S. No.क्र. सं. Name of Workकार्य का नाम Date of Start Cost (In Lac) Target Progress Agency Present Position Satisfactory Viewदेखें
Stp. Completion
Exp. Completion Expenditure Phy. Progress Bottleneck Quality Safety Progress
1 Redevelopment of Tis Hazari District Court

519981.00
0.00 (Mar'19)

0.00 (Mar'19)
A/A & E/S awaited
Detail Report
Graph / Photo
2 Elevated Road, Extradosed Bridge, Flyover, Clover Leaves, Loops, Ramps, Footpath, Cycle Track, Road Work including Signages, Street Light Works & Allied Works Pile, Pile Cap, Pier cap, Pier, well foundation and casting of segment 18/04/2015
17/10/2017
31/10/2024
96400.00
150954.52 (Jul'24)

0.00 (Jul'24)
Larson & Toubro Limited RMP 31D - 31E G1 girder reinforcement checking in progress
land not fully available and tree cutting permission pending
Detail Report
Graph / Photo
3 Underground Tunnel, Underpass, FOB, Loops, Ramps, Footpath, Road Work including Road Signage, Road/Street Lighting works, Tunnel furnishing (FF& FA system, PA system, Automated drainage, integrated tunnel management system etc.), landscaping/horticulture work & allied works 08/11/2017
29/08/2019
31/08/2023
77700.00
45144.48 (May'24)

0.00 (May'24)
M/s L&T Ltd. Work in progress, transformer already installed
light fitting installed
Detail Report
Graph / Photo
4 Setting up of Semi permanent temporary I.C.U. Hospital at Shalimar Bagh(G plus 3) (1430beds), Kirari (G plus 4)(458 Beds) and Sultanpuri (G plus 3)(525 Beds) Package I

43132.08
2581.36 (Mar'24)

0.00 (Mar'24)

Detail Report
Graph / Photo
5 Construction of District Court Complex at Sector-26, Rohini, Delhi 10/06/2024
09/02/2026
09/02/2026
43055.92
439.99 (Dec'24)
29.00 %
0.00 (Dec'24)
Roshan Real Estate Pvt Ltd. Pre-construction activities like construction of site office, lab and barricading works is in progress
Detail Report
Graph / Photo
6 Supply, installation, testing, commissioning of CCTV camera in Delhi. (Sub: Empanelment of firms for supply, installation, testing, commissioning & CAMC of CCTV system in Delhi). 24/11/2018
23/11/2019
14/11/2027
42798.32
9361.10 (May'24)

0.00 (May'24)
Bharat Electronics Ltd work completed. The work of CAMC which is part of the project, is going on.
Detail Report
Graph / Photo
7 C/O Integrated campus of G.B. Pant Engineering College and Polytechnic at Okhla delhi. 22/03/2024
21/11/2026
21/11/2026
42361.79
1531.57 (Sep'24)
27.00 %
0.00 (Sep'24)
Som Projects Pvt. Ltd. Work is help up due to revalidation of tree cutting permission by Hon’ble Delhi High Court.
Detail Report
Graph / Photo
8 setting up of Semi permanent/temporary i.c.u at CNBC (G+4)(1912 beds) and GTB Hospital complex (G+4 ) (1912 Beds) Package-II (Electrical) 23/09/2021
22/02/2022
04/08/2022
40775.18
12588.56 (Jan'24)

0.00 (Jan'24)
SAM India Builtwell GTB : The erection of PEB structure and deck slab in main ward block nearing completion, while the same in Arrival & Diagnostic blocks in progress. The fire paint, internal partition etc. are in progress. The work is delayed due to revision in drawings by consultant, ban on construction works due to pollution during November-December followed by covid wave. CNBC : The erection of PEB structure and deck slab are nearing completion. The fire paint, internal partition, external wall etc. are in progress. The work is delayed due to revision in drawings by consultant as per requirement of MS, CNBC, ban on construction works due to pollution during November-December followed by covid wave.
Detail Report
Graph / Photo
9 Setting up of Semi-permanent temporary I.C.U Hospital at Chacha Nehru Bal Chikitsalaya (G plus 4) (596 beds) and GTB Hospital Complex (G plus 4) (1912 Beds) Package II

35533.93
18212.15 (Mar'24)

0.00 (Mar'24)

Detail Report
Graph / Photo
10 C/o Additional Court Rooms on the existing Court Bldg. in District Court Complex at Rohini

33532.67

A/A & E/S awaited
Detail Report
Graph / Photo
11 Construction of Flyover with Ramps, Footpath, Road Work including Road Signage, Street Light works, Drainage, Horticulture, Mural Works & allied works at Road No. 56 between Anand Vihar ROB and Apsara Border ROB, New Delhi (EPC Mode 10/09/2022
08/12/2023
08/12/2023
33420.85
14140.70 (Sep'24)

0.00 (Sep'24)
finishing work under progress
nill
Detail Report
Graph / Photo
12 Construction of New Hospital Block at Babu Jagjivan Ram Memorial Hospital, Jahangirpuri, New Delhi

31879.73
13.58 (Jan'24)

0.00 (Jan'24)
PE of Civil Work submitted to the O/o Chief Engineer on dated 10/05/2023.
Detail Report
Graph / Photo
13 Construction of Home for Assisted Living at Narela, Delhi

30528.15

Land available. A/A & E/S is yet to be received
Detail Report
Graph / Photo
14 Providing 600 Nos. LED Screens at Various Locations in Delhi.

29481.84

The tender has been cancelled on 07.07.2023 due to administrative reasons
Detail Report
Graph / Photo
15 Setting up of Semi-permanent temporary I.C.U Hospital at Sarita Vihar (G plus 4) (336beds) and Raghubir Nagar (G plus 3)(1577 Beds) Package III

29175.20
2718.19 (Mar'24)

0.00 (Mar'24)

Detail Report
Graph / Photo
16 Repairing of fire alarm system installed at Lawyers chamber block 3 28/02/2020
27/03/2020
27388.89

Ekta Enterprises
Detail Report
Graph / Photo
17 Construction of Hospital at Madipur, New Delhi 11/11/2020
10/11/2022
31/03/2024
26970.58
18686.95 (Dec'24)

0.00 (Dec'24)
Ramacivil India Construction Private Limited Physical Progress- 92 % Financial Progress - 144.10 Cr.
9th & 10th Floor Approval awaited
Detail Report
Graph / Photo
18 Construction of Hospital at Hastsal, New Delhi 17/06/2021
16/06/2023
30/06/2025
23695.11
6578.45 (Dec'24)
100.00 %
0.00 (Dec'24)
Structure work of main building completed. Stone cladding work, RCC work of water storage tank & front projection area, Structural steel work and other miscellaneous works are in progress. The overall progress of civil part is about to 68%.
Progress of work is slow due to non-availability of funds.
Detail Report
Graph / Photo
19 REWIRING/REPAIRING OF ELECTRICAL ACCESSORIES IN TOILETS AT VARIOUS DELHI GOVT. SCHOOL 09/08/2017
09/11/2019
23127.43

NKG Infrastructure Limited
Detail Report
Graph / Photo
20 C/o Additional Lawyer Chambers near District Court, Dwarka, Sec-10, New Delhi.

22764.65
0.00 (Mar'19)

0.00 (Mar'19)
A/A & E/S is awaited
Detail Report
Graph / Photo
21 Construction of 132 Type-V Quarters and 52 Type-VI Quarters for Judges at Anand Vihar Delhi.

22456.97

A/A & E/S awaited
Detail Report
Graph / Photo
22 C/o Police Housing project at Mandoli, Delhi-93(SH: C/o 300 Nos. Type-II and 60 Type-IV qtrs and its related development works)

22130.16

A/A & E/S is awaited
Detail Report
Graph / Photo
23 C/o New Building for office of Deputy Commissioner & District Magistrate (South-west) at Sector-10, Dwarka, New Delhi

19481.76
0.00 (Mar'19)

0.00 (Mar'19)
Revised preliminary drawings has been prepared by Sr. Architect, PWD
Detail Report
Graph / Photo
24 Supply, Installation, Testing and Commissioning and CAMC of CCTV Camera system in Delhi Phase-II Package-II. 14/01/2020
11/07/2020
31/03/2024
19053.31
2893.49 (Mar'24)

0.00 (Mar'24)
Total CCTV to be fixed =70000 Installed CCTV=62761 Approved CCTV= 66693* Note*: Erroneously the quantity of approval cameras counted wrong, hence the necessary correction made. 0 The work for installation of remaining CCTV cameras is under progress
Detail Report
Graph / Photo
25 Supply, Installation, Testing and Commissioning and CAMC of CCTV Camera system in Delhi Phase-II Package-1 14/01/2020
11/07/2020
31/05/2024
19050.80
3692.41 (Sep'24)

0.00 (Sep'24)
Total CCTV to be fixed =70000 Installed CCTV=57498 Approved CCTV= 66172 The work for installation of remaining CCTV cameras is under progress
Detail Report
Graph / Photo
26 Construction additional courts at new plot at Karkardooma in front of existing Karkardooma Court Complex, Delhi.

17394.78

A/A & E/S awaited
Detail Report
Graph / Photo
27 C/o 750 Bedded Hospital at Dwarka, New Delhi.

16355.70
441.02 (Jun'23)

0.00 (Jun'23)

Work has been transferred to EE(E) South West Health Maintenance Division.

Detail Report
Graph / Photo
28 Construction of Flyover at Nand Nagri and Gagan Cinema Junction of Mangal Paney Marg including Elevated Corridor Footpath Road Work and Road Signages Electrical Works Drainage Rain Water Harvesting and Allied works on EPC mode 03/02/2023
31/07/2024
11/10/2024
15785.00
10757.02 (Sep'24)

0.00 (Sep'24)
Ram Kumar Contractor Piling completed / pier cap / PSC girder is in progress. 88 Nos. of PSC girders have been erected out of 132 Nos. 12 No. of deck slab has been casted. BSES shifting in progress. Tree cutting permission awaited. Work getting delayed due to non availability of tree cutting permission.
Detail Report
Graph / Photo
29 Construction of Hospital Block at Guru Gobind Singh Govt. Hospital located at Raghubir Nagar, New Delhi 18/10/2019
10/04/2021
31/12/2024
13447.15
8366.10 (Oct'24)

0.00 (Oct'24)
Roshan Real Estate Pvt Ltd. Work is in progress.
Slow progress of electrical work
Detail Report
Graph / Photo
30 Construction of Additional Court at New Plot at Karkardooma in Front Of existing Karkardooma Court Complex, Delhi (SH: C/o Main Block, External Development, Internal electrical installation, External lighting, Lift, Fire Fighting System, Fire Alarm with PA System, D.G. Sets, Electrical Sub-Station, HVAC works, Horticulture work & allied works.) 10/06/2024
09/02/2026
09/02/2026
12402.76
183.59 (Dec'24)
29.00 %
0.00 (Dec'24)
Abhilasha Enterprises Site logistic setup and mobilization at site is under progress.
Detail Report
Graph / Photo
31 C/o District Court Complex at Shastri Park, Near Usmanpur Police Station, Delhi. (SH: C/o Main Block, External Development, Internal Electrical Installation, External lighting, Lift, Fire Fighting System, Fire Alarm with PA System, D.G. Sets, Electrical Sub-Station, HVAC works, Horticulture work & allied works.) 10/06/2024
09/02/2026
09/02/2026
12052.77
65.36 (Jul'24)
29.00 %
0.00 (Jul'24)
Abhilasha Enterprises Work recently awarded
Work recently awarded
Detail Report
Graph / Photo
32 C/o High Security Jail Complex at Narela, Delhi.

10000.00


Detail Report
Graph / Photo
33 C/o Family Court Complex at Rohini, New Delhi

9579.83
11.08 (Sep'24)

0.00 (Sep'24)
• Approval of plans by BMCC received on 27.12.2022. • A/A & E/S received on 22.10.2021 for Rs. 85.62 Crore. • The consultant had revised the architectural plans and proposed 18 Courtrooms against the 21 courtrooms earlier. • Revised Plans submitted to Delhi Fire Service on 27.02.2024 and NOC received on 07.03.2024. • Revised plans submitted to DUAC and NOC received on 18.03.2024. • During review meeting on 09.05.2024, Consultant has given the assurance to submit the detailed estimate of both Civil & electrical by 20.05.2024 and Draft NIT for call of tenders upto 22.05.2024. • Detailed Estimate submitted on 30.05.2024 and under scrutiny. • T.S. & NIT is under process.
Detail Report
Graph / Photo
34 C/o Haji House at Sector-22, Phase-II, Dwarka, New Delhi

9566.03
0.00 (Mar'19)

0.00 (Mar'19)
A/A & E/S awaited
Detail Report
Graph / Photo
35 C/o New DC office at Mandawali, Fazalpur, Delhi

8432.86

A/A & E/S awaited
Detail Report
Graph / Photo
36 Construction of Delhi Fire Service Headquarter Building at Connaught Place, New Delhi-110001

8094.10
0.00 (Mar'19)

0.00 (Mar'19)
This project is being carried out of Architectural work in House. In earlier estimate amounting to Rs. 80.51 Cr. was sent to the client department but due to change of ground coverage by 30 to 50 and FAR by 120 to 300 as per new UBBL-2016. Drawings has been modified. Accordingly, the estimate has been modified amounting to Rs. 158,65,77,000/- on the basis of latest DPAR 2023 and the same has been submitted to the Director, Delhi Fire Service by Chief Engineer (J&P) vide letter No. 23(19)/PWD/CE(J&P)/2024/645-H dated 04.03.2024.
Detail Report
Graph / Photo
37 Maintenance of P.C. in Divn and SD Office.

7122.82

PNSC Infrastructure Pvt. Ltd
Detail Report
Graph / Photo
38 Construction of proposed New Buildings for expansion of Rao Tula Ram Memorial Govt. Hospital at Jaffarpur, Delhi. 06/08/2019
29/10/2020
31/03/2025
6563.40
4395.59 (Oct'24)

0.00 (Oct'24)
PNSC Infrastructure Pvt. Ltd Internal finishing & external development works are under progress.
Detail Report
Graph / Photo
39 Construction of Bridge on Najafgarh Drain at Tri Nagar/Inderlok, Karampura and Rampura, Delhi to cover the complete Right of Way (ROW) excluding area of already constructed bridge alongwith road improvement on either side of bridge including making. 16/03/2019
30/09/2021
30/09/2022
5388.53
5824.00 (Mar'24)

0.00 (Mar'24)
Ram Kumar Contractor Final bill is yet to be paid.
work is in progress
Detail Report
Graph / Photo
40 Construction of Police Station and Multi storyed Staff Quarters at Paschim Vihar, Delhi.

