Equipments at FSL, Madhuban Chowk, Sec-14, Rohini, Delhi (SH : AMC of Johnson Make Lifts) | 2024.03.01 | 2025.02.28 | 10.48 | Johnson Lifts Pvt. Ltd. |
Detail Report
Graph / Photo |
|||
158 | C/o of Two Nos. of Toilet(One for Handicapped and Other for Transgender) and Water Proofing Treatment of Roof at DDMA and Block-C, P/F Kota stone Slab flooring with Granite strip in front of A block etc at the O/o the D.M(East) dg 2022-23 (Balance work) | 2022.08.15 | 2022.11.14 | 10.47 | Aamir Khan |
Detail Report
Graph / Photo |
|||
159 | Upgradation of Type-II, Type-III and Type-IV Flat No. B-415, 97, 80, 118, 149, 407 ,168, 234, 309, 303, 330, 485, 469, 621, 497, 605 ,85, 387, 33 etc. C-734, 741, 756 etc, D-21, D-7, D-30 DA Flats Timarpur Delhi-- Electrical Work, EI and Fans | 2022.02.28 | 2022.08.27 | 10.14 | 0.00 (Mar'24) | Dashmesh Enterprises | 100% Work Completed |
Detail Report
Graph / Photo |
|
160 | A/A to Karkardooma Court dg. 2023-24.(Miscellaneous Civil Work at Mediation Centre, KKD Court, Delhi.) | 2024.04.26 | 2024.06.24 | 9.13 | 0.00 (Aug'24) | M N Construction Co. |
Detail Report
Graph / Photo |
||
161 | Installation of LED Boards at Entry Gate 1, 1A and 2 and on the roof of Main Building, Tis Hazari Court Complex, Delhi. | 2024.02.10 | 2024.04.09 | 9.07 | MOHD AMJAD | work in progress |
Detail Report
Graph / Photo |
||
162 | Supplying, Installation, Testing and Commissioning of oil filled heat radiators for chambers of Ld. Judicial Officers at various locations in District Court Complex, Sector-14, Rohini, Delhi-110085 | 2024.01.08 | 2024.02.07 | 8.04 | 0.00 (Mar'24) | Lokesh Garg |
Detail Report
Graph / Photo |
||
163 | Wall paneling wooden flooring and toilet renovation work Civil and Electrical works | 2022.06.11 | 2022.07.10 | 7.36 | 0.25 (Mar'23) | 0.00 (Mar'23) | JAI KALKA CONSTRUCTION COMPANY |
Detail Report
Graph / Photo |
|
164 | Construction of 10 Nos. Room for faculty of Anesthesia with gypsum partition at 4th floor, B.L. Taneja Block at MAMC New Delhi | 2022.09.12 | 2022.11.11 | 7.11 | 8.76 (Feb'23) | 0.00 (Feb'23) | M/s Bajrang Electrical (India) | Work in progress |
Detail Report
Graph / Photo |
165 | Providing of Queue Management System and Calling bell Console system at Delhi Mediation Center, Karkadooma Courts Delhi. 33/EE(E)/JED-1/PWD/2023-24 | 2024.04.01 | 2024.05.30 | 6.93 | J R CONSULTANT & ENGINEERS | Work in progress |
Detail Report
Graph / Photo |
||
166 | Replacement of damaged hospital signage boards in various locations at Sanjay Gandhi Memorial Hospital, Mangolpuri Delhi | 2022.11.16 | 2022.12.15 | 6.66 | 0.00 (Mar'24) | M/s Rudraksh Associated |
Detail Report
Graph / Photo |
||
167 | Construction of underground water storage tanks for upcoming Court Rooms with additional storage facility for existing Court Complex and Residential Complex Saket including upgrading of existing water main line feeding Residential Court Complex--- | 2023.02.03 | 2023.03.02 | 6.57 | 0.00 (Mar'24) | ARSHAD |
Detail Report
Graph / Photo |
||
168 | Sweeping of road, development of rain water harvesting system, CO sump tank and other misc repair works | 2022.08.04 | 2023.05.10 | 6.41 | 4.94 (Mar'23) | 0.00 (Sep'23) | Invalid | Work in Progress |
Detail Report
Graph / Photo |
169 | Construction of tin shed near main gate and provision for sitting. | 2023.06.28 | 2023.08.11 | 6.28 | N.M. Construction Co. | WORK YET TO STARTED. |
Detail Report
Graph / Photo |
||
170 | Replacement of wooden sofa chair with new visitor chairs at I/C E.D. Lockup and miscellaneous furniture work at courts of Shahdara District Branch, KKD Court Delhi | 2022.07.09 | 2022.08.07 | 6.07 | 7.32 (Jan'23) | 0.00 (Jan'23) | Ganpati Furniture System Pvt Ltd |
Detail Report
Graph / Photo |
|
171 | ARMO various Electrical and Mechanical services (Internal & External) in Keshav Maha Vidyalaya at Pitampura, Delhi during 2023-24. (SH: Replacement of old electrical tube fittings with LED based luminaries & necessary EI work alongwith provision of glow signage board etc.) | 2023.12.04 | 2024.01.03 | 5.95 | 0.00 (Mar'24) | BAJRANG ELECTRICAL (INDIA) |
Detail Report
Graph / Photo |
||
172 | Construction of 500 LPM PSA Plant for Covid- 19 at A U Tibbia College Hospital, Karol Bagh, New Delhi. (Electrical Works) | 2021.11.11 | 2022.01.10 | 5.94 | Shyam Electricals & Engineers |
Detail Report
Graph / Photo |
|||
173 | SITC of ventilation fans in various wards at CJ-10, Rohini, Delhi dg.2023-24 | 2023.12.25 | 2024.01.24 | 5.77 | 0.00 (Feb'24) | R J P ENTERPRISE |
Detail Report
Graph / Photo |
||
174 | Electrical work. | 2023.07.04 | 2023.09.03 | 5.68 | RAJA ELECTRICAL ENGINEERING WORKS |
Detail Report
Graph / Photo |
|||
175 | Tentage & sitting arrangement | 2022.07.30 | 2022.08.09 | 5.68 | 6.37 (Mar'23) | 0.00 (Dec'23) | Vishal Tents and Decorators | work in progress |
Detail Report
Graph / Photo |
176 | Providing and fixing dustbin at Karkardooma Court Complex, Delhi | 2022.06.13 | 2022.07.12 | 5.66 | 77.43 (Mar'23) | 0.00 (Mar'23) | JAI KALKA CONSTRUCTION COMPANY |
Detail Report
Graph / Photo |
|
177 | A/A to Karkardooma Court Complex dg. 2023-24 (SH : Making office of Legal Office Aid Defense Council at KKD Court, Delhi (Civil work). | 2024.04.26 | 2024.05.25 | 5.54 | 0.00 (Jun'24) | PANKAJ SINGH CHAUHAN |
Detail Report
Graph / Photo |
||
178 | Civil Works | 2022.09.01 | 2022.09.30 | 5.36 | 0.25 (Mar'23) | 0.00 (Mar'23) | JAI KALKA CONSTRUCTION COMPANY |
Detail Report
Graph / Photo |
|
179 | Providing & Installation of 1000 LPH Reverse Osmosis Plant with Water cooler cum Purifier at each floor of main building in GGSSS No. 2, Mubarakpur Dabas, Delhi. (School ID:- 1412253) | 2024.01.22 | 2024.02.21 | 5.29 | 0.00 (May'24) | LAXMI WATER WORLD |
Detail Report
Graph / Photo |
||
180 | SITC of Wireless Access point for extending range of existing Wi-Fi system in all court rooms of Extension Block Tis Hazari Court Complex, Delhi | 2024.02.16 | 2024.03.16 | 5.11 | ARTEK ENTERPRISES | work in process |
Detail Report
Graph / Photo |
||
181 | Renovation of NDMC ESS of Temporary High Court & ESS of A Block (old building) at Delhi High Court, New Delhi. (SH: Electrical Work). | 2024.06.24 | 2024.07.23 | 4.97 | 0.00 (Sep'24) |
Detail Report
Graph / Photo |
|||
182 | Making arrangement for sanitized the Judges residential complex and Lawyers chamber blocks D E F G H preventive measures for Corona Virus COVID 19 in Karkardooma Court Complex Delhi. Sanitization work and providing hand sanitizer | 2022.01.31 | 2022.03.31 | 4.93 | 5.35 (Jun'22) | 0.00 (Jun'22) | PURIFIRES INDIA | In Progress. |
Detail Report
Graph / Photo |
183 | Providing Furnitures at Ladies Bar Association Room at KKD courts, Delhi. | 2023.03.22 | 2023.04.20 | 4.88 | 13.84 (Jun'23) | 0.00 (Jun'24) | Uma Shankar |
Detail Report
Graph / Photo |
|
184 | Major repair work on water supply pipe line tanks. | 2023.02.11 | 2023.04.11 | 4.70 | 7.99 (Jun'23) | 0.00 (Sep'23) | Mohd Azam |
Detail Report
Graph / Photo |
|
185 | Providing and fixing of UPVC Doors and Windows S.S railing Blinds cupboard work. | 2023.05.13 | 2023.06.11 | 4.67 | 0.00 (Mar'24) | Anuj Kumar Singal | In Progress. |
Detail Report
Graph / Photo |
|
186 | Civil Works. 1st Recall | 2023.01.06 | 2023.02.04 | 4.63 | 0.87 (Jun'23) | 0.00 (Dec'23) | Mohd. WAZID |
Detail Report
Graph / Photo |
|
187 | Construction of fire resistant barriers in E and M shafts at Delhi High Court | 2019.09.28 | 2019.10.27 | 4.49 | Naini Electricals |
Detail Report
Graph / Photo |
|||
188 | Renovation of Chamber of Office-in-Charge IT & Digitization Cell at Rouse Avenue Court, New Delhi (SH: E&M Works). | 2023.12.26 | 2024.01.24 | 4.48 | 0.00 (Mar'24) | R. Diamond Enterprises | Work Completed |
Detail Report
Graph / Photo |
|
189 | Urgent Repair of boundary wall of Parking between Gate No 1 and 2 and pump house at GTB Hospital Shahdara Delhi | 2022.11.07 | 2023.01.05 | 4.01 | 0.00 (Jul'23) | Nasir Ali | Work in progress. |
Detail Report
Graph / Photo |
|
190 | C/o SPS Structure (4 storey) for ITI at Bakkarwala, Delhi. (SH: Supplying, installation, testing and commissioning of Water coolers with inbuilt UV System alongwith RO System) | 2020.01.10 | 2020.02.08 | 3.99 | 99.00 % (Jan'21) | A TO Z Engineering Works | Letter written to firm for submission of final bill. |
Detail Report
Graph / Photo |
|