5120.46


Detail Report
Graph / Photo
41 Construction of Pucca School Buildings (G+3) with Ancillary Facilities including internal water supply, sanitary installation, internal electrical installation and development of site at Sector-16, Dwarka ,New Delhi. (SH: Civil and Electrical Composite Work). 18/07/2021
17/07/2022
31/12/2024
5058.13
1607.60 (Nov'24)

0.00 (Nov'24)
PNSC Infrastructure Pvt. Ltd Initial Delay was due to delay in receiving local body approval. DUAC approval received on 19.09.2022. Building Plans approved by SE (Bldg.), MCD vide file No. 10106691 dt. 03.04.2023. All local body approval has been received. Structural drawing prepared & proof checking from DTU Delhi is completed. Architectural & Structural drawing is issued to the agency. Building work started on 19.05.2023. Foundation work completed. Superstructure work started, RCC slab for floor-2 level is under progress. RPE amounting to Rs.47.52 Cr. sent to DoE vide this office letter 23(49)/23/CE(Proj.)/PWD/ Estimate/501 dated: 21.03.2024 for accord of Revised A/A & E/S.
Qutubapur- SANCTION WITHDRAWN (i). Site layout plan has been uploaded to MCD by consultant for approval on dated 25.05.2022 and property tax of land also has been deposited. (ii). There is no tree cutting and no transplanting required. (iii). Additional Commissioner MCD & CTP, MCD during meeting 3.10.2022 informed that due to urbanization of villages, this gram sabha land is now under control of DDA .MCD is yet to upload their observation regardfing Layout Plan . (iv) DO dated 17.11.2022 issed by E-in-C to VC, DDA regarding clarification required by MCD. Response is still awaited. (v) LoP was discussed during meeting in MCD on 27.03.2023. Minutes of Meeting is still awaited. Above Sanction Withdrawn by DoE vide letter no.F.16/Estate/Cons./ Pucca School/Qutubapur/ 1594-1601 Dated: 24.05.2023 .
Detail Report
Graph / Photo
42 Strengthening of Rohtak Road (NH-10) from Punjabi Bagh Round about to Metro Pillar No. 526 under PWD, Maintenance Division West-2 Roads, New Delhi

4613.56

Estimate submitted to MORTH for approval
Detail Report
Graph / Photo
43 Construction of G+5 Integrated Complex and demolishing of existing building near OHB-II, Sewa Kutir Complex, Delhi.

4437.18


Detail Report
Graph / Photo
44 Street Scaping of Shivdaspuri Marg and Patel Road (From Moti Nagar T-Point to Pusa Round about), Delhi.(Composite Work of Civil Road Work i/c Electrical and Horticulture Work)

4350.79
58.64 (Nov'24)

0.00 (Nov'24)

Technical bid opened


Work transffered to Street scapping Division

Detail Report
Graph / Photo
45 Street Scaping of Shivdaspuri Marg and Patel Road (From Moti Nagar T-Point to Pusa Round about), Delhi.(Composite Work of Civil Road Work i/c Electrical and Horticulture Work) 43,50,79,456

4350.79


Detail Report
Graph / Photo
46 Street Scaping of Shivdaspuri Marg and Patel Road (From Moti Nagar T-Point to Pusa Round about), Delhi.(Composite Work of Civil Road Work i/c Electrical and Horticulture Work)

4350.79
395.55 (Mar'24)

0.00 (Mar'24)

Detail Report
Graph / Photo
47 Construction of underpass by jack pushing of pre-cast RCC boxes at outer ring road near Mukarba Chowk including construction of approach road from Badli Junction to Haiderpur Metro Station. 14/10/2022
13/10/2023
31/12/2024
4329.32
398.75 (Aug'24)
100.00 %
0.00 (Aug'24)
Dharamraj Contracts (I) Pvt. Ltd. Shifting of IGL gas pipeline has been completed on 28.11.2023. Payment of Rs. 5.15 Cr has been made to TPDDL on 22.12.2023. The casting of the thrust bed has been completed.  Machinery is being mobilized for box pushing. The casting of the four boxes has been completed. Pushing of the boxes will commence soon. Acquisition of land from IFCD is to be expedited.
Work affected due to non-availibility of NOC from I&FCD
Detail Report
Graph / Photo
48 GAMMA KNIFE CENTRE(GIPMER),NEW DELHI,110002

4000.00


Detail Report
Graph / Photo
49 Supplying and installation of Modular Operation Theatre and Medical Gas Pipe line System at orthopedic department of LNH including Emergency Trauma Services and Intensive Care Beds (50)

3742.21


Detail Report
Graph / Photo
50 Construction of 140 nos additional SPS Classrooms in DOE Schools GGSSS No. 1 Tukhmirpur, Delhi (1104262) 40 Class rooms, GGSSS No. 2 Tukhmirpur, Delhi (1104419) 32 Class rooms & GSKV Khajuri Khas, Delhi (1104022) 68 Class rooms including Laboratory, staircases, toilets and ramps, internal water supply, sanitary installations, Internal electrification and fire fighting arrangements.

3713.27

The fund has not alloted by SSA and vide CE office letter No. 23(45)/ 22/CE(Proj.)/ PWD /E&NE/852 dated: 22.09.2022 informed the Education Department/SSA for withdrawn the sanction.
The fund has not alloted by SSA and vide CE office letter No. 23(45)/ 22/CE(Proj.)/ PWD /E&NE/852 dated: 22.09.2022 informed the Education Department/SSA for withdrawn the sanction.
Detail Report
Graph / Photo
51 (a) C/o 76 Nos. Equivalent rooms SPS type (i.e. classrooms, Labs and Principal rooms), 12 Nos. toilets with ancillary facilities like pumping, sanitary and electrical installation like Lift, Fire Fighting work and development of site at Plot No.-1B, Sector-41, Rohini, Delhi. (b) C/o 72 Nos. Equivalent rooms SPS type (i.e. classrooms, Labs and Principal rooms), 1MP Hall, 08 Nos. toilets with ancillary facilities like pumping, sanitary and electrical installation like Lift, Fire Fighting work and development of site at Plot No.-2,C.F.-3, Sector-41, Rohini, Delhi. 20/01/2024
19/01/2025
19/01/2025
3527.47
1514.82 (Dec'24)
90.00 %
0.00 (Dec'24)
RKMT BUILDCON PRIVATE LIMITED Work in progress
Detail Report
Graph / Photo
52 E & M works relating to all day to day operation & maintenance, A/R & M/O Works & Special Repair Works etc 27/05/2022
26/05/2024
26/05/2024
3516.35
4032.31 (Oct'24)

0.00 (Oct'24)
Swastik Electrotech Pvt. Ltd.

Work in progress


Work in progress

Detail Report
Graph / Photo
53 Renovation work of offices of Hon’ble CM and various Ministers at Delhi Sachivalya during 2021-22 (Civil & Electrical Works)

3385.59
2858.20 (Nov'23)

0.00 (Nov'23)

Detail Report
Graph / Photo
54 Renovation work of offices of Hon’ble CM and various Ministers at Delhi Sachivalya during 2021-22 (Civil & Electrical Works)

3368.55
678.56 (Mar'23)

0.00 (Mar'23)

Detail Report
Graph / Photo
55 Construction of Six Storeyed conventional multilevel Parking at Dr. Baba Saheb Ambedkar Hospital at Rohini Sector-6,Delhi.

3266.00

the work is under planning stage
Detail Report
Graph / Photo
56 Construction of Pucca School Building (G+3) with ancillary facilities including internal water supply, sanitary installation, electrical installation and development of site etc. at Vacant land of F1 & F2 Block Sunder Nagri, Delhi. 17/10/2022
16/10/2023
31/07/2024
3000.18
2107.66 (Oct'24)

0.00 (Oct'24)
Jai Bhagwan RCC work completed, stone work 98% completed, Some repair work is going on. The paint putty, fixing of doors & windows in progress and development work in progress and same will be completed by 31.07.2024.
RCC work completed, stone work 98% completed, Some repair work is going on. The paint putty, fixing of doors & windows in progress and development work in progress and same will be completed by 31.07.2024.
Detail Report
Graph / Photo
57 Construction of DTC Bus Depot in resettlement colony at Sawada Ghevra, Delhi 05/04/2022
04/12/2022
31/07/2024
2915.78
345.00 (Jul'24)

0.00 (Jul'24)
SVK Infrastructures Building Work: is in advance stage. Revised sanction awaited because of which work is hindering. If the santion is not received work will have to be foreclosed.
Detail Report
Graph / Photo
58 Providing services of Data Entry / Computer Operators, Personal Secretary, Clerical Staff, Messengers, Messenger cum Peon & Peon for the office of E-in-C, Pr. Chief Engineer (M&F), Chief Engineer (East)-M, Chief Engineer (Flyover) along with its subordinate office, Circle C & ND – M & C & ND-Roads Division, Providing services of security guard for watch and ward for the office of Circle C & ND-M & C&ND-R Division & Watch and Ward of integrated tunnel in and around ITPO. 01/04/2023
31/03/2025
31/03/2025
2892.73
2618.86 (Oct'24)
85.00 %
0.00 (Oct'24)
RAKSHAK SECURITAS PVT. LTD. Work in progress
Detail Report
Graph / Photo
59 Street Scaping of Ring Road from Moolchand Junction to Ashram Chowk

2880.35
289.42 (Oct'24)

0.00 (Oct'24)

Detail Report
Graph / Photo
60 Day to Day maintenance and repair of Civil Work, Electrical Work and Horticulture Work.

2820.52
47.89 (Jan'24)

0.00 (Jan'24)

Detail Report
Graph / Photo
61 Expansion / Remodeling of Deep Chand Bandhu Govt. Hospital at Kokiwala Bagh, Ashok Vihar, Delhi. Including water supply, sanitary, drainage and electrical works etc. 28/06/2019
22/06/2020
30/11/2024
2806.33
955.19 (Mar'24)

0.00 (Mar'24)
Roshan Real Estate Pvt Ltd. Work in progress (Civil 98% progress) (Electrical 100%)
Detail Report
Graph / Photo
62 C/o 100 Nos. Equivalent SPS Classrooms in addition to Swimming Pool, Boundary Wall, 1 No. MP Hall, i/c Internal & External Water Supply, Sanitary Installation and Electrical Installation, RWH, UGT, Septic Tank, Development of site and Fire Fighting Systemetc. for New School Building at Naseerpur, New Delhi 12/02/2022
09/11/2022
30/06/2024
2800.59
3274.57 (Nov'24)

0.00 (Nov'24)
SVK Infrastructures Initially site was encroached by local people. Encroachment on the major part of land was removed with help of education department and Delhi Police on 22.03.2022. Partly site handed over to the agency for boundary wall and building construction on 23.03.2022. Due to High Court stay order dated 30.08.2022, work was stopped in disputed area. SDM Dwarka issued his order on 21.03.2023. After which work also started in the area which was earlier under dispute. Both Blocks of school building have been completed. Work of swimming pool is in progress.
Detail Report
Graph / Photo
63 Civil works and Electrical works. 22/08/2023
21/05/2024
31/08/2024
2735.12
0.00 (Apr'24)

25.00 % (Apr'24)

Foundation work for boundary wall completed.

Plinth Beam casting for administrative block in progress. Foundation work for workshop in progress.


Foundation work for boundary wall completed.

Plinth Beam casting for administrative block in progress. Foundation work for workshop in progress.

Detail Report
Graph / Photo
64 SITC and CAMC of CCTV System in Delhi Govt. Schools. SH- Providing and Maintenance of Internet lease line Connection. 17/08/2019
16/02/2020
30/09/2023
2691.32

Reliance Jio Infocomm Work is in progress and shall be completed along with main work of installation of CCTV camera in Delhi Government Schol.
Detail Report
Graph / Photo
65 Construction of conventional Bus Depot no. I & II on ground floor at Sector A-1, A-4, Narela, Delhi 23/08/2021
22/05/2022
31/07/2024
2373.12
0.00 (Jun'24)

93.00 % (Jun'24)
M/s PK Gupta & Co. Building Work: RCC work and Brickwork of Admin cum Rest Room, Toilet Block have been completed. Finishing work completed in Admin cum Rest room has been completed. Workshop Building-All the Structural work has been completed and finishing work is in progress. Hard standing/CC Pavement: All the work related to hardstanding has been completed except for the area occupied by TPDDL equipments and Labour camps. The progress of the work is being affected due to encroachment /non handing over of the land by TPDDL. The progress of work is hampered due to non availability of budget.
work is in progress
Detail Report
Graph / Photo
66 Uttam Nagar T Point Ram Mandir Marg Mall Rd C1 to C1A Block Rd under Sub Division WR12 Lala Ganesh Das Khatri Marg G-1 Block Vikaspuri Rd Rd No 235 Rd Adjacent to PVR under SubDivision WR13 80 Feet Chowkhandi Rd Shakti Mandir Marg Major Sudesh Marg

2305.99


Detail Report
Graph / Photo
67 Construction of Old Age Home Sector-4, Rohini, Delhi

2240.23


Detail Report
Graph / Photo
68 Improvement and strengthening of Rama Road from Zakhira Crossing to Patel Road including construction of outfall drain 29/10/2012
28/08/2013
2197.33
308.84 (Mar'14)

193.00 % (Mar'14)
N.S.C. Project Pvt. Ltd.
Detail Report
Graph / Photo
69 Construction of Cluster Bus Depot at Kirari Village, Plot No.8 (PSP7), Sector-41, Rohini, Delhi. SH: Civil works and Electrical works. 24/05/2023
23/01/2024
31/12/2024
2107.18
0.00 (Jun'24)
98.00 %
30.00 % (Jun'24)
Kundu Nirma The building work affected due to high water table. Matter of constructing the building on pile foundation was finalised. Casting of more than 440 piles has been completed. 80% of the Earth work has been completed. Casting of 1st Floor Columns of building are in progress. The progress of work is hampered due to non availability of budget.
work is in progress
Detail Report
Graph / Photo
70 A. Strengthening of Outer Ring Road (Road ID 347) from Africa Avenue crossing to RTR Flyover under PWD Division South West Road-I, New Delhi. B. Strengthening of Rao Tula Ram Marg (Road ID 98) from Ring Road crossing to NH8 under PWD Division.......