191 | C/o SPS Structure (4 storey) for ITI at Ranhola, Delhi. (SH: Supplying, installation, testing and commissioning of Water coolers with inbuilt UV System alongwith RO System) | 2020.01.10 | 2020.02.08 | 3.99 | 99.00 % (Jan'21) | A TO Z Engineering Works | Letter written to firm for submission of final bill. |
Detail Report
Graph / Photo |
|
192 | Installation of 1 no. borewell at Fire Station Tahirpur Delhi dg. 2022 23. Civil and Electrical Works | 2022.09.21 | 2022.10.20 | 3.93 | 4.37 (Jun'23) | 0.00 (Jun'23) | Lucky Project |
Detail Report
Graph / Photo |
|
193 | RMO of water coolers , Split or Window or Ductable ACs installed at Lawyers block , Utility Block , Lockup building and Main Court Building at District Court Complex saket New delhi -110017. | 2019.02.03 | 2020.02.02 | 3.91 | 17.36 (Jun'23) | 0.00 (Jun'23) | ARORA ELECTRICAL WORKS |
Detail Report
Graph / Photo |
|
194 | Addition and alteration to Indira Gandhi Hospital at Sector-9, Dwarka, New Delhi during 2023-24 (SH: Providing & fixing aluminium partitions with glass in MRD Area at Upper Basement) | 2024.01.30 | 2024.02.28 | 3.67 | JAI KUMAR BHARDWAJ | Work is under progress. |
Detail Report
Graph / Photo |
||
195 | Replacement / repairing of Fire fighting system alongwith accessories at Govt. Sarvodaya Co-ed Vidyalaya, A-Block, Keshavpuram Delhi-110035 (School ID-1411021) | 2024.06.19 | 2024.07.18 | 3.60 | Vivek associates |
Detail Report
Graph / Photo |
|||
196 | Replacement of broken glass and painting of grills of window providing and fixing of signage board and other misc. work at DIET Building Karkardooma Institutional area Delhi 110032 1st Recall | 2022.09.09 | 2022.10.08 | 3.59 | 4.18 (Mar'23) | 0.00 (Jul'24) | JAI KALKA CONSTRUCTION COMPANY |
Detail Report
Graph / Photo |
|
197 | Barricading of dangerous portion of old school building, chipping of unsound/weak concrete & demolishing damaged RCC & brick work in Gandhi Memorial School, Shahdara (Near Shyamlal College), Delhi. (1st recall) | 2022.08.17 | 2022.09.15 | 3.26 | 0.00 (Jul'24) | JAI KALKA CONSTRUCTION COMPANY |
Detail Report
Graph / Photo |
||
198 | Construction of Parking shed in C.B.D. Shahdara Fire Station Building Shahdra under KKD Court Division Delhi dg. 2022 23. 1st Recall | 2023.01.06 | 2023.02.04 | 3.22 | 4.01 (Feb'23) | 0.00 (Sep'23) | Mohd. WAZID |
Detail Report
Graph / Photo |
|
199 | Construction of New Passenger Lift for 13 Persons including connection corridor with existing Building PGC, M-Block, Vikas Bhawan, New Delhi (SH. Electrical Works in Lift Shaft and replacement of existing Light in Connecting Corridors) | 2017.10.17 | 2018.01.16 | 3.14 | Chetan Enterprises |
Detail Report
Graph / Photo |
|||
200 | Construction of Parking shed in C.B.D. Shahdara Fire Station Building Shahdra under KKD Court Division Delhi dg. 2022 23 | 2022.08.26 | 2022.09.24 | 3.06 | 0.25 (Mar'23) | 0.00 (Mar'23) | PRASHANT BUILDERS |
Detail Report
Graph / Photo |
|
201 | 1) RMO various Electrical Installations and Mechanical Equipments at Fire Safety Management Academy, Sector 5 & Sector 16 Fire Station, Rohini, Delhi. 2) ARMO various Electrical Installations and Mechanical Equipments at Forensic Science Laboratory, Madhuban Chowk, Sector-14, Rohini, Delhi. 3) ARMO Various Electrical Installation and Mechanical Equipments of 119 type-III, Residential Quarters for the staff of GNCTD of Delhi at Sector 11, Rohini, Delhi (SH: Servicing of ceiling fan) | 2024.03.27 | 2024.04.26 | 2.73 | R S ELECTRIC CO. |
Detail Report
Graph / Photo |
|||
202 | Renovation work | 2023.01.13 | 2023.02.11 | 2.61 | 0.00 (Dec'23) | Mohd Azam |
Detail Report
Graph / Photo |
||
203 | Renovation of office of Secretary in DSSSB Building at Karkardooma Shahdara Delhi dg 2022 23 | 2022.08.03 | 2022.09.01 | 2.56 | 6.31 (Apr'23) | 0.00 (Apr'23) | Mohd Azam |
Detail Report
Graph / Photo |
|
204 | Installation of Stainless Steel Grill on the window for safety and security of Valuable assets | 2022.06.13 | 2022.07.12 | 2.29 | 2.90 (Apr'23) | 0.00 (Apr'23) | Mohd Azam |
Detail Report
Graph / Photo |
|
205 | Stationing of a Porta Cabin in the premises Multilevel Car parking, Delhi High Court, New Delhi. (SH: - Civil Work) | 2023.09.30 | 2023.10.21 | 2.19 | 0.00 (Sep'24) | IRFAN KHAN AND CO. | Work in progress |
Detail Report
Graph / Photo |
|
206 | Wiring / Rewiring i/c providing fans, fitting, flood light, main electrical panel with Suitable switchgears & Water cooler and Air conditioning for computer lab at Shakupr No. 1 g (Co-ed ) SSS Delhi (SH:- SITC of auto cleaning system for water supply | 2024.06.19 | 2024.07.03 | 2.08 | R.S. Electric Co. |
Detail Report
Graph / Photo |
|||
207 | Replacement of 04 Nos. Air conditioners at Land & Estate Branch Lucknow Road, Old Sectt, Delhi-54 | 2022.06.22 | 2022.07.06 | 2.08 | 2.09 (Aug'22) | 0.00 (Aug'22) | CHETAN SHARMA | 100% Work Completed |
Detail Report
Graph / Photo |
208 | C/o of 3 nos. SPS Room and 2 nos. porta Cabin fro Election office at the office complex of Deputy commissioner (North West ), Kanjhawala, Delhi. (SH:- Ei & Fans fitting and service connection and other allied elecrtic work | 2024.04.01 | 2024.04.05 | 1.92 | SAGAR ASSOCIATES |
Detail Report
Graph / Photo |
|||
209 | SPS type building i/c internal internal & external water supply, sanitary installations, electrical installations, development of site, fire fighting system & providing furniture etc. | 2022.03.25 | 2022.04.23 | 1.90 | MKSC Design India Private Limited | Work in Progress |
Detail Report
Graph / Photo |
||
210 | Construction of 72 Nos. equivalent classrooms (G+3) including internal electrical works sanitary installations, water supply, fire fighting and external development works etc for Govt. Co-ed. Sr. Sec. School at PSP-10, Industrial area Phase-V, Rohini, Kirari, Delhi (Civil and Electrical). (SH: Carrying out structural analysis and preparation of structural drawings)”. | 2022.03.23 | 2022.04.22 | 1.85 | MKSC Design India Private Limited | Work in progress |
Detail Report
Graph / Photo |
||
211 | Provision of New gate and laying C.C path at the entrance of VSKV Old Seemapuri | 2021.09.04 | 2021.10.03 | 1.85 | 0.88 (Mar'22) | 0.00 (Mar'22) | Sanjeev Kumar |
Detail Report
Graph / Photo |
|
212 | Hiring of New Digital Photocopier Machine Model Sharp AR-6020N New Model on Rental basis with ADE Duplex Printer and Scanner | 2021.09.05 | 2023.09.04 | 1.81 | 0.82 (Dec'22) | 0.00 (Dec'22) | Frank Copier Pvt. Ltd. |
Detail Report
Graph / Photo |
|
213 | Supply Installation Testing and Commissioning of Digital Set Top Box in Special Ward at L N Hospital New Delhi due to COVID 19 | 2021.03.18 | 2021.04.01 | 1.70 | DURGA ENTERPRISES |
Detail Report
Graph / Photo |
|||
214 | Electrical Renovation Work of Evening Shift Principal Office at GSKV, Rohini Ext., Sector-20, (Pooth Kalan), Delhi-86 | 2024.03.26 | 2024.04.25 | 1.66 | 0.00 (Aug'24) | R S ELECTRIC CO. |
Detail Report
Graph / Photo |
||
215 | Special Repair of Electrical Installation including replacement of Defective fans, fitting, Street Lights & Security Light at SKV Bharat Nagar, New Delhi. | 2024.03.16 | 2024.03.30 | 1.30 | Decent care solutions | Work in progress |
Detail Report
Graph / Photo |
||
216 | Measuring and Mapping of Veterinary Polyclinic and SPCA building of Shahdara District A.H. Unit. | 2022.06.23 | 2022.07.07 | 0.74 | 0.74 (Sep'22) | 0.00 (Sep'22) | Kesari & Associates |
Detail Report
Graph / Photo |
|
217 | Soil investigation and bearing capacity of soil | 2021.08.19 | 2021.08.28 | 0.50 | Allied Engineers |
Detail Report
Graph / Photo |
|||
218 | C/o of Researcher Block and Residential Staff Quarters for Delhi Institute of Hotel Management and Catering Technology at Lajpat Nagar New Delhi under HSD South-III/HD-South/PWD/New Delhi dg. 2020-21. Transplantation of trees | 2021.04.05 | 2021.05.19 | 0.16 | Om Prakash Sharma BEYPS5726N1ZC |
Detail Report
Graph / Photo |
|||
219 | Repairing of aluminium doors & Shutters. | 2014.08.19 | 2014.09.03 |
Detail Report
Graph / Photo |
|||||
220 | Providing and laying RCC drain cover in open surface drain in basement. | 2014.08.16 | 2014.09.15 | 2.58 (Mar'21) | 0.00 (Mar'21) |
Detail Report
Graph / Photo |
|||
221 | Providing calcium silicate false ceiling & HRD fabrication in opening balcony at second floor. | 2014.09.16 | 2014.10.15 |
Detail Report
Graph / Photo |
|||||
222 | Finishing of exterior wall in 20 nos. CBI flats. | 2014.12.08 | 2014.12.26 | Pradeep Kumar Sharma |
Detail Report
Graph / Photo |
||||
223 | P/F Manhole cover & Drain cover. | 2015.01.08 | 2015.02.07 | M. N. Construction Co. |
Detail Report