1932.54

Work in progress
Detail Report
Graph / Photo
71 SITC of Modular Operation Theatre and MOT Integration System and MGPS 05/06/2023
04/03/2034
04/03/2034
1896.47
132.15 (Jan'24)
16.00 %
0.00 (Jan'24)
MDD Medical System (INDIA) Pvt. Ltd

work in progress


work in progress

Detail Report
Graph / Photo
72 Construction of SPS (4-Storey) for additional class rooms at Karampura Campus of Dr. B.R. Ambedkar University, Delhi. 24/03/2023
19/09/2023
31/07/2024
1887.50

85%
The structural work of the building is completed. Internal plaster i.e. putty and painting almost completed. Door frame including shutter and UPVC window fixed. The false ceiling work is in classroom portion is in progress. Tile flooring granite and SS railing and grill work almost completed.
Detail Report
Graph / Photo
73 Construction of Govt Sr Sec Pucca School building G plus 3 with ancillary facilities including internal water supply internal electrical installation sanitary installations development of site STP and RWH etc at Sector 27 Rohini. 31/05/2020
30/05/2021
31/12/2024
1874.70
3043.29 (Oct'24)

0.00 (Oct'24)
SSP Promoters and Builders Private Limited Since last one month NGT Ban has implemented due to pollution.
Detail Report
Graph / Photo
74 STREET SCAPING OF 1000 METER OF NELSON MANDELA ROAD TO MAKE IT MODEL STRETCH OF STREET SCAPING PROJECT

1870.18


Detail Report
Graph / Photo
75 Street Scaping of 800 meter length of Ring Road, Bhairon Road T-Junction to Shantivan Crossing to make it Model Stretch of Street Scaping Project

1859.21


Detail Report
Graph / Photo
76 Street scaping of 675 metre of Road NH-10 Delhi Rohtak Road Metro Pillar 410 to Tikri Border to make it Model stretch of Street scaping Project

1814.36
1069.45 (Mar'24)

0.00 (Mar'24)

Detail Report
Graph / Photo
77 Street scaping of 675 metre of Road NH-10 Delhi Rohtak Road Metro Pillar 410 to Tikri Border to make it Model stretch of Street scaping Project

1814.36
30.56 (Mar'24)

0.00 (Mar'24)

Detail Report
Graph / Photo
78 Balance Civil, Electrical and Horticulture Work as per revised concept

1809.71


Detail Report
Graph / Photo
79 Payment of Electricity bills in respect of East Delhi Road Street Light.

1800.00
9.76 (May'19)

0.00 (May'19)

Detail Report
Graph / Photo
80 Payment of monthly salaries to work charge staff including other payment relating to salary head like arrear, allowance ec.

1800.00


Detail Report
Graph / Photo
81 C/o 52 Nos. (G+3) equivalent SPS class rooms including stilt, 1 lift, 8 toilet blocks & 4 staircase at A C C GSBV at Jhilmil Colony, Delhi & 48 Nos. (G+3) equivalent SPS class rooms including 3 nos staircase, lift and 4 toilet blocks at Mustafabad School, Delhi including internal & external water supply, sanitary installations, melectrical installations, development of site, boundary wall, UGR, RWH, Fire Fighting system etc 01/04/2022
24/02/2023
31/08/2024
1798.93
257.13 (Nov'24)

0.00 (Nov'24)
K. L. ARORA & SON For 60% area work completed & for 30% area RCC work completed and finishing work just started and will be completed by 31.08.2024 & remaining 10% area could not start due to space constraints and branches of tree in building line and for the same application has applied for pruning to the forest department.
For 60% area work completed & for 30% area RCC work completed and finishing work just started and will be completed by 31.08.2024 & remaining 10% area could not start due to space constraints and branches of tree in building line and for the same application has applied for pruning to the forest department.
Detail Report
Graph / Photo
82 Strengthening of Dev Prakash Shastri Marg (ID: 1255) from T-Point Loha Mandi to Rattan Puri Chowk, Dr. K.S. Krishnan Marg (ID: 216) from Rattan Puri Chowk to Pusa Round about and Girdhari Lal Goswami Marg (ID: 2126) from T- Point Naraina to Shadipur Red Light under Sub Division-III, Division South West Road -1, PWD, New Delhi.

1789.26
1650.94 (Oct'24)

0.00 (Oct'24)
work in progress
funds
Detail Report
Graph / Photo
83 Providing Slip Road Bridge On Kondli Bridge over Gazipur Drain Hindon Canal from Road along Gazipur drain to Shamshan Ghat Ghazipur Dairy Farm Road Delhi 22/11/2021
17/10/2022
30/06/2024
1773.27
573.72 (Mar'24)

0.00 (Mar'24)
Harbel Singh & Sons - Work slow down due to shortage of funds. - 4 Nos of slab casted out of 5. - 5th span girder launched. -RPE submitted to higher office after compliance of observations. Proposal for foreclosure is being initited due to want of sanction.
NA
Detail Report
Graph / Photo
84 Construction of New Teaching Block in DIET at Daryaganj, New Delhi

1764.30
109.73 (Jun'22)

0.00 (Jun'22)

Detail Report
Graph / Photo
85 Construction of Skywalk FOB at Madhuban Chowk (on Outer Ring Road ) connecting Pitampura Metro Station and Rohini court, Delhi.

1736.00

PE submitted


PE submitted

Detail Report
Graph / Photo
86 Construction of SPS (4-Storey) for additional class rooms at Karampura Campus of Dr. B.R. Ambedkar University, Delhi. 24/03/2023
19/09/2023
31/07/2024
1729.05
1289.31 (Oct'24)

0.00 (Oct'24)
SPS Infrabuild Pvt. Ltd. 85%
The structural work of the building is completed. Internal plaster i.e. putty and painting almost completed. Door frame including shutter and UPVC window fixed. The false ceiling work is in classroom portion is in progress. Tile flooring granite and SS railing and grill work almost completed.
Detail Report
Graph / Photo
87 Remodelling and Upgradation of existing Blocks for Expantion of Government Hospitals situated in North West District Delhi.S.H. :- Construction of Multi Level Car Parking,Mortuary,ESS for Sanjay Gandhi Memorial Hospital,Mangolpuri,Delhi,

1700.00

work
Detail Report
Graph / Photo
88 Repair and Rehabilitation of ISBT Flyover (Yudhister Setu), Kashmere Gate, Delhi. (SH:Repair and Rehabilitation work). 27/11/2021
26/11/2022
31/12/2023
1677.86
322.71 (Aug'24)

0.00 (Aug'24)

Work in Progress


null

Detail Report
Graph / Photo
89 STREET SCAPING OF 700 METER LENGTH OF K.N. KATJU MARG TO MAKE IT MODEL STRETCH OF STREET SCAPING PROJECT

1644.08


Detail Report
Graph / Photo
90 Construction of Hostel for College Going Blind Students (Boys) at Sewa Kutir, Kingsway Camp, Delhi.

1573.00


Detail Report
Graph / Photo
91 C/o 68 Nos. (G+3) Equivalent SPS classrooms in SKV (Ravindra Thakur), East Vinod Nagar, Delhi (School ID 1002028) including 5 nos. staircase, 8 nos toilets, 1 no. lift & 25 nos Class rooms over existing (G+1) SPS structure with Prefabricated fibre reinforced sandwich panel with Light Gauged Steel Framed Structure including internal & external water supply, sanitary installations, electrical. 27/03/2023
19/02/2024
31/07/2024
1554.26
1372.77 (Nov'24)

0.00 (Nov'24)
SWASTIC CONSTRUCTION CO Block A Finishing work in progress and canopy structure work in progress. Block B Tile & granite work in progress along with plaster work back side of building. Development work in progress.
Block A Finishing work in progress and canopy structure work in progress. Block B Tile & granite work in progress along with plaster work back side of building. Development work in progress.
Detail Report
Graph / Photo
92 C/o 48 nos. additional (G+3) SPS equivalent classrooms including 3 nos staircase, 2 nos lifts and 8 nos toilet block at St. Eknath SKV J&K Block Dilshad Garden and 36 nos. additional (G+3) SPS equivalent classrooms including 2 nos Staircase, 4 nos toilet blocks & 1 lift and 1 MP hall at DIET J&K block Dilshad Garden, Delhi including internal & external water supply, sanitary installations, electrical installations, development of site, UGR, RWH, Fire Fighting system etc 26/03/2022
19/02/2023
31/08/2024
1553.88
457.41 (Nov'24)

0.00 (Nov'24)
K L Arora & Son Tower A - Finishing & development work under progress and will be completed by the end of 30th June 2024 and will be handed over by 15.07.2024 Tower B - is not taken up due to existency of trees in the proposed building plan regarding the same this office has written a letter to HOS to not being taken up due to tree in building plan. MP Hall - Work completed. DIET Block - Structural work completed of 2/3 building portion and structural work of remaining 1/3 portion of 2nd floor under progress except 2 no. classrooms and 1 staircase held up as there are branches of tree in the building line for which approval is pending for prunning of trees from forest department. Tile work & finishing work under progress in structurally completed 2/3 building portion and will be completed by 31.08.2024
Tower A - Finishing & development work under progress and will be completed by the end of 30th June 2024 and will be handed over by 15.07.2024 Tower B - is not taken up due to existency of trees in the proposed building plan regarding the same this office has written a letter to HOS to not being taken up due to tree in building plan. MP Hall - Work completed. DIET Block - Structural work completed of 2/3 building portion and structural work of remaining 1/3 portion of 2nd floor under progress except 2 no. classrooms and 1 staircase held up as there are branches of tree in the building line for which approval is pending for prunning of trees from forest department. Tile work & finishing work under progress in structurally completed 2/3 building portion and will be completed by 31.08.2024
Detail Report
Graph / Photo
93 Construction of 66KV GIS Sub station at IGH Dwarka

1549.73
984.49 (Sep'23)

0.00 (Sep'23)

Detail Report
Graph / Photo
94 Construction of New Academic Block (G+3) at DIET Keshavpuram, Delhi

1541.76


Detail Report
Graph / Photo
95 Street Scaping of 800 Meter of Road No. 58 jagat Puri Red Light to Karkardooma Chowk to make it model stretch of Street Scaping Project

1524.43


Detail Report
Graph / Photo
96 Street Scaping of 800 Meter of Road No. 58 jagat Puri Red Light to Karkardooma Chowk to make it model stretch of Street Scaping Project

1524.43
2164.27 (Jan'24)

0.00 (Jan'24)

Detail Report
Graph / Photo
97 Interior, furniture and auditorium Civil and electrical work

1512.30


Detail Report
Graph / Photo
98 Strengthening of road surface of Outer Ring Road (Road ID-972) from Modi Mill Flyover to Chirag Delhi Flyover, Chirag Delhi Flyover to Modi Mill Flyover and connecting service lanes under PWD Division SER-2/21.

1491.87


Detail Report
Graph / Photo
99 Strengthening of G.T. Road (Shahdara Flyover to Dharampura T-point & service lane ) under sub-division M-2111

1491.26

Preliminary Estimate R.I.O. from Circle office vide letter no. 23(Road)/SE Shah./2980 dated 11.07.2019 Letter written to CRRI vide No. 23(QA)/ 4993 dated 16.10.2019 for milling method. Quotation/ Invoice received from CRRI vide letter No. CRRI/FBD/PWD/Shahdara/857 dated 31.10.2019 for Rs.1770000. Fresh estimate to be prepared after receiving of report from CRRI.
work has been completed on 22/12/2022
Detail Report
Graph / Photo
100 Strengthening of Sri Aurobindo Marg (ID - 96), Ch. Harsukh Marg (ID - 19), and Ch. Jhandu Singh Marg (ID - 13) by cold milling and recycling process under SubDivision-II of Division South Road-II PWD, New Delhi during 2022-23. 19/06/2023
16/09/2023
15/11/2024
1489.16
1169.53 (Oct'24)

0.00 (Oct'24)
SBG INFRACON PRIVATE LIMITED Work in Progress.
Work in Progress.
Detail Report
Graph / Photo
101 STREET SCAPING OF 600 METER OF C-22, LODHI ROAD TO MAKE IT MODEL STRETCH OF STREET SCAPING PROJECT

1480.89
4186.23 (Mar'24)

0.00 (Mar'24)

Detail Report
Graph / Photo
102 STREET SCAPING OF 600 METER OF C-22, LODHI ROAD TO MAKE IT MODEL STRETCH OF STREET SCAPING PROJECT.

1480.89


Detail Report
Graph / Photo
103 Composite Work : C/o Prefab structures office, trainee, staff accommodation, class room, kitchen, store, toilet block, parking shed, road work and other misc. civil work and various Electrical works 01/11/2023
30/04/2024
30/04/2024
1462.98

Kalyan Chandra Goyal & Company
Detail Report
Graph / Photo
104 Providing Smart card based access control system & DESfire card system for Advocate for High Court & District Court.

1462.20
134.62 (Oct'24)

0.00 (Oct'24)

Detail Report
Graph / Photo
105 Comprehensive Maintenance of Civil works for Day-to-day Maintenance and A/R and M/o Work, Special Repair etc of Dr. BSA Hospital Campus, Sector-6, Rohini, Delhi and Sanjay Gandhi Memorial Hospital Campus, Mangolpuri, Delhi during 2022-23 and 2023-24 01/05/2022
30/04/2024
30/04/2024
1462.16
520.92 (Oct'24)

0.00 (Oct'24)
work in porgress
Detail Report
Graph / Photo
106 Interior, furniture and auditorium Civil and electrical work (SW SITC of Audio visual system for Auditorium , Conference Room etc.)

1445.84
5.17 (Mar'22)

0.00 (Mar'22)

Detail Report
Graph / Photo
107 Construction of 48 Nos G plus 3 SPS Eq. classroom including 3 staircase 1 lift and 1 toilet block in Mustafabad School Delhi Including internal and external water supply sanitary installations electrical installations development of site Boundary W 09/03/2023
01/02/2024
31/12/2024
1442.22

3rd Floor Level beam reinforcement work in progress, brick masonary at GF in progress The site approach is very narrow and no congested working space for material and labour at site.
3rd Floor Level beam reinforcement work in progress, brick masonary at GF in progress The site approach is very narrow and no congested working space for material and labour at site.
Detail Report
Graph / Photo
108 STREET SCAPING OF 810 METER OF AUROBINDO MARG TO MAKE IT MODEL STRETCH OF STREET SCAPING PROJECT

1379.62
142.11 (Jan'24)

0.00 (Jan'24)

Detail Report
Graph / Photo
109 Operation & Maintenance of EI & Fans, HVAC, Sub Stations, DG Sets, UPS, Fire Fighting System, Fire Alarm System, Lifts, Solar Water Heating System etc. for the year 2022-23 and 2023-24 27/05/2022
26/05/2024
26/05/2024
1369.68
608.52 (Jun'24)

0.00 (Jun'24)
In Progress
Detail Report
Graph / Photo
110 Rehabilitation / Strengthening of PWD roads by cold milling and recycling process of various roads under Sub Division East Road-IV of Division East Road/(M-212), Delhi during 2023-24. 1. Noida Link Road (Road ID:- 70- 40036) 2. Noida more flyover (slip Road) (Road ID:- 1730).