Graph / Photo |
||||
224 | Providing Security Guard for watch and ward for Sub Divn. Office & Vacant Flats at Mayur Vihar Ph-II and Division Office. | 2014.08.18 | 2015.01.01 |
Detail Report
Graph / Photo |
|||||
225 | Repair of toilet roof at Rajkiya Sarvodaya Kanya Vidyalaya Kondli Delhi-110091. | 2015.01.08 | 2015.02.04 |
Detail Report
Graph / Photo |
|||||
226 | Providing and fixing PVC doors in bathrooms in qtrs. in place of old damaged ones. | 2014.09.18 | 2014.10.17 |
Detail Report
Graph / Photo |
|||||
227 | Replacement of Damaged roof of Sub Divn. Office M-233. | 2014.11.11 | 2014.12.10 | 35.49 (Aug'21) | 0.00 (Aug'21) |
Detail Report
Graph / Photo |
|||
228 | Cleaning of sewer line, manhole & gully traps etc. | 2014.12.22 | 2015.01.21 |
Detail Report
Graph / Photo |
|||||
229 | Providing and fixing door in toilet at G.G.S.S.S. Vasundhara Enclave Delhi School ID-1002185. | 2015.01.24 | 2015.02.23 | M. N. Construction Co. |
Detail Report
Graph / Photo |
||||
230 | Repair of toilet roof at Rajkiya Sarvodaya Kanya Vidyalaya Kalyan Puri Delhi. | 2015.01.08 | 2015.02.07 | M. N. Construction Co. |
Detail Report
Graph / Photo |
||||
231 | Providing and fixing polycarbonate in available. | 2014.12.19 | 2015.01.18 |
Detail Report
Graph / Photo |
|||||
232 | Misc. work at RSKV Mayur Vihar Ph-1 Pkt-IV. | 2015.01.17 | 2015.02.16 | Pradeep Kumar Sharma |
Detail Report
Graph / Photo |
||||
233 | Providing and fixing Acrylic sheet in windows, kerb stone, painting work and misc. civil work. | 2015.02.08 | 2015.03.08 |
Detail Report
Graph / Photo |
|||||
234 | Repair to damaged windows, renewing glass panes with acrylic plastic sheet & signage work. | 2015.02.06 | 2015.03.15 |
Detail Report
Graph / Photo |
|||||
235 | Water proofing treatment of first floor toilet. | 2014.12.15 | 2015.01.14 |
Detail Report
Graph / Photo |
|||||
236 | Providing and fixing door & window shutters in pooling booth centre at GGSSS Kondli Gharoli. | 2015.02.06 | 2015.02.20 |
Detail Report
Graph / Photo |
|||||
237 | Misc. Civil Works. | 2015.03.16 | 2015.03.30 | Shekhar |
Detail Report
Graph / Photo |
||||
238 | Providing ramps in Schools & miscellenious works. | 2015.02.12 | 2015.02.26 |
Detail Report
Graph / Photo |
|||||
239 | P/F Floor tile & broken tile. | 2015.11.20 | 2015.12.12 |
Detail Report
Graph / Photo |
|||||
240 | Providing and laying cement concrete. | 2015.03.12 | 2015.03.25 | Indal Yadav |
Detail Report
Graph / Photo |
||||
241 | Providing railing for Park. | 2015.11.23 | 2015.12.05 |
Detail Report
Graph / Photo |
|||||
242 | Construction of table top in front of Entry and Exit Gates of Residential Complex, District Court Saket at Birla Vidya Niketan Marg under Subdivision -14/ South Road-1 during 2023-24. | 2023.08.14 | 2023.09.13 | 0.00 (Jul'24) | Work in progress |
Detail Report
Graph / Photo |
|||
243 | EOR to Swami Dayanand Sarvoday Kanya Vidyalaya, Old Rajinder Nagar,New Delhi during 2023-24.(Re-construction of boundary wall of school) (Balance Work) | 2023.09.28 | 2023.11.26 | work in progress |
Detail Report
Graph / Photo |
||||
244 | Development of Sports infrastructure in govt. Co-ed. Senior Secondary School, Najafgarh Dhansa Road, Mitraon Village (ID No.1822178), Najafgarh, Delhi. | 2023.11.09 | 2024.08.14 | 7 |
Detail Report
Graph / Photo |
||||
245 | Barrier free infrastructure of school building. 1. Accessible Route/pathway-Entire corridor should have anti-skid surface, tactile path, ramp (with handrails) and signage. 2. Lift / elevator or ramp on every floor. 3. Accessible staircase – Color contrasting strips on the horizontal surface of the steps. 4. Accessible toilet with handrails and urinals. 5. Accessible drinking water facility – Drinking water taps accessible for person with disability. | 2023.07.07 | 2023.10.06 | WORK IN PROGRESS |
Detail Report
Graph / Photo |
||||
246 | C/o Stage-I of Phase-II, Delhi Technological University at Bawana Road Delhi. (SH: C/o Common Mess Building near to the newly constructed Girls Hostel Building at DTU Campus) | 2023.08.14 | 2024.05.09 | 0.00 (Oct'23) | Work awarded on 14.08.2023. Preparation of Structural drawings & their approval is in progress. |
Detail Report
Graph / Photo |
|||