1366.08
5.90 (Nov'24)

0.00 (Nov'24)

Detail Report
Graph / Photo
111 C/o 76 Nos. (G Plus 3) SPS equivalent classrooms at RSKV Mandawali No. 2 (School ID 1002023) including 5 staircase, 8 toilet blocks, 1 lift and internal & external water supply, sanitary installations, electrical installations, development of site, UGR, RWH, Natural STP & Fire Fighting System etc 02/04/2022
25/02/2023
15/07/2024
1359.28
451.84 (Nov'24)

0.00 (Nov'24)
K. L. ARORA & SON Work completed and cleaning and development work is in progress and will be completed by 15.07.2024
Work completed and cleaning and development work is in progress and will be completed by 15.07.2024
Detail Report
Graph / Photo
112 Operation & Maintenance of EI & Fans, DG Sets, Fire Engine, HVAC Works, Fire Alarm System, Fire Fighting and Wet Riser System, Sub Station, Solar Water Heating System etc. for the year 2022-23 and 2023-24. 26/05/2022
25/05/2024
25/05/2024
1350.14
862.61 (Oct'24)

0.00 (Oct'24)
In Progress
Detail Report
Graph / Photo
113 Strengthening/Reconstruction of Service Road of Rohtak Road (NH-10) from Metro Pillar No. 410 to 570 Mundka Industrial Area both sides (Actual length of One side 5.00 Km) under PWD, Maintenance Division West Road-2, New Delhi during 2022-23.

1296.54


Detail Report
Graph / Photo
114 Strengthening of S.A. Road under the jurisdiction of Division SER-2/21, New Delhi (Road ID: 946). 14/04/2023
12/07/2023
30/06/2024
1291.28
1626.14 (Dec'24)

0.00 (Dec'24)
MAHAVIR PRASAD GUPTA AND SONS 95%
Work in Progress
Detail Report
Graph / Photo
115 Construction of New Academic Block (G+3) at Lakshmibai College, Ashok Vihar, Delhi

1280.15
30.41 (Mar'24)

0.00 (Mar'24)

Detail Report
Graph / Photo
116 Construction of 72 Nos. equivallent classrooms (G+3) including internal electrical works sanitary installations, watter supply, fire fighting and external development works etc for Govt. Co-ed. Sr. Sec. School at PSP-10, Industrial area Phase-V, Rohini, Kirari, Delhi (Civil and Electrical) 12/03/2022
04/02/2023
15/12/2024
1275.84
667.46 (Nov'24)

0.00 (Nov'24)
M/s SURENDRA KUMAR Work in progress
Detail Report
Graph / Photo
117 STREET SCAPING OF 800 METER LENGTH OF RING ROAD, BHAIRON ROAD T-JUNCTION TO SHANTIVAN CROSSING TO MAKE IT MODEL STRETCH OF STREET SCAPING PROJECT

1226.77
493.44 (Jan'24)

0.00 (Jan'24)

Detail Report
Graph / Photo
118 Street scaping of 550 Metre of Road No 59 Waizrabad Road to make it model Street Scaping projec

1193.08
5288.56 (Jun'24)

0.00 (Jun'24)

Detail Report
Graph / Photo
119 Street scaping of 550 Metre of Road No 59 Waizrabad Road to make it model Street Scaping project

1193.08
298.41 (Mar'24)

0.00 (Mar'24)

Detail Report
Graph / Photo
120 Street scaping of 550 Metre of Road No 59 Waizrabad Road to make it model Street Scaping project

1193.08


Detail Report
Graph / Photo
121 Construction of NGO's Mess Tahirpur, Dilshad Garden, Delhi. (SH: Civil work, Electrical work and Horticulture work)

1162.30
0.50 (Nov'21)

0.00 (Nov'21)

Detail Report
Graph / Photo
122 Construction of G+4 Building for space for record room and office of Legal Aid Defense Counsel at Karkardooma Court, Delhi.

1155.11


Detail Report
Graph / Photo
123 Construction & connectivity between Anand Vihar Bus Terminal & Road No. 56 and extension of existing entry & exit of ISBT Terminal over trunk drain No. 2

1143.47

Modified PE submitted to Circle Office vide letter No. 23(5)/679 Dated 05.03.2020
Detail Report
Graph / Photo
124 Strengthening of various roads such as Najafgarh Road, Punjab Garden Road, Smt. Ginni Devi Road, Bhagwan Das Road, Hemwati Nandan Bahuguna Marg, road from Milan Cinema to H. No. 19/289 , Road from House no. H-1 to I-47 near Milan Cinema Karampura and Road from House HIL to bus terminal of 234, HIL Karampura, Lal Sai Mandir Marg D story, Pankaj Batra Marg under PWD Maintenance Division WR-2 / Sub Division WR-21, New Delhi during 2022-23. 28/04/2023
27/08/2023
27/08/2023
1124.92
1306.68 (Oct'24)

0.00 (Oct'24)
MIA Construction Pvt. Ltd.
Detail Report
Graph / Photo
125 Construction of Polyclinic at CS/OCF-2, Sector-23, Rohini, Delhi.

1123.00


Detail Report
Graph / Photo
126 STREET SCAPING OF 900 METRE OF ROAD NO. 51, MCD COLONY TO MUKUND PUR CHOWK TO MAKE IT MODEL STRETCH OF STREET SCAPING PROJECT

1119.07
28.85 (Nov'24)

0.00 (Nov'24)

Detail Report
Graph / Photo
127 Comprehensive Consultancy Services For Construction of Delhi Sports University at Village Ghevra Delhi

1110.28
71.00 (Mar'24)

0.00 (Mar'24)
30
Detail Report
Graph / Photo
128 Comprehensive consultancy Services for Construction of Delhi Sports University at Village Ghevra Delhi 06/04/2022
05/04/2025
05/04/2025
1099.29
142.42 (Oct'24)
87.00 %
0.00 (Oct'24)
SIKKA ASSOCIATES REGD. 30
Detail Report
Graph / Photo
129 C/o 76 Nos (G+3) equivalent SPS Class Rooms including 2 nos stilt, 8 nos toilet, 4 nos staircase, 1 no lift, RWH & UGR in SKV Vishwamitra, Old Seemapuri, Delhi. (SH : SPS type building i/c internal & external water supply, sanitary installations, electrical installations, development of site, fire fighting system etc.) 18/04/2022
13/03/2023
15/07/2024
1090.67
375.04 (Nov'24)

0.00 (Nov'24)
K. L. ARORA & SON Work in progress. Internal work completed & cleaning in progress, some development work under progress. One block handed over and remaining one will be handed over by 15.07.2024.
Work in progress. Internal work completed & cleaning in progress, some development work under progress. One block handed over and remaining one will be handed over by 15.07.2024.
Detail Report
Graph / Photo
130 Strengthening of road from Western Yamuna Canal to Bawana under Sub-Division NR-15, North Roads Division, PWD, Delhi(Second Call) 04/07/2023
03/12/2023
03/12/2023
1087.55
1053.38 (Oct'24)

0.00 (Oct'24)
MIA Construction Pvt. Ltd. Work in progress
na
Detail Report
Graph / Photo
131 Re-Carpeting of Najafgarh Road from Raja Garden to Uttam Nagar T Point under Division WR-I, PWD, New Delhi (Balance Work)

1076.89


Detail Report
Graph / Photo
132 Strengthening of Josip Broz Tito Marg (BRT Road) from Defence Colony Flyover to Chirag Delhi Flyover under PWD Sub-Division SER-11 of Division SER-1. (Road ID No. 1717).

1069.49
1176.29 (Jul'24)

0.00 (Jul'24)

Detail Report
Graph / Photo
133 C/o 48 Nos. (G+3) SPS Eq. classroom including 3 staircase, 1 lift and 1 toilet block in Mustafabad School , Delhi Including internal & external water supply, sanitary installations, electrical installations, development of site, Boundary Wall, UGR, RWH & Fire Fighting system etc. 09/03/2023
01/02/2024
31/12/2024
1058.78
482.51 (Oct'24)

0.00 (Oct'24)
AMOCON 3rd Floor Level beam reinforcement work in progress, brick masonary at GF in progress The site approach is very narrow and no congested working space for material and labour at site.
3rd Floor Level beam reinforcement work in progress, brick masonary at GF in progress The site approach is very narrow and no congested working space for material and labour at site.
Detail Report
Graph / Photo
134 Street Scaping of 800 Meter of Road No. 58 jagat Puri Red Light to Karkardooma Chowk to make it model stretch of Street Scaping Project

1041.75
51.29 (Nov'24)

0.00 (Nov'24)

Detail Report
Graph / Photo
135 Operation & Maintenance of EI & Fans, HVAC, DG Sets & Sub Stations, Fire Alarm System, Fire Fighting and Wet Riser System, Lifts, Solar Water Heating System etc. for the year 2022-23 and 2023-24 26/05/2022
25/05/2024
25/05/2024
1031.52
733.79 (Oct'24)

0.00 (Oct'24)
In Progress
Detail Report
Graph / Photo
136 Construction of annexe building adjoining to existing DSSSB building Karkardooma, Delhi.

988.53


Detail Report
Graph / Photo
137 Construction of annexe building adjoining to existing DSSSB building Karkardooma, Delhi.

988.53


Detail Report
Graph / Photo
138 C/O OLD AGE HOME AT BG 6 PASCHIM VIHAR DELHI

987.85


Detail Report
Graph / Photo
139 Mechanised House Keeping and Security Services/Facility Management services (FMS) for Chandni Chowk Road and appurtenances/System installed from Lal Jain Mandir to Fatehpuri Mosque for the Period 2022-2023(1 Years) 26/08/2022
25/08/2023
25/08/2023
983.09
1798.40 (Oct'24)

0.00 (Oct'24)
Soni Management & Allied Services Pvt. Ltd.
Detail Report
Graph / Photo
140 Providing Automated Housekeeping at Hon’ble CM residence & Bungalow of Delhi Council of Minister’s Delhi.

981.35
550.81 (Aug'24)

0.00 (Aug'24)

Detail Report
Graph / Photo
141 EOR to District Court Rohini at Sector-14, Delhi (SH: Emergent Civil Upgradation Remedial for Critical damaged structural elements of Court building) 09/09/2024
08/06/2025
08/06/2025
975.86
66.82 (Nov'24)

0.00 (Nov'24)
Work in progress
Detail Report
Graph / Photo
142 Repair and Rehabilitation of Shahdara Flyover Delhi. (SH: Construction of New Crash Barrier and Strengthening of edge beam after dismantling of old crash barrier) 12/03/2023
11/11/2023
11/11/2023
971.06
102.42 (May'24)

0.00 (May'24)

Work in Progress


null

Detail Report
Graph / Photo
143 Strengthening of Pusa Road from Pusa Round About to Dayal Chowk, PUSA Institute (IARI) Internal Road from Ratanpuri Chowk to PUSA Employment Exchange Gate and O.P. Bharti Marg, improvement of riding surface of Guru Ravi Dass Marg and Prof. Ram Nat...

968.64
90.00 (Jun'24)

0.00 (Jun'24)

Detail Report
Graph / Photo
144 Repair and Rehabilitation of 10 Nos. Bridges- Timarpur Crossing (2 nos.), Mall Road Crossing, Maurice Nagar (2 Nos.), Gurmandi (Vijay Nagar Crossing), GT Road Crossing near Shakti Nagar (2 Nos.) and Bharat Nagar (2 Nos.) over Najafgarh Drain, Delhi.

964.90


Detail Report
Graph / Photo
145 C/o Researcher Block and Residential Staff Quarters for Delhi Institute of Hotel Management and Catering Technology at Lajpat Nagar, New Delhi 09/08/2020
08/11/2021
08/11/2021
958.41
148.14 (Nov'24)

0.00 (Nov'24)
Sushil Buildwell Pvt. Ltd. Work Just Started
Detail Report
Graph / Photo
146 Strengthening of various roads under PWD Division North West Road-1 under Sub Division NWR-12 During 2022-23

954.00
716.73 (Mar'24)

0.00 (Mar'24)
work completed
Nil
Detail Report
Graph / Photo
147 Strengthening of Nangloi-Najafgarh Road from Nilothi Mor to Airforce Bani Camp under WR-14, PWD New Delhi

953.94
671.44 (Sep'22)

0.00 (Sep'22)

Detail Report
Graph / Photo
148 Operation of E.I. and Fans, Pumps, Automatic Fire Fighting system, Fire Alarm system

951.12


Detail Report
Graph / Photo
149 Comprehensive Maintenance of Electrical, Civil & Horticulture Operations relating Day to day Maintenance, Special Repair etc of Ch. Brahm Prakash Auyrved Charak Sansthan, Khera Dabar, Najafgarh, Delhi during 2022-23 & 2023-24

950.40
173.12 (Mar'24)

0.00 (Mar'24)
work has been rescind
no work started
Detail Report
Graph / Photo
150 Improvement & strengthening of Road No. 63, Delhi (From Bhopura Border to loni Gol Chakkar except flyover).

935.18
38.95 (Mar'22)

0.00 (Mar'22)
A/A & E/S awaited
Detail Report
Graph / Photo
151 Strengthening of Najafgarh Road from Uttam Nagar to Dwarka Mod under Sub - Division WR-14, PWD New Delhi

935.00
15.80 (Feb'23)

0.00 (Feb'23)

Detail Report
Graph / Photo
152 EOR to District Court Dwarka Sec.-10 Dwarka, under Sub Division-III of SWBMD, New Delhi during 23-24. (SH:- Immediate reinforce measures for spelling hazard cases at critical locations of RCC slabs between ABCD wing connecting corridor, public toilets (22 Nos.) Admn Block toilet (08 Nos), Ahlmad Room (08 No.), some damaged portion of public stair and Judges Stair at various location for smooth functioning of Dwarka Court Complex.

926.04
45.00 (Jul'24)

0.00 (Jul'24)

Detail Report
Graph / Photo
153 Construction of FoB/Skywalk from Supreme Court Metro Station to Additional Building Supreme Court and Supreme Court Main Campus on Mathura Road, New Delhi 16/07/2022
16/01/2023
31/08/2023
926.03

Work in progress
NA
Detail Report
Graph / Photo
154 Strengthening of Najafgarh Road from Uttam Nagar to Dwarka Mod under Sub - Division WR-14, PWD New Delhi.(Balance Work)

919.83
939.93 (May'23)

0.00 (May'23)

Detail Report
Graph / Photo
155 STREET SCAPING OF 810 METER OF AUROBINDO MARG TO MAKE IT MODEL STRETCH OF STREET SCAPING PROJECT

910.96
508.81 (Mar'23)

0.00 (Mar'23)

Detail Report
Graph / Photo
156 Running operation of lifts 06/05/2021
05/05/2024
05/05/2024
909.76
465.79 (Oct'24)

0.00 (Oct'24)
Guruji Elevator
Detail Report
Graph / Photo
157 Comprehensive Maintenance of Electrical, Civil & Horticulture Operations relating Day to day Maintenance, Special Repair etc of Ch. Brahm Prakash Ayurved Charak Sansthan, Khera Dabar, Najafgarh, Delhi during 2022-23 & 2023-24 (Balance works).

906.11
264.62 (Aug'24)

0.00 (Aug'24)
work has been rescinded
work not started by the firm
Detail Report
Graph / Photo
158 Construction of Police Post at Bakkarwala

900.00
213.56 (Jun'24)

0.00 (Jun'24)

Detail Report
Graph / Photo
159 Strengthening of various roads under sub division NWR-24, Division NWR-2, SainikVihar Delhi under PWD North Zone with hot recycling method after cold milling for roads upto 30m ROW

880.22
738.35 (Jun'24)

0.00 (Jun'24)

Detail Report
Graph / Photo
160 RMO Specialized Electrical & Mechanical Services of Delhi High Court, New Delhi. (SH: Comprehensive Maintenance & Operation of Multi Level Under Ground Automated Car Parking along with associated Electrical & Mechanical Services installed at Delhi High Court, Sher Shah Suri Marg, New Delhi).

878.02


Detail Report
Graph / Photo
161 Construction of annexe building adjoining to existing DSSSB building Karkardooma, Delhi. (Civil and Electrical Work)

871.75


Detail Report
Graph / Photo
162 Operation and Maintenance of EI and FANS Sub Station and DG Set HVAC Works Fire Fighting and Wet Riser System Fire Alarm System Lifts RO Plant etc

866.40
81.85 (Jul'24)

0.00 (Jul'24)

Detail Report
Graph / Photo
163 Rehabilitation/ Strengthening of PWD roads by cold milling and recycling process of various roads of Sub Division East Road-III under Division East Road/(M-212), Delhi during 2023-24. 1. Road Along Ghazipur Drain. - (Road ID:- 129-40GZR).

866.23


Detail Report
Graph / Photo
164 Strengthening of Road No. 57 (Swami Dayanand Marg from Bihari Colony Railway crossing to Telco T-point red light) 17/09/2022
15/12/2022
15/12/2022
861.04
1228.01 (Oct'24)

0.00 (Oct'24)
Invalid
Detail Report
Graph / Photo
165 Repair and Rehabilitation of Gokul Puri Flyover Delhi. (SH: Replacement of Bearings and Expansion joint and repair of Bearing Pedestal). (Recall) 07/10/2022
12/01/2023
31/12/2023
859.23
346.90 (Aug'24)

0.00 (Aug'24)

Work in Progress


null

Detail Report
Graph / Photo
166 Two fixed single court and one doubles court with movable wall and SITC of EI, VRF, CCTV, LAN System, Fire Fighting System, Fire Alarm System & Signage Board) (Civil and Electrical work.

847.08


Detail Report
Graph / Photo
167 Operation & Maintenance of EI & FANS, Sub Station & DG Set, HVAC Works , Firen Fighting and Wet Riser System, Fire Alarm System, Lifts, RO Plant etc.

843.88


Detail Report
Graph / Photo
168 Operation of lifts

834.91


Detail Report
Graph / Photo
169 Strengthening of Mehrauli Mahipalpur Road from Andheria More to NH-48 (Road ID: 777)

834.48


Detail Report
Graph / Photo
170 Operation & Maintenance of E.I., pumps, fire fighting& fire alarm system, DG Sets & Sub-station, Lifts, ETP/STP Plant and HVAC System & AC units etc

831.74


Detail Report
Graph / Photo
171 C/o Pucca School Building at Mandawali Fazalpur (I.P Extn) Delhi. 09/03/2012
08/06/2013
08/06/2013
827.32
935.50 (Apr'14)

100.00 % (Apr'14)
PNSC Infrastructure Pvt. Ltd.
Detail Report
Graph / Photo
172 Construction of Police Post Sadiq Nagar, New Delhi during 2020-21 (SH: Civil and Electrical work).

824.93
482.82 (Mar'24)

0.00 (Mar'24)
95%
nil
Detail Report
Graph / Photo
173 Re-Carpeting of Najafgarh Road from Raja Garden to Uttam Nagar T Point under Division WR-I, PWD, New Delhi. (Balance Work). 30/09/2022
29/03/2023
29/03/2023
818.33
1245.87 (Mar'24)

0.00 (Mar'24)
SATYA PARKASH AND BROS PVT LTD
Detail Report
Graph / Photo
174 Strengthening of various roads of Pitampura area under PWD Division North West Road-1 and under Sub Division NWR-14 During 2022-23

802.14
529.67 (May'24)

0.00 (May'24)
work is on hold.
work could not be processed due to cold weather conditions
Detail Report
Graph / Photo
175 Police Post Rampura Golden Park

798.00
188.33 (Mar'24)

0.00 (Mar'24)

Detail Report
Graph / Photo
176 Comprehensive Maintenance ,Operation of Multi Level Under Ground Automated Car Parking along with associated Electrical ,Mechanical services installed at Delhi High Court, Sher Shah Suri Marg, New Delhi

793.37


Detail Report
Graph / Photo
177 Comprehensive Maintenance & Operation of Multi Level Under Ground Automated Car Parking along with associated Electrical & Mechanical services installed at Delhi High Court, Sher Shah Suri Marg, New Delhi

793.37


Detail Report
Graph / Photo
178 Comprehensive Maintenance & Operation of Multi Level Under Ground Automated Car Parking along with associated Electrical & Mechanical services installed at Delhi High Court, Sher Shah Suri Marg, New Delhi

793.37
1282.73 (Oct'24)

0.00 (Oct'24)

Detail Report
Graph / Photo
179 Strengthening of Road No. 235, Guru Virjanand Marg, Road between Jupiter Appt. to Priya Appt., Nalanda Appt. to Nightingale Appt., Navyug Appt. to IFC drain (Brotherhood Appt.), Road between Devdoot Appt. to Parmarth Appt., Road between Kirti Appt. to DAV school, Road between Lok Vihar Appt. (PWD Road) to F-block Market, Road Sunrise Appt. to DAV School, Road from F-234 to IFC drain (Over head tank) Vikaspuri, Road from ITICorner to Central School, Road starting from Oxford School to Airport Appt. and Road No. 236 at Vikaspuri under sub division WR-14, Division WR-1

790.08
638.21 (May'23)

0.00 (May'23)

Detail Report
Graph / Photo
180 Strengthening of roads from (i) Ramdev Chowk Narela to Singhu Border, NH44 (ii) Ramdev Chowk Narela to Piao Maniyari border (iii) Y-Section railway crossing to CRPF camp, under Sub-Division NR-13, PWD Division North Roads, Delhi 08/07/2023
03/01/2024
03/01/2024
789.25

MIA Construction Pvt. Ltd. Work yet to be started
NIL
Detail Report
Graph / Photo
181 Anticarbonation painting with designing and theme painting work on Britannia flyover, Wazirpur Flyover and Shalimar Bagh Elevated Flyover on Ring Road and Elevated Flyover from Mukarba Chowk to Mangolpuri Flyover on Outer Ring Road.

787.93
75.00 (Oct'24)

0.00 (Oct'24)

Detail Report
Graph / Photo
182 Strengthening of Road No.40 (Vir Banda Bairagi Marg) from Zakhira Pump House to Metro Pillar No.100 under PWD Division North West Road-1 under Sub Division NWR-13 During 2023-24.

774.14
612.25 (Oct'24)

0.00 (Oct'24)
work in progress
Nil
Detail Report
Graph / Photo
183 Addition Alternation in Residence of Honble Chief Minister at 6 Flag Road, Civil Lines, Delhi during 2020 21 (SH:Providing additional Accommodation Civil and Electrical works)

761.07
2926.01 (Oct'23)

0.00 (Oct'23)

Detail Report
Graph / Photo
184 Operation & Maintenance of E.I, pumps, sub-station, DG Sets, firefighting & fire alarm system, HVAC & AC units & R.O. Plant etc 24/05/2022
23/05/2024
23/05/2024
754.12
397.81 (May'24)

0.00 (May'24)
SKYLINE AIRCONDITIONING ENGINEERS PVT.LTD.
Detail Report
Graph / Photo
185 Strengthening of Najafgarh Road from Uttam Nagar to Dwarka Mod under Sub - Division WR-14, PWD New Delhi 14/07/2022
13/10/2022
13/10/2022
751.50

Chaudhary Construction Company Pvt. Ltd.
Detail Report
Graph / Photo
186 Renovation work at office complexes of Divisional Commissioner 5 Shamnath Marg Delhi 110054 15/12/2021
14/06/2022
31/07/2023
747.65
289.55 (Oct'23)

0.00 (Oct'23)
Work In Progress. Site available in Parts.
satisfactory
Detail Report
Graph / Photo
187 Comprehensive Maintenance of Civil works for Day-to-day Maintenance and A/R & M/o Work, Special Repair etc of GTB Hospital, Campus Shahdara, Rajiv Gandhi Super Speciality Hospital, Campus Tahirpur, Dr. Hedgewar Arogya Sansthan, DGHS, Karkardooma, Hospital, Campus, AAPC Kanti Nagar & Various Dispensaries under CHMSD-V, Delhi during 2022-2023& 2023-24 03/06/2022
02/06/2024
02/06/2024
721.25
402.95 (Nov'24)

0.00 (Nov'24)
AZFARUDDIN (Up to date progress of all Sub Divisions) Work is in progress.
Detail Report
Graph / Photo
188 Strengthening of various roads (SGH Road, Kalamandir Cinema Road, LP Road, B Block and G/F Block Road - Mangolpuri, H Block Road and G Block Road - Sultanpuri, Road No. A2 sector 1/2 - Rohini) having ROW<30 meter under sub division NWR-21, Division NWR-2, Sainik Vihar Delhi under PWD North Zone with hot recycling method after cold milling during 2022-23 and 2023-24.

714.93
219.43 (Oct'24)

0.00 (Oct'24)

Detail Report
Graph / Photo
189 Construction of Police Post Mianwali Nagar

714.00
139.17 (Jun'24)

0.00 (Jun'24)

Detail Report
Graph / Photo
190 Construction of Police Post Paschimpuri (now Sayyad village at Nangloi)

700.00
231.52 (Jun'24)

0.00 (Jun'24)

Detail Report
Graph / Photo
191 Replacement of chillers installed at Delhi Secretariat Building

700.00


Detail Report
Graph / Photo
192 Providing and installing factory made Customozed Galvanized Steel Sheet Modular Kitchen Cabinets with Miscellanous civil and Electrical work at 'A, B, C & D' block of jedges Quarters, District Court Residential Complex, Saket, New Delhi

695.92


Detail Report
Graph / Photo
193 Strengthening of various roads (Road No. 318, Road No. 319, Sir Chhotu Ram Ram Marg-A3 Road, N.S. Hardikar Marg-A1 Road) under Sub Division NW R-21, Division NW R-2, Sainik Vihar, Delhi under PWD North Zone with hot recycling method after cold milling.

686.56
486.42 (Sep'24)

0.00 (Sep'24)

Detail Report
Graph / Photo
194 Providing and installing factory made Customized Galvanized Steel Sheet Modular Kitchen Cabinets and civil work at ‘A, B, C & D’ block of Judges Quarters, District Court Residential Complex, Saket, New Delhi.

684.19


Detail Report
Graph / Photo
195 Comprehensive maintenance of Civil services at Deen Dayal Upadhyaya Hospital & Residential Complex, Hari Nagar, Janakpuri Superspeciality Hospital C2B Janakpuri New Delhi, Shree Dada Dev Matri avum Shishu Chikitsalya, Dabri and DG at various places, P.W.D (GNCTD), New Delhi for 2 years i.e. 2022-2023, 2023-24 27/05/2022
26/05/2024
26/05/2024
683.47
462.62 (Sep'24)

0.00 (Sep'24)
Anand and Company

Work in Progress


Detail Report
Graph / Photo
196 Re laying of World Athletics approved 400 Mtr. synthetic athletic track at Chhatrasal Stadium, Delhi 26/03/2022
24/07/2022
24/07/2022
679.06
704.12 (Jan'24)

0.00 (Jan'24)
ADVANCED SPORT TECHNOLOGIES LLP Work in progress
Work in progress
Detail Report
Graph / Photo
197 Operation, Routine Maintenance and special repair of various Electrical & Mechanical installations at Delhi High Court, New Delhi

675.71
216.17 (Mar'24)

0.00 (Mar'24)

Detail Report
Graph / Photo
198 Operation, Routine Maintenance and special repair of various Electrical & Mechanical installations at Delhi High Court, New Delhi

675.71
130.80 (Jan'24)

0.00 (Jan'24)

Detail Report
Graph / Photo
199 Construction of VREC-68 Gokalpur at Wazirabad Road Mandoli under North East (B&R) Maint. Division PWD, Delhi (SH:- Structural design & drawing and soil testing)

675.19


Detail Report
Graph / Photo
200 Construction of Old Age Home including electrical work at BG-6, Paschim Vihar, Delhi. (Composite work).

668.69

Work is held up for Architectural Plan & revised plan submitted to fire department for approval by SA


Detail Report
Graph / Photo
201 Repair and Rehabilitation of Vikas Marg Flyover & Ashram Chawk Flyover Delhi. (SH: Repair of Spalled and Honeycomb Concrete, RCC Jacketing of Piers, Carbon Fiber wrapping of Pier Cap, Replacement of Expansion joint, Repair of Bearing Pedestal and Maintenance of bearing) 26/03/2023
25/09/2023
25/09/2023
666.76
280.84 (Jun'24)

0.00 (Jun'24)

Work in Progress


null

Detail Report
Graph / Photo
202 Comprehensive Maintenance , Operation of Multi Level underground automated car parking along with associated Electrical , Mechanical services installed at Delhi High Court, Sher Shah Suri Marg, New Delhi

661.38
604.53 (May'23)

0.00 (May'23)

Detail Report
Graph / Photo
203 Remodeling of drain from 25 futa road, Meet nagar to Loni Gole Chakkar at Road No.-63, Construction of sump well at loni Gole Chakkar & MIG/ LIG Flat, Providing and laying K-9 pipe from Loni gole Chakkar to Drain No-01 & Construction of pump House, Electrical & mechanical Services at Loni Gole Chakkar & MIG/ LIG Flat. 31/03/2022
28/07/2022
28/07/2022
657.45
755.13 (Dec'24)

0.00 (Dec'24)
K. L. ARORA & SON work is in progress
BSES HT Line shifting
Detail Report
Graph / Photo
204 Providing Automated Housekeeping at Honble CM Residence and Bungalow of Delhi Council of Ministers Delhi

649.40
684.55 (Nov'24)

0.00 (Nov'24)

Detail Report
Graph / Photo
205 Strengthening of road of Major District Road -138 from Mazara Dabas Mor to CRPF gate under Sub-Division NR-15, PWD Division North Roads, Delhi 28/04/2022
24/10/2022
24/10/2022
643.92
797.07 (Oct'24)

0.00 (Oct'24)
Kundu Nirma work
completed
Detail Report
Graph / Photo
206 Strengthening of DDU Marg, JLN Marg & NS Marg under Sub Division-2/Division SRDP-I dg. 2022-23 05/01/2023
19/02/2023
19/02/2023
638.88
608.87 (Jul'24)

0.00 (Jul'24)
ROAD TECH
Detail Report
Graph / Photo
207 Construction of Police Post Sector - 21 & 23 Rohini.