247 | Drone Videography and photographs to capture vantage view and acreate chronological records for hospitals under HMD(North) | 2024.06.24 | 2025.06.23 | Work in Progress (25% Progress). |
Detail Report
Graph / Photo |
||||
248 | A/R & M/o. to BJRM Hospital Jahangir Puri, Delhi under HMSD-2(N) during 2024-25.(SH: Supply of Water from DJB through Tankers due to acute shortage of water supply) | 2024.07.05 | 2025.07.04 | Work in Progress (8% Progress). |
Detail Report
Graph / Photo |
||||
249 | A/R & M/o. to Maharishi Valmiki Hospital Complex including Residential Quarters and DGD Dispensary at Hirankudna and Jwalapuri, Pooth Khurd, Delhi during 2024-25 (SH: Providing service of workers to attend day to day complaints) | 2024.07.25 | 2024.09.22 | Work in Progress (60% Progress). |
Detail Report
Graph / Photo |
||||
250 | A/R & M/o. to Satyawadi Raja Harish Chandra Hospital Complex including Residential and DGD Dispensary at Bhorgarh and Punjabi Colony, Narela, Delhi during 2024-25 (SH: Providing service of workers to attend day to day complaints) | 2024.07.25 | 2024.09.22 | Work in Progress (58% Progress) |
Detail Report
Graph / Photo |
||||
251 | Consultancy Services for Comprehensive Architectural and Engineering Planning and Designing for Construction of 100 seated Government Veterinary College/Research Institute at Satbari in South Delh. | 2023.09.04 | 2026.12.04 | Work on hold |
Detail Report
Graph / Photo |
||||
252 | Construction of 48 Nos G plus 3 SPS Eq. classroom including 3 staircase 1 lift and 1 toilet block in Mustafabad School Delhi Including internal and external water supply sanitary installations electrical installations development of site Boundary W | 2023.03.09 | 2024.02.01 | 3rd Floor Level beam reinforcement work in progress, brick masonary at GF in progress The site approach is very narrow and no congested working space for material and labour at site. |
Detail Report
Graph / Photo |
||||
253 | Construction of SPS (4-Storey) for additional class rooms at Karampura Campus of Dr. B.R. Ambedkar University, Delhi. | 2023.03.24 | 2023.09.19 | 3.99 (Jan'23) | 0.00 (Jan'23) | 85 |
Detail Report
Graph / Photo |
||
254 | Filling, Carriage and pouring out of drinking and non drinking water into water tank of Burari Hospital complex | 1900.01.12 | 2023.07.11 | Tender is under process |
Detail Report
Graph / Photo |
||||
255 | C/o Residential Hostel at Chhatrasal Stadium Model Town, Delhi. (SH : comprehensive maintenance of PC’s and associated accessories for O/o PM(HEP), PWD and O/o EE(E), B141, PWD.) | 2023.04.20 | 2026.04.19 | Work in progress. |
Detail Report
Graph / Photo |
||||
256 | Cleaning of sewer line, manholes, road gully chambers and storm water drain | 2023.05.30 | 2024.05.30 | 0.00 (Nov'23) | In-progress |
Detail Report
Graph / Photo |
|||
257 | Civil works and Electrical works. | 2023.08.22 | 2024.05.21 | 25.00 % (Apr'24) | Foundation work for boundary wall completed. Plinth Beam casting for administrative block in progress. Foundation work for workshop in progress. |
Detail Report
Graph / Photo |
|||
258 | Beautification of gate water proofing of new building block S S railing and other misc works Balance Work | 2022.09.10 | 2023.01.09 | work in progress. 65% work has been done. |
Detail Report
Graph / Photo |
||||
259 | A/R & M/O to Rouse Avenue Court Complex at DDU Marg, New Delhi During 2022-23 & 2023-24. (SH: Operation and Maintenance of STP Plant of 180 KLD). | 2022.09.30 | 2024.09.29 | 4.59 (Mar'23) | 0.00 (Mar'24) | Work is in progress |
Detail Report
Graph / Photo |
||
260 | Annual Maintenance and Networking of Computers Systems UPS Photocopier machines and Printers of Circle office M 22 Divisional office M 221 and Sub Divisional Office M 22 | 2022.09.30 | 2023.09.29 | work in progress. |
Detail Report
Graph / Photo |
||||
261 | Preventive maintenance for Civil works | 2023.01.20 | 2024.01.19 | 0.00 (Sep'24) | work in progress. 40% work has been done. |
Detail Report
Graph / Photo |
|||
262 | Filling, Carriage and pouring out of drinking and non drinking water into water tank of Dr. BSA Hospital complex | 2022.12.30 | 2023.06.29 | 100.00 % (Jul'23) | work in progress |
Detail Report
Graph / Photo |
|||