634.43


Detail Report
Graph / Photo
208 E & M works relating to day to day operation & maintenance, A/R & M/O Works & Special Repair Works 26/05/2022
25/05/2024
25/05/2024
619.38
706.09 (Oct'24)

0.00 (Oct'24)
H. N. TRADERS & ENGINEERS

Work in progress


Work in progress

Detail Report
Graph / Photo
209 Civil and Electrical Work. 05/03/2023
29/11/2023
29/11/2023
617.03
96.64 (Nov'24)

0.00 (Nov'24)
CHANDRA CONSTRUCTION COMPANY
Detail Report
Graph / Photo
210 Making Building and Campus Barrier Free for accessibility of disabled persons CWDS. 21/10/2023
16/01/2024
16/01/2024
614.92
106.24 (Nov'24)

0.00 (Nov'24)
work in progress
Detail Report
Graph / Photo
211 Repair and Rehabilitation of Tilak Nagar District Center Flyover, Tilak Nagar Near Metro Flyover & Punjabi Bagh Flyover (SH: Repair of Spalled and Honeycomb Concrete, Replacement of Expansion joint, Repair of Bearing Pedestal, Replacement of Elastromeric Bearings, Maintenance of POT-PTFE Bearing and Installation of Height Barrier) 26/05/2023
25/01/2024
25/05/2024
612.17
181.38 (Aug'24)

0.00 (Aug'24)

Work in progress. Fund is not avilable for payment.


Work in progress. Fund is not avilable for payment.

Detail Report
Graph / Photo
212 Rehabilitation/ Strengthening of Vikas Marg (Road ID:- 611) by cold milling and recycling process under Sub Division East Road-IV of Division East Road/(M-212), Delhi during 2023-24.

603.44


Detail Report
Graph / Photo
213 Comprehensive routine maintenance and operation of EI and Fans compound lights High Masts, Lifts, pumps, Fire Fighting System, AFA and PA system, HVAC plant, RO Plant and water softening plant, water coolers and substation DG sets at District Court Dwarka New Delhi 26/07/2022
25/07/2024
25/07/2024
600.77
103.74 (Nov'23)

0.00 (Nov'23)
Swastik Electrotech Pvt. Ltd.
Detail Report
Graph / Photo
214 Upgradation of one staff room, each at 951 School under Delhi Govt. SH 123 Nos. of staff rooms under West Maintenance Circle.

593.40
156.62 (Oct'22)

0.00 (Oct'22)

Detail Report
Graph / Photo
215 Structural Work. 21/02/2012
20/10/2012
30/11/2012
588.19

Rama Const. Co.
Detail Report
Graph / Photo
216 Strengthening of Roads Dr. Kundan Lal Marg, Rajouri Apartment Road, H.No. 14/35 to 13/101 Subhash Nagar (Near Shadley School), Shanti Devi Marg, Ayodhya Prasad Chopra Marg, R.No. 32 to 17/117 Subhash Nagar, DA-1, Hari Nagar to DB-1 Hari Nagar, BA-BB 25/09/2022
24/01/2023
24/01/2023
583.83
939.89 (Oct'24)

0.00 (Oct'24)
MAHAVIR PRASAD GUPTA AND SONS
Detail Report
Graph / Photo
217 Providing stone Matrix Asphalt(SMA) under Sub Division-II, South West Road-II Najafgarh, New Delhi 23/11/2021
21/01/2022
21/01/2022
581.89
320.63 (Mar'23)

0.00 (Mar'23)
Pawan Kumar
Detail Report
Graph / Photo
218 Construction of New Academic Block (G Plus 3) with Future Extention of One Floor at Lakshmibai College, Ashok Vihar, Delhi (Civil and Electrical) Composite work 28/01/2022
27/12/2022
31/08/2023
579.95
825.13 (Aug'24)

0.00 (Aug'24)
Invalid Work is in progress.
Detail Report
Graph / Photo
219 Strengthening of Ring Road from I.P. Flyover to Raj Ghat Crossing under Sub-Division-3 of Division (C & ND)-Roads (M-413), PWD, New Delhi during 2022-23. 02/06/2023
01/08/2023
01/08/2023
579.40
736.93 (Oct'24)

0.00 (Oct'24)
MAHAVIR PRASAD GUPTA AND SONS Work in Progress.
Detail Report
Graph / Photo
220 Strengthening of various roads such as prof. Joginder Singh Marg Major Deepak Tyagi Marg Lal Sai Marg 60 Futa Road Possangi Pur Road A 1 Block Main Road Opp A 1 Block Main Road and Asalat Pur Road 1 under Sub Division WR 12 Division WR-1 PWD New Delh 25/09/2022
24/01/2023
24/01/2023
578.76
846.83 (Mar'24)

0.00 (Mar'24)
MAHAVIR PRASAD GUPTA AND SONS
Detail Report
Graph / Photo
221 Strengthening of Najafgarh Jharoda Road ic raising of depressed road at Ekta Vihar under Sub Division II South West Road II PWD New Delhi. ID 1231 16/10/2019
12/02/2020
12/02/2020
567.80
236.37 (Jul'20)

0.00 (Jul'20)
Pawan Kumar WORK IN PROGRESS
WORK IN PROGRESS
Detail Report
Graph / Photo
222 Repair and Rehabilitation of Africa Avenue Flyover, Moti Bagh Flyover, Savitri Cinema & IIT Flyover, Delhi. (SH: Repair of Spalled and Honeycomb Concrete, Replacement of Expansion joint, Maintenance of bearing and Installation of Height Barrier & Seismic Arrester) 26/05/2023
25/01/2024
25/01/2024
566.13

Work in Progress
null
Detail Report
Graph / Photo
223 Construction of Inter-connecting RCC box type storm water drain between JhaitkaraMorh via Chhawla Village to IandFC Najafgarh drain, NajafgarhBijwasan Road (ID 1173) under PWD Division SWR-II, New Delhi. 17/03/2023
12/09/2023
12/09/2023
564.26
722.02 (Jul'24)

0.00 (Jul'24)
Rajan Builders
Detail Report
Graph / Photo
224 Strengthening / Resurfacing of (1) Road No. 70, (2) Road 62, (3) Road from Seemapuri Bus depot Road no. 70 to GTB Hospital Road (Gurudwara road), (4) Road from Labour chowk (Seemapuri link road) to General Hospital Road no. 64 (Divider Road), (5) Road from Rajiv Gandhi Super Specialty Hospital to GTB Hospital Road. 26/01/2023
25/05/2023
25/05/2023
554.25
399.12 (Oct'24)

0.00 (Oct'24)
Kundu Nirman
Detail Report
Graph / Photo
225 C/o Police Post at Preet Vihar, Delhi.

552.89
0.78 (Mar'22)

0.00 (Mar'22)

Detail Report
Graph / Photo
226 Renovation / Upgradation of one room for Teachers Training at 5 nos. school under NWB-2, Delhi. SH: Civil Work

552.73


Detail Report
Graph / Photo
227 Strengthening of Kanjhawala Road (Road No.3) from Mangolpur Kalan Marble Market to Rajeev Nagar under PWD Sub Division-NWR-25 and Division NWR-2, Sainik Vihar Delhi under PWD North Zone with hot recycling method after cold milling for roads upto 30m ROW 27/02/2022
26/06/2022
26/06/2022
548.07
718.68 (Mar'24)

0.00 (Mar'24)
RK Brothers
Detail Report
Graph / Photo
228 Providing services of Maintenance vehicle with labour & T&P etc. for all Sub-Division for two year

542.39


Detail Report
Graph / Photo
229 Construction of Additional 12 nos Classroom, 2 nos Toilet along with 2 nos staircase in GGSSS Khajoori Khas (School Id:- 1104153) and 11 nos Classroom, 1 no Toilet & 2 nos staircase at SKV, Khajoori Khas (School Id:- 1104022), over existing (G+1) SPS structure with Prefabricated fibre reinforced sandwich panel with Light Gauged Steel Framed Structure

541.10
43.69 (Oct'24)

0.00 (Oct'24)

Detail Report
Graph / Photo
230 Comprehensive Maintenance , Operation of Multi Level underground parking along with associated Electrical , Mechanical services installed at Delhi High Court, Sher Shah Suri Marg, New Delhi dg. 2018-19. 02/11/2018
01/11/2019
01/11/2019
539.98
214.77 (Sep'19)

0.00 (Sep'19)
Work in progress
No
Detail Report
Graph / Photo
231 Strengthening of various road under North Roads, Division, Sub-Division NR-14, Shaheed Captain Vikram Batra Chowk PWD, New Delhi. 1. Mam Chand Dhaniya Marg from Old GTK Road to Siraspur Village 2. ITI Road at Jahangirpuri from Main Road to Metro Apartment & K-Block from Metro Apartment to dividing road K-Block.3. C-D Park Road from Main Road Jahangirpuri to Kushal Cinema Road. 4. I-Block Road & JBlock Road from Main Road Jahangirpuri to G.T. Road at Jahangirpuri. 21/04/2023
19/07/2023
19/07/2023
538.44
473.46 (Oct'24)

0.00 (Oct'24)
Karambir Rana Builders work in progress
null
Detail Report
Graph / Photo
232 Improvement of footpath & Strengthening of road from Chandgi Ram Akhara Red Light to Timarpur Red Light Crossing under Sub Division-4,C&ND-R, New Delhi dg 2023-24. 10/06/2023
09/08/2023
09/08/2023
536.55
156.94 (Mar'24)

0.00 (Mar'24)
Sethi Construction Work in Progress.
Detail Report
Graph / Photo
233 Construction of Police Post at Sanjay Gandhi Transport Nagar, Delhi.

536.00

.
Detail Report
Graph / Photo
234 Civil work comprehensive maintenance of Shanker Road and Vandematram Marg including carriageway, footpaths, central verge, Service road etc within the right...

535.97


Detail Report
Graph / Photo
235 Renovation / construction works at Rajiv Gandhi Stadium, Bawana 07/07/2022
04/11/2022
04/11/2022
535.01
389.62 (Mar'24)

0.00 (Mar'24)
M/s Vinod Kumar & Company Work in progress
Work in progress
Detail Report
Graph / Photo
236 Providing services of Maintenance vehicle with labour and T and P etc for Division NW R 1 for two year

533.23
42.86 (Apr'23)

0.00 (Apr'23)
work completed on dated 6/11/23
nil
Detail Report
Graph / Photo
237 CIVIL Works - Comprehensive maintenance of various roads i/c carriageway, footpaths, central verge within right of way, mechanised desilting of drains etc and other mi

533.12


Detail Report
Graph / Photo
238 Development of Sports infrastructure in govt. Co-ed. Senior Secondary School, Najafgarh Dhansa Road, Mitraon Village (ID No.1822178), Najafgarh, Delhi. 14/02/2024
11/10/2024
11/10/2024
532.93

0%
A letter wrote to DDE(Sports) regarding hindrance due to existing trees on the alignment of swimming pool and half Basket Ball Court vide letter No. 54(110)/EE/Epd-III/ PWD/2023-24/198 dated 15.03.2024, 226 dated 26.03.2024 and 296 dated 30.04.2024
Detail Report
Graph / Photo
239 Widening of carriageway including shifting of central verge and footpath of Outer Ring Road from Majnu ka Tila Red Light to Wazirabad Flyover (Under 77 corridor improvement plan) in Division C&ND-R New Delhi dg. 2022-23 08/11/2022
07/03/2023
31/08/2023
532.40
314.00 (Jul'24)

0.00 (Jul'24)
AMOCON Work in Progress.
Detail Report
Graph / Photo
240 Improvement / Strengthening of Garhi Mendu Road (From 3rd Pusta to Wazirabad Road No. 59) under Sub Division M-2134 (Agmt No. 31/2024-25)

523.72
159.26 (Oct'24)

0.00 (Oct'24)

Detail Report
Graph / Photo
241 Improvement and reconstruction of footpath on various roads (Mathura Road, Bhairon Marg and Ring Road under Division M-321, Delhi on urgent basis in view of G-20 SUMMIT 2023. 12/02/2023
14/04/2023
14/04/2023
518.84
123.07 (Nov'23)

0.00 (Nov'23)
In-progress
Detail Report
Graph / Photo
242 Strengthening/Raising of Road to prevent Water Logging on the Road Deenpur to Kachha Talab and Tazpur mod to police check post at goyala deenpur Road (ID 1168) under Sub Division-V, South West Road-II, PWD New Delhi. 28/03/2023
25/06/2023
25/06/2023
517.09
727.33 (Jul'24)

0.00 (Jul'24)
Mahavir Prasad Gupta & Sons
Detail Report
Graph / Photo
243 Strengthening of various roads of Sector-3,5,6 & 7 under sub division NWR22, Rohini, Delhi under PWD North Zone with hot recycling method after cold milling during 2022-23

513.31
472.82 (Nov'23)

0.00 (Nov'23)

Detail Report
Graph / Photo
244 Strengthening of Mall Road Extension from Azadpur H Point to Sanjay Enclave (GTK Depot) under Sub Division NR-12, North Roads Division, PWD, Delhi. 17/02/2023
17/04/2023
17/04/2023
507.62
554.16 (Oct'24)

0.00 (Oct'24)
M.C.CONSTRUCTION CO. 60%
null
Detail Report
Graph / Photo
245 Comrehensive Maintenance to Residential & Non-residential buildings under jurisdiction of North Building Division (Sub Division M-3221, M3222 & M3223), Delhi during 2024-25

506.94


Detail Report
Graph / Photo
246 Repair & Rehabilitation of facade and other RCC members i/c water tank and water proofing of terrace of Vyaapar Bhawan, Deptt of Trade & Taxes Building, I. P Estate, New Delhi.

500.66


Detail Report
Graph / Photo
247 Repair & Rehabilitation of facade and other RCC members i/c water tank and water proofing of terrace of Vyaapar Bhawan, Deptt of Trade & Taxes Building, I. P Estate, New Delhi .

500.66
0.20 (Jul'22)

0.00 (Jul'22)

Detail Report
Graph / Photo
248 +=> Testing 12072027-1221 by Deepak <=+ EOR to Govt. Co-Ed. S.S.S., Singhu Delhi-40. (SH:- 1.Water Proofing treatment of roof, room no. 14,15,16,17,18,19,20,21 and MP hall, bathroom adjoining with MP hall 2. Minor repair of classroom roofs, wall and boundary wall) (Bldg. Id-13101260), (Sch. Id-1309268) & (EOR Id-20232108).

500.00


Detail Report
Graph / Photo
249 C/o Common Mess Building near to the newly constructed Girls Hostel Building at DTU Campus. 14/08/2023
09/05/2024
09/05/2024
498.97

Satish Chand RaJesh Kumar Pvt. Ltd. Work awarded on 14.08.2023. Preparation of Structural drawings & their approval is in progress.
in progress
Detail Report
Graph / Photo
250 Strengthening of Mehrauli-Mahipalpur Bypass Road (Road Id: 2140) from NH-8 to CPWD Flyover.

492.92
314.71 (Jun'24)

0.00 (Jun'24)

Detail Report
Graph / Photo
251 Maintenance and Operation of various Electrical Installations.

491.77
16.90 (Dec'23)

0.00 (Dec'23)

Detail Report
Graph / Photo
252 Construction of Police Post Sawada Ghevra B Block Colony Delhi

487.01


Detail Report
Graph / Photo
253 Running and Maintenance of lifts installed in residential and non-residential buildings at GTB Hospital complex, Shahdara, Delhi Sub Head Running operation of lifts 17/01/2019
16/01/2021
16/01/2021
485.43
103.10 (Oct'23)

0.00 (Oct'23)
Guruji Elevator Work in progress 3RD RA 40220380
Detail Report
Graph / Photo
254 Remodelling of drain from Gurudwara near Mahendra Park Junction to G.T.K. Depot near Sanjay Enclave, both side carriageway at Mall Road Extension under Sub Division NR-12 06/08/2022
03/12/2022
03/12/2022
484.07
570.51 (Oct'24)

0.00 (Oct'24)
Invalid work in progress
null
Detail Report
Graph / Photo
255 Nazafgarh Road to A-71, Rajauri Garden, A-31 Rajauri Garden, 20-Block Tilak Vihar Road, Radhaswami Satsang Marg and Tilak Nagar Main Market Road under PWD Division WR-1, New Delhi.

481.51


Detail Report
Graph / Photo
256 Renovation of 64 Nos. Toilets of Lawyers Chamber Block D E F and G at Karkardooma Court Delhi dg. 2023 24 (Civil and Electrical Work).

477.50

cpvc pipe line laying work is in progress at E block
pipe line laying
Detail Report
Graph / Photo
257 Supply, Installation, Testing and Commissioning of Mike Based Communication System for Court Rooms at Saket Court Complex, New Delhi

472.59


Detail Report
Graph / Photo
258 Supply, Installation, Testing and Commissioning of Mike Based Communication System for Court Rooms at Saket Court Complex, New Delhi

472.59
417.19 (Mar'23)

0.00 (Mar'23)

Detail Report
Graph / Photo
259 Construction of Foot Over Bridge with staircase and lift for padestrian at Rao Tula Ram Marg (Road ID-98) near Petrol Pump, New Delhi.

465.11


Detail Report
Graph / Photo
260 Providing and installation of informatory/directional sign boards on various roads under Division NWR-1 & NWR-2 for DSEU Campus, Ashok Vihar, DSEU Campus, Pitampura, DSEU Campus Rohini, DSEU Campus, Wazirpur I DSEU Campus, Wazirpur II) of North Zone

460.45


Detail Report
Graph / Photo
261 Providing and installation of informatory/directional sign boards on various roads under Division NWR-1 & NWR-2 for DSEU Campus, Ashok Vihar, DSEU Campus, Pitampura, DSEU Campus Rohini, DSEU Campus, Wazirpur I DSEU Campus, Wazirpur II) of North Zone

460.45

Full site not given by client.
Site not fully available
Detail Report
Graph / Photo
262 Providing and installation of informatory directional sign boards on various roads under Division NWR1 and NWR2 for DSEU Campus Ashok Vihar DSEU Campus Pitampura DSEU Campus Rohini DSEU

460.45


Detail Report
Graph / Photo
263 Operation & Maintenance of E.I., pumps, fire fighting& fire alarm system, DG Sets & Sub-station, Lifts, ETP/STP Plant and HVAC System & AC units etc. 04/06/2022
03/06/2024
03/06/2024
457.53
326.79 (Oct'24)

0.00 (Oct'24)
M/s Jain Electric Works
Detail Report
Graph / Photo
264 Rehabilitation and strengthening of Janak Setu Flyover in New Delhi (Balance Work) 29/03/2020
29/09/2020
31/03/2021
457.44
197.55 (Aug'24)

0.00 (Aug'24)

Work in progress


null
Detail Report
Graph / Photo
265 Strengthening / resurfacing of PWD roads by cold milling and recycling process of various roads of Sub Division East Road-II under Division East Road /(M-212), Delhi during 2023-24. 1. Road No. 109 from Sapera Basti to Khora Chowk. 2. Dallupura Road from Timber Market to Noida Border. 3. Budh Singh Marg from Manav Ashray Cut to Dallupura T-point 20/03/2024
18/05/2024
18/05/2024
456.73
251.55 (Oct'24)

0.00 (Oct'24)
Chaudhary Construction Company Pvt. Ltd.
Detail Report
Graph / Photo
266 RMO specialized Electrical and Mechanical services of Delhi High Court, Delhi. (Sub Head Operation, Routine Maintenance and special repairs of various Electrical and Mechanical installations at Delhi High Court, New Delhi.) 27/05/2024
26/05/2025
26/05/2025
452.42
121.48 (Nov'24)
57.00 %
0.00 (Nov'24)
M/s Shaka Electrical (India) WORK IN PROGRESS
Detail Report
Graph / Photo
267 Construction of Foot Over Bridge between Newly Constructed Court Building and Tis Hazari Court Complex at Boulevard Road under Sub Division-I of Division SRDP-I, Delhi (Sh:- Civil & Electrical Works). 20/02/2023
21/05/2023
21/05/2023
450.86
370.04 (Nov'24)

0.00 (Nov'24)
S S Chauhan & Sons steel erection work is in progress
work delayed due to existing service coming in layout
Detail Report
Graph / Photo
268 Construction of approach roads for RUB (North side) along with ROB at Meet Nagar on Road No. 63.

450.13

A/A & E/S awaited
Detail Report
Graph / Photo
269 Improvement of Karawal Nagar Road from Wazirabad Road (Near Bhajanpura Mazaar) to Dayalpur Chowk( Length of Road- 1.75Km)

449.01

A/A & E/S awaited
Detail Report
Graph / Photo
270 Civil Works - Mechanised Sweeping and Cleaning of Roads including Carriageway, Footpaths, Central Verge, Service Roads etc. within the right of way, Mechanised Desilting

448.15


Detail Report
Graph / Photo
271 Comprehensive maintenance of civil operation relating day by day maintenance, special repair etc. of Burari Hospital, Kaushik Enclave, Burari, Delhi during 2022-23 and 2023-24 05/11/2022
04/11/2024
04/11/2024
445.82
104.57 (Oct'24)
100.00 %
0.00 (Oct'24)
work in progress, as per complaint received in sub division, the regular day to day compliance is made.
no
Detail Report
Graph / Photo
272 Routine maintenance and operation of EI and fans Compound Lights High Masts Lifts Pumps Fire Fighting System AFA and PA system Sub Station and DG set and 4 x 400 TR Central HVAC Plant at Delhi Judicial Academy and National Law University at Sector 14 06/03/2023
05/03/2026
05/03/2026
443.54
90.91 (Nov'23)
57.00 %
0.00 (Nov'23)
GLOBAL ENTERPRISES
Detail Report
Graph / Photo
273 Remodelling of drain from 5th Pusta to Ghonda Chowk at Gamri Road Delhi.

440.84

sanction awaited
AA & ES awaited
Detail Report
Graph / Photo
274 Civil & Electrical Works.

440.61
173.30 (Mar'24)

0.00 (Mar'24)

Detail Report
Graph / Photo
275 Construction of Old Age Home at Sarita Vihar, New Delhi including internal andexternal water supply sanitary installations, electric installations, Lift, SolarHeating System and fire Fighting (Civil + Electrical Works).

436.76


Detail Report
Graph / Photo
276 Providing additional staircase from Skywalk towards Moti Bagh, MS staircase for underground sump, provision for additional railing over skywalk, Covering of Skywalk with CGI sheet roofing & C/o wall with MS Grill towards Moti bagh at FOB Durgabai Deshmukh Metro Station, Ring Road New Delhi. 29/06/2023
28/10/2023
28/10/2023
435.39
106.59 (Mar'24)

0.00 (Mar'24)
Work in Progress
null
Detail Report
Graph / Photo
277 Operation & Comprehensive Maintenance of FOB Lifts, Security Guards, Maintenance of Electrical Installation & Other Electrical Work at Various FOB’s & Subways under AE(E), SD-I, Thyagraj Stadium, New Delhi.

434.57


Detail Report
Graph / Photo
278 Operation & Comprehensive Maintenance of FOB Lifts,Security Guards, Maintenance of Electrical Installation & Other Electrical Work at Various FOB’s & Subways under AE(E), SD-I, Thyagraj Stadium, New Delhi.

434.57


Detail Report
Graph / Photo
279 Construction of 200 Bedded Hospital at Kaushik Enclave, Burari, Delhi. (S.H. Supplying, installation, testing and commissioning of 11 Nos. additional prefabricated Modular Operation Theatre)

432.01
88.29 (Feb'23)

0.00 (Feb'23)

Work has been transferred to EE(E) Health Maintenance Elect Divn (N)


Detail Report
Graph / Photo
280 Replacement of existing metal halide sports flood lights with energy efficient LED Sports Flood Light including all the allied works at Chhatrasal Stadium Model Town Delhi

430.21
180.33 (Oct'23)

0.00 (Oct'23)

Updated


.

Detail Report
Graph / Photo
281 Strengthening of Najafgarh Phirni Road ID 1228 under Sub Division II of South West Road II PWD New Delhi

429.94

WORK IN PROGRESS
WORK IN PROGRESS
Detail Report
Graph / Photo
282 Comprehensive improvement and maintenance of horticulture and landscaping work on soft areas of central verges and sides of footpath etc. on Inner Ring Road (from Mayapuri to Mall Road and Arihant Marg Road No. 51), Delhi under North Zone, PWD.

429.78


Detail Report
Graph / Photo
283 Construction of Additional 18 nos Classroom, 2 nos Toilet along with 5 nos staircase in GGSSS Sonia Vihar (School Id:- 1104335) over existing (G+1) SPS structure with Prefabricated fibre reinforced sandwich panel with Light Gauged Steel Framed Structure including electrical and Furniture installations

426.34


Detail Report
Graph / Photo
284 Comprehensive maintenance of various roads under Sub-Division South East Road-13

425.32
14.60 (Jun'20)

0.00 (Jun'20)

Detail Report
Graph / Photo
285 Routine/Comprehensive Maintenance & Operation of Electrical & Mechanical Services

425.32
172.21 (May'24)

0.00 (May'24)

Detail Report
Graph / Photo
286 Civil and Electrical work

420.91


Detail Report
Graph / Photo
287 Construction of 112 Nos. additional SPS classrooms [GGSS, Mukundpur Village (Sch. ID 1207230) - 36 Nos., GBSSS Bakhtawarpur (Sch. ID 1309266) - 56 Nos. including 01 No. M.P Hall Equivalent to 08 Nos. Class Rooms and SV Lancer Road (Sch. ID 1207032) - 20 Nos.)] under North Education Division, PWD Delhi, including internal and external water supply, sanitary installations, electrical installations, development of site and fire fighting system etc. SH : Balance Work.

419.01
285.32 (Dec'24)

0.00 (Dec'24)

Detail Report
Graph / Photo
288 EI work (Composite Work) 19/01/2009
31/08/2012
31/08/2012
417.80

Bhart Eletricals (Associated of M/s ERA)

...


Detail Report
Graph / Photo
289 EI work (Composite Work) 19/01/2009
30/11/2013
30/11/2013
417.80

Bhart Eletricals (Associated of M/s ERA)

...


Detail Report
Graph / Photo
290 Operation of Pumps, Fire Fighting system, Lifts, DG Sets and repair and fixing of E.I.

417.30


Detail Report
Graph / Photo
291 Operation of Pumps, Fire Fighting system, Lifts, DG Sets and repair and fixing of E.I.

417.30


Detail Report
Graph / Photo
292 Op. of Pumps, Fire Fighting system, Lifts, DG Sets and repair and fixing of E.I

417.30


Detail Report
Graph / Photo
293 Operation of Pumps, Fire Fighting system, Lifts, DG Sets and repair and fixing of E.I.

417.30


Detail Report
Graph / Photo
294 Strengthening of various roads (Ahinsha Marg sector-9, Rohini, Babosachowk to Tulsi Aptt., Ring road to Maheswari Aptt., ORR to Road No. B-5 sector-14, Rohini, Internal road of sector-9, Rohini, Pkt.-14 to Pkt.C-1, Pkt.-10 to Pkt.D-4, sector-20, Rohini, Pkt. 8 to Pkt. 9, Pkt. B-2 to Park, Pkt. 13 to pkt. 9, Pkt. 5 to Pkt. 6 sector-21, Rohini) having ROW < 30 mtr. under Sub Division NWR-23, PWD Division NWR-2, Sainik Vihar Delhi under PWD North Zone by cold milling method with recycled material, dg. 2022-23 & 2023-24. 16/08/2023
15/02/2024
15/02/2024
415.97
138.14 (Jun'24)

0.00 (Jun'24)
R K Brothers & Company
Detail Report
Graph / Photo
295 Comprehensive maintenance & development of dense horticulture work in the juridiction of East Road Sub Division-IV (Civil), under Hort. Sub Division East Horticulture Division East. SH:-Gap filling and dense plantation in Green Belt i/c maintenance of existing plants on Noida Link Road(From Akshardham to Noida Border),Vikas Marg (From Sachivalya crossing to ITO Chungi), Road No. 57-A (N.H.9 to Road 56 T Jnction), Madhu Vihar Road,(Joshi Colony to Road No. 56 T Jnction) & Narwana Road ( Mother Dairy to Punch Mahal Awas, IP.).

414.13


Detail Report
Graph / Photo
296 Construction of Building for Old Age Home at Geeta Colony, New Delhi.

413.84


Detail Report
Graph / Photo
297 Strengthening of Ring Road from Shantivan to Hanuman Setu under Sub-Division-3 of Division (C & ND)-Roads (M-413), PWD, New Delhi. During 2022-23. 02/06/2023
01/08/2023
01/08/2023
413.71
408.77 (Oct'24)

0.00 (Oct'24)
MAHAVIR PRASAD GUPTA AND SONS Work in progress
Detail Report
Graph / Photo
298 Providing X-ray Baggage scanner, DFMD security equipment at entry/security check points at Delhi High Court, New Delhi.