263 | Repairing works and water proofing of DGHS Dispensary OLD Seemapuri New Delhi | 2023.01.08 | 2023.02.07 | 0.00 (Sep'23) | Work in progress. |
Detail Report
Graph / Photo |
|||
264 | Renovation of Emergency Lab and Blood Storage room at Jag Pravesh Chandra Hospital, Shastri Park, Delhi | 2023.01.01 | 2023.03.01 | 0.00 (Oct'23) | Work could not be started due to site is not handed over by the client department. |
Detail Report
Graph / Photo |
|||
265 | Laying of sewerline and connecting with main DJB sewerline in SKV Janki Devi | 2022.11.13 | 2022.12.12 | 0.00 (Mar'24) | work in progress and sewerline connection is pending. |
Detail Report
Graph / Photo |
|||
266 | Construction of Spectator Gallery for VIP’s/ Visitors | 2022.12.22 | 2023.03.21 | In-Progress |
Detail Report
Graph / Photo |
||||
267 | Comprehensive maintenance of civil operation relating day by day maintenance, special repair etc. of Burari Hospital, Kaushik Enclave, Burari, Delhi during 2022-23 and 2023-24 | 2022.11.05 | 2024.11.04 | 90.27 (Jun'23) | 0.00 (Jul'24) | work in progress, as per complaint received in sub division, the regular day to day compliance is made. |
Detail Report
Graph / Photo |
||
268 | Construction of SPS (4-Storey) for additional class rooms at Karampura Campus of Dr. B.R. Ambedkar University, Delhi. | 2023.03.24 | 2023.09.19 | 85% |
Detail Report
Graph / Photo |
||||
269 | Providin gand fixing interlocking tiles, polycarbonate sheet and green board in classrooms. | 2016.01.17 | 2016.04.30 | 80.00 % (Jul'16) | polycarbonate |
Detail Report
Graph / Photo |
|||
270 | providing rain water harvesting Pit, laying interlocking paver block in the ground and raising of boundary wall of Govt., Girls Sr. Sec. School. | 2016.05.01 | 2016.06.30 | 0.01 % (Jul'16) | work in progress |
Detail Report
Graph / Photo |
|||
271 | E.O.R. to G.G.S.S.S at C block Dilshad Garden Delhi | 2016.04.10 | 2016.06.09 | 0.01 % (Jul'16) | Estimate re-submitted to SE(N) vide letter No.23(05)/EE(N)/DB/PWD/15-16/ 2270 |
Detail Report
Graph / Photo |
|||
272 | Construction of new boundary wall | 2016.04.24 | 2016.07.20 | 21.77 (May'17) | 100.00 % (May'17) |
Detail Report
Graph / Photo |
|||
273 | Repair and renovation of toilets | 2016.06.17 | 2016.08.15 | 91.00 % (Sep'16) | Detailed estimate under process. |
Detail Report
Graph / Photo |
|||
274 | Renovation of Classrooms, Corridor, Principal Room & Staff Room. | 2016.06.16 | 2016.09.13 | 53.00 % (Sep'16) | T.S. under process. |
Detail Report
Graph / Photo |
|||
275 | Acoustic treatment system and renovation of multipurpose hall. | 2017.10.20 | 2018.01.17 | 40.27 (Nov'21) | 0.00 (Nov'21) | 65% (Work is delayed due to ongoing electrical work as well as Covid-19) |
Detail Report
Graph / Photo |
||
276 | Comprehensive Maintenance , Operation of Multi Level underground parking along with associated Electrical , Mechanical services installed at Delhi High Court, Sher Shah Suri Marg, New Delhi dg. 2018-19. | 2018.11.02 | 2019.11.01 | 214.77 (Sep'19) | 0.00 (Sep'19) | Work in progress |
Detail Report
Graph / Photo |
||
277 | Installation of Rain Water Harvesting System with bore well in GGSSS Roop Nagar No 3 School Delhi | 2019.03.07 | 2019.04.06 | Work In Progress |
Detail Report
Graph / Photo |
||||
278 | Reconstruction of collapsed boundary wall of CBD plot at Shahdara, Delhi owned by Urban Development Department. | 2019.07.24 | 2021.09.22 | in progress. |
Detail Report
Graph / Photo |
||||
279 | Construction of Hospital at Hastsal, New Delhi | 2021.06.17 | 2023.06.16 | 1643.90 (Jun'23) | 0.00 (Aug'24) | Structure work almost completed of the main building. Brick work, AAC block, Tile, Granite, Waterproofing in toilets, Sanitary & water supply, Gypsum Plaster, Cement Plaster and misc. other works are in progress. |
Detail Report
Graph / Photo |
||
280 | C/o Trauma Centre and Utility Block at SGMH at Mangolpuri, Delhi, including Water Supply, Sanitary Installations, Electrical Installation, HVAC, Low side, Fire Alarm, and Fire Fighting System etc. (Hiring of Photocopier Machine.) | 2019.09.04 | 2021.03.03 | 632.27 (Mar'23) | 0.00 (Mar'23) | work in progress |
Detail Report
Graph / Photo |
||