407.68
282.47 (Apr'23)

0.00 (Apr'23)

Detail Report
Graph / Photo
299 Improvement/providing and fixing of MS railing in central verge from Peeragarhi Chowk to Rama Road Round About (Zakhira Flyover) under PWD Division West Road-2/ Sub Division WR-21 & WR-24, New Delhi during 2019-20

406.91

Estimate sent to Circle office for approval
Detail Report
Graph / Photo
300 Repair and Rehabilitation Mukundpur and Karampura Flyover. SH: - (Replacement of bearings and expansion joints of Karampura Flyover and rehabilitation of RCC jacketing of two piers of Mukundpur Flyover.- (Recall) 05/10/2022
04/04/2023
31/10/2023
406.38
50.71 (Jun'24)

0.00 (Jun'24)

Work in Progress


null

Detail Report
Graph / Photo
301 AR MO to Various Residential Buildings Type III IV V and VI under Sub Division M 3231 at 16 Rajpur Road Delhi dg 2022 23

401.13
406.08 (Oct'24)

0.00 (Oct'24)

Detail Report
Graph / Photo
302 stopping vibration and noise 26/02/2013
25/06/2013
31/05/2014
398.44

K.L. Arora & Son Sanctioned
Detail Report
Graph / Photo
303 Providing remedial measures for stopping vibration and noise due to flyover to Outer Ring Road near Ber Sarai, Munirka and Vasant Vihar. 26/02/2013
25/06/2013
31/05/2014
398.44

K.L. Arora & Son Work Foreclosed
Work Foreclosed
Detail Report
Graph / Photo
304 Improvement and Strengthening of Road no. 65 from Keshav Chowk to Road No. 66 under PWD Sub Division M-2134, Delhi (Agmt No. 17/2024-25)

397.06
150.00 (Oct'24)

0.00 (Oct'24)

Detail Report
Graph / Photo
305 C/o Additional 8 nos. classrooms, 1 no. Toilet alongwith 1 no. Staircase in GBSSS Karawal Nagar (School Id-1104143) and 9 nos. classrooms, 1 no. Toilet alongwith 2 no. Staircase at GGSSS Tukhmirpur No-2, ID - 1104419 over existing (G+1) SPS structure with prefabricated fibre reinforced sandwich panel with light gauged steel framed structure including and furniture installation.

396.18
76.42 (Oct'24)

0.00 (Oct'24)

Detail Report
Graph / Photo
306 Operation of lifts 22/10/2022
21/10/2024
21/10/2024
389.63
296.20 (May'24)

0.00 (May'24)
Akash enterprises 1st RA bill paid
Work in progress
Detail Report
Graph / Photo
307 Strengthening of Prithvi Singh Dagar Marg ID 1175 from RawtaMorh Dhansa Road to Daurala Border under PWD Division- South West Road-II New Delhi. 16/10/2019
12/02/2020
388.15
0.84 (Apr'22)

0.00 (Apr'22)
Pawan Kumar UNDER TENDERING PROCESS
UNDER TENDERING PROCESS
Detail Report
Graph / Photo
308 Improvement and maintenance of horticulture and landscaping work on central verges and sides of footpath etc. on Inner Ring Road (from Mayapuri to Mall Road and Arihant Marg Road No. 51), Delhi under North Zone, PWD for 36 months.

387.36


Detail Report
Graph / Photo
309 Replacement of outlived Sub station equipment installed atDepartment of Trade , Taxes, Vyapar Bhawan Building, I.P. Estate New Delhi

387.07
260.73 (Oct'24)

0.00 (Oct'24)

Detail Report
Graph / Photo
310 Strengthening of Keshopur Sabzi Mandi Road from Outer Ring Road to Subhash Nagar Drain Chowkhandi Road, Road from GuruVirjananad Marg to Distt. Park Vikas puri, Tilak Vihar Main Road, Pelicon Road from Guru Virjananad Marg to Road No. 235 Ext, Brain 25/09/2022
24/12/2022
24/12/2022
386.35
584.79 (Mar'24)

0.00 (Mar'24)
MAHAVIR PRASAD GUPTA AND SONS
Detail Report
Graph / Photo
311 Running operation and comprehensive maintenance of online UPS, TVSS, CVCF, APFF, PAC and Isolation transformer of different capacity installed at RGSS Hospital, Tahirpur, Delhi.

385.81


Detail Report
Graph / Photo
312 Providing, running and maintaining Water Sprinkler Anti Smog Guns on hire basis on various roads under Sub Division-I of Shahdara Road Division, PWD, New Delhi during 2024-25.

385.75


Detail Report
Graph / Photo
313 SITC of Central Air conditioning Plant in upper 3.5 Three and Half stories including strengthening of sub station and provision of false ceiling of MCH Block 500 Bedded New Ward Block at G.T.B. Hospital Shahdara Delhi

385.28


Detail Report
Graph / Photo
314 Strengthening of Amar Shaheed Bismil Marg, Police Line road Parwana Road under Sub Division NWR-24, Division NWR-2, Sainik Vihar, Delhi under PWD North Zone with hot recycling method after cold milling for roads upto 30m ROW. 20/08/2023
19/12/2023
19/12/2023
381.30
452.42 (Jul'24)

0.00 (Jul'24)
SBG INFRACON PRIVATE LIMITED
Detail Report
Graph / Photo
315 Repair and Rehabilitation of Vehicular Under Pass (VUP) and its approaches and Approaches of three RoBs at PulMithai on SPM Marg, Delhi 16/01/2020
15/10/2020
31/03/2021
379.24
92.13 (May'24)

0.00 (May'24)

Work in progress


null
Detail Report
Graph / Photo
316 Street Scaping of Nelson Mandela Road, New Delhi. 01/07/2023
29/08/2023
29/08/2023
377.15
246.26 (Feb'24)

0.00 (Feb'24)
MAHAVIR PRASAD GUPTA AND SONS
Detail Report
Graph / Photo
317 Comprehensive repair of road footpath, drain, painting, Speed breakers, Patch repairs and other misc. repair works in SectionI & Section-II for 1 year

376.63
202.87 (Oct'24)

0.00 (Oct'24)

Detail Report
Graph / Photo
318 Comprehensive repair of road footpath, drain, painting, Speed breakers, patch repairs and other misc. repair works in SectionI & Section-II for 1 year

376.63


Detail Report
Graph / Photo
319 Operation & Maintenance of E.I, pumps, substation, DG Sets, fire fighting & fire alarm system, HVAC & ductable AC system, lift, Cold Room & solar water heating system etc. 10/05/2022
09/05/2024
09/05/2024
376.50
265.70 (Oct'24)

0.00 (Oct'24)
M/s Vivek Associates
Detail Report
Graph / Photo
320 (i) Civil work Comprehensive maintenance of Ring Road including carriageway, footpaths, central verge, service road etc. within the right of way, mechanised desilting

375.34
56.99 (Jan'24)

0.00 (Jan'24)

Detail Report
Graph / Photo
321 Providing of services of Security Guard ,security supervisor & security manager &Mechanized Housekeeping Services for Internal and External areas of Tis Hazari court Extension block in Delhi-110054. 01/07/2023
31/12/2023
31/12/2023
373.04
477.53 (Jul'24)

0.00 (Jul'24)
SONI MANAGEMENT AND ALLIED SERVICES PVT. LTD.
Detail Report
Graph / Photo
322 Road Resurfacing of Savitri Cinema (Road ID-601) Road from Guru Ravi Dass Marg to Outer Ring Road under Sub Division SER-24. 15/04/2023
14/06/2023
30/04/2024
372.52
520.12 (Mar'24)

0.00 (Mar'24)
Kundu Nirman work in progress
no hindrance
Detail Report
Graph / Photo
323 Thermoplastic paint on various roads under Sub-Division R11, R-12, R-13 and 14.

371.03
225.72 (Jan'24)

0.00 (Jan'24)

Detail Report
Graph / Photo
324 Construction of RMCRoad From Shaheed Bhagat Sigh Marg to Chanchal park under Sub-Division WR-14, Division WR-1, New Delhi. Dg. 2021-22

369.30


Detail Report
Graph / Photo
325 Construction of RMC Road From Shaheed Bhagat Sigh Marg to Chanchal park under Sub-Division WR-14, Division WR-1, New Delhi. Dg. 2021-22

369.30


Detail Report
Graph / Photo
326 Comprehensive Maintenance of Central Jail Mandoli Complex dg. 2024- 25 (12 Months).

369.22
63.94 (Oct'24)

0.00 (Oct'24)

Detail Report
Graph / Photo
327 Providing Solar Panel on roof top at District Court Karkardooma Delhi.

366.36


Detail Report
Graph / Photo
328 Civil Repair works of Footpaths, Central Verge, Service Roads etc. on various roads under Sub-Division NWR-24 29/09/2022
27/09/2023
27/09/2023
366.09

work completed
Detail Report
Graph / Photo
329 Strengthening of Ring Road from Raj Ghat to Shanti Van Crossing under Sub-Division-3 of Division (C & ND)-Roads (M-413), PWD, New Delhi. During 2022-23. 02/06/2023
01/08/2023
01/08/2023
364.49
402.57 (Oct'24)

0.00 (Oct'24)
MAHAVIR PRASAD GUPTA AND SONS Work in progress
Detail Report
Graph / Photo
330 Strengthening of Sewadham Road from Road No. 63 to UP Border dg. 2024-25, Delhi (Agmt No. 16/2024-25)

361.41
183.78 (Dec'24)

0.00 (Dec'24)

Detail Report
Graph / Photo
331 Up-gradation of Analog Camera to IP CCTV Surveillance Systems at District Court Karkardooma Delhi.

360.66
77.04 (Jul'24)

0.00 (Jul'24)

Detail Report
Graph / Photo
332 C/o 20 Nos. Additional SPS Class Rooms and 2 Nos. Toilet in GGSSS, Tukhmirpur-1 (School ID: 1104262), 6 Nos. Classrooms in GGSSS, Tukhmirpur-2 (School ID: 1104419) & C/o Additional 7 Nos. Classrooms at Govt. Co.ed. Sec. School Teliwara, Shahdara (School ID: 1001151) over existing (G+1) SPS Struture.

360.43
134.89 (Oct'24)

0.00 (Oct'24)

Detail Report
Graph / Photo
333 Strengthening of C.C. Pavement of Disused Canal Road by C.G.B.M under Sub-Division East Road-I of Division East Road/(M-212) Delhi. dg. 2023-24

359.73


Detail Report
Graph / Photo
334 Re-Surfacing of various roads of Vasant Vihar Roads (Poorvi Marg (Road ID - 781), Paschimi Marg (Road ID - 782 ), Basant Marg 1 (Road ID - 778), Basant Marg 2 (Road ID - 779), Munirka Marg 1 and2 (Road ID - 783)) and Providing and Laying of Stone Ma

359.35


Detail Report
Graph / Photo
335 Construction of Foot Over Bridge at Gurudwara Majnu ka Tila on Road No. 45 under Sub-Division-4 of Division C and ND-R, New Delhi. 06/09/2022
05/03/2023
05/03/2023
358.46
33.14 (Aug'24)

0.00 (Aug'24)
Fiberfill Engineer
Detail Report
Graph / Photo
336 Construction of Old Age Home at Sarita Vihar, New Delhi. 02/09/2022
01/09/2023
01/09/2023
358.09
9.95 (Jun'23)

0.00 (Jun'23)
WORK IN PROGRESS
WORK IN PROGRESS
Detail Report
Graph / Photo
337 1) Running and maintenance of UPS at GTB Hospital complex, complex, shahdara, Delhi. 2) Running and maintenance of servo voltage stabilizer at GTB Hospital Complex, Shahdara, Delhi. (SH: Comprehensive maintenance and operation of UPS and CVCF System).

355.41


Detail Report
Graph / Photo
338 Strengthening of RMC Road from Shaheed Bhagat Singh Marg to Chanchal park under Sub Division WR 14 Division WR 1 New Delhi during 2021 22

354.88


Detail Report
Graph / Photo
339 Strengthening of RMC Road from Shaheed Bhagat Singh Marg to Chanchal park under Sub-Division WR-14, Division WR-1, New Delhi during 2021-22

354.88


Detail Report
Graph / Photo
340 Strengthening of RMC Road from Shaheed Bhagat Singh Marg to Chanchal park under Sub-Division WR-14, Division WR-1, New Delhi during 2021-22

354.88


Detail Report
Graph / Photo
341 Strengthening of RMC Road from Shaheed Bhagat Singh Marg to Chanchal park under Sub-Division WR-14, Division WR-1, New Delhi during 2021-22

354.88


Detail Report
Graph / Photo
342 Improvement and Strengthening of MB Road Khajuri Chowk to Sabhapur Village at City Side.

353.93

A/A & E/S awaited
Detail Report
Graph / Photo
343 Civil & Electrical Work. 30/03/2023
29/09/2023
29/09/2023
352.07
184.33 (Oct'24)

0.00 (Oct'24)
Engineers India Construction Ltd.
Detail Report
Graph / Photo
344 Construction of SPS Fire Station Mandawali Delhi-110092 (SH:- Civil & Electrical Work)

352.07
23.52 (Jan'24)

0.00 (Jan'24)

Detail Report
Graph / Photo
345 C/o 200 Bedded Hospital at Kaushik Enclave, Burari, Delhi. (S.H. SITC of Medical Gas Pipe Line System)

350.95
67.59 (Nov'23)

0.00 (Nov'23)
Tender Awarded
Detail Report
Graph / Photo
346 Comprehensive repair works of footpaths, central verge, service roads etc. on other roads under Sub division NWR-23

350.32


Detail Report
Graph / Photo
347 Desilting of road side storm water drain/ sewer line by Super Sucker Machine on Various roads, under SRD Project Division-I.) Recall of Tender. 26/03/2023
25/03/2024
25/03/2024
349.42
336.62 (Mar'24)

0.00 (Mar'24)
NITIN KUMAR SHARMA
Detail Report
Graph / Photo
348 (1) SITC of Additional Surveillance CCTV System at different locations of Dwarka Court Complex at Sector10, Dwarka, New Delhi. (2) Up-gradation of existing analog CCTV Surveillance system to I P Base CCTV Surveillance System at District Court, Sector-10, Dwarka, New Delhi 22/05/2022
21/11/2022
21/11/2022
348.67
30.00 (Aug'23)

0.00 (Aug'23)
Pan Intellecom Ltd work in progress
bullet supply awaited
Detail Report
Graph / Photo
349 Renovation of 64 Nos. Toilets of Lawyers Chamber Block D E F and G at Karkardooma Court Delhi dg. 2023 24.(Civil and Electrical Work. 1st Recall) 27/08/2023
22/02/2024
22/02/2024
348.05
75.02 (Dec'23)

0.00 (Dec'23)
Mohd Aftab laying of cpvc pipe E block
in progress
Detail Report
Graph / Photo
350 Construction of Additional 18 nos Classroom, 2 nos Toilet along with 5 nos staircase in GGSSS Sonia Vihar (School Id:- 1104335) over existing (G+1) SPS structure with Prefabricated fibre reinforced sandwich panel with Light Gauged Steel Framed Structure including electrical installation etc.

343.90
58.41 (Oct'24)

0.00 (Oct'24)

Detail Report
Graph / Photo
351 Comprehensive maintenance of Civil works at Guru Gobind Singh Govt. Hospital, Raghubir Nagar, Delhi and Rao Tula Ram Memorial Govt. Hospital, Jaffarpur Kalan, Delhi P.W.D. (GNCTD), New Delhi for 2 years 2021-22, 2022-23. 23/05/2022
21/05/2024
30/11/2024
343.73
83.41 (Mar'24)

0.00 (Mar'24)
Aliyan Constaruction Company Work is under progress.
Detail Report
Graph / Photo
352 Comprehensive Maintenance and Operation of Trauma Block, New Ward Block, OT, Gynae, Old Ward Block, Doctors and Nurses Hospital and Residential Complex Lifts