281 | Construction of multipurpose court, levelling and preparing the layer of good earth on the play ground in Delhi Police Public School at PTS, Wazirabad, Delhi | 2019.06.30 | 2019.08.29 | 26.71 (Mar'21) | 0.00 (Mar'21) | work in progress |
Detail Report
Graph / Photo |
||
282 | Comprehensive architectural consultancy services for Construction of Pucca School Buildings (G+3) with Ancillary Facilities including internal water supply, sanitary installation, internal electrical installation and development of site at Jaffarpur Kalan, Nangli Sakrawati and Qutubapur (Sainik Vihar) New Delhi. (Package-1) | 2021.10.04 | 2022.10.03 | 51.25 (Mar'23) | 0.00 (Feb'24) | Agmt. No. 04/EE/Edu. (M)/South-west/2021-22 received from EE (Edu.) South West, PWD, Sector-6, Dwarka, New Delhi. Agency yet to submit the terrace floor and other misc. drawings. |
Detail Report
Graph / Photo |
||
283 | Maintenance of P.C. in Division and Sub-Division Office | 2021.07.31 | 2023.07.30 | work in progress |
Detail Report
Graph / Photo |
||||
284 | Renovation work at office complexes of Divisional Commissioner 5 Shamnath Marg Delhi 110054 | 2021.12.15 | 2022.06.14 | 274.83 (Mar'23) | 0.00 (Oct'23) | Work In Progress. Site available in Parts. |
Detail Report
Graph / Photo |
||
285 | Renovation/Upgradation of the GST Office i/c A,B and C Wing at 4th Floor, Deptt. of Trade & Taxes Bldg. , IP Estate, New Delhi | 2022.10.06 | 2023.04.05 | Work delayed due to not handing over site / electrical work |
Detail Report
Graph / Photo |
||||
286 | Providing fencing around the small plants in Central Park of Dr. BSA Residential complex | 2022.06.09 | 2022.08.08 |
Detail Report
Graph / Photo |
|||||
287 | Repairs & maintenance of Resource Center for Children with special needs: 1208014--Partap Nagar-SKV | 2022.06.30 | 2022.08.30 | Work in Progress |
Detail Report
Graph / Photo |
||||
288 | Running and Maintenance and supply of Fittings for Newly constructed Covid Hospital | 2022.04.14 | 2023.04.07 | 6.88 (Aug'22) | 0.00 (Aug'23) |
Detail Report
Graph / Photo |
|||
289 | Comprehensive Maintenance of Civil works for Day-to-day Maintenance and A/R and M/o Work, Special Repair etc of Dr. BSA Hospital Campus, Sector-6, Rohini, Delhi and Sanjay Gandhi Memorial Hospital Campus, Mangolpuri, Delhi during 2022-23 and 2023-24 | 2022.05.01 | 2024.04.30 | 357.33 (Mar'23) | 0.00 (Aug'24) | work in porgress |
Detail Report
Graph / Photo |
||
290 | Construction of cycle stand, toilet room, sport room and development of rain water harvesting and other misc. work at RSBV Jheel Khuranja Delhi-110031 (School ID1003003) | 2022.03.30 | 2022.06.29 | 0.00 (Jan'24) | work in progress. 60% work has been done. |
Detail Report
Graph / Photo |
|||
291 | Providing and Fixing Bullet Proof Protective Posts 03 Nos at different locations of Delhi Secretariat | 2022.06.26 | 2022.08.09 | work in progress & testing required. 95% work has been done. |
Detail Report
Graph / Photo |
||||
292 | Strengthening of damaged beams and slabs Beautification of main gates Development of pathways and misc works | 2022.03.03 | 2022.09.02 | work in progress. 92% has been done. |
Detail Report
Graph / Photo |
||||
293 | Re-construction of boundary wall of school | 2023.12.14 | 2024.05.11 | work in progress |
Detail Report
Graph / Photo |
S. No.क्र. सं. | Description | Details |
---|
S. No.क्र. सं. | Remarks | As On | Revised On |
---|
S. No.क्र. सं. | Upload Date | Description |
---|
S. No. | Date | Location | Remarks | Physical Progress (%) | View | ||
---|---|---|---|---|---|---|---|
Last | Upto | Photo | Doc |
S. No.क्र. सं. | Remarks | Date | Document |
---|
This is the Portal of Public Works Department, Govt. of NCT of Delhi, developed with an objective to enable a single window access to information and services being provided by the different wing of PWD Delhi. It is an initiative towards E-Governance Plan. यह लोक निर्माण विभाग, राष्ट्रीय राजधानी क्षेत्र (दिल्ली सरकार) का पोर्टल है जिसे इस उद्देश्य के साथ विकसित किया गया है जिससे लोक निर्माण विभाग, दिल्ली के विभिन्न स्कन्धों (विंग) द्वारा प्रदान की जा रही सूचनाओं तथा सेवाओं को एकल खिड़की के माध्यम से जाना जा सके | यह ई - गवर्नेंस योजना की दिशा में पहल है |
12th Floor, MSO Building,
I. P. Estate, New Delhi – 110002
Toll Free: 1800 11 00 93
© 2021 All Rights Reserved. Version 35.2.9 / 01-04-2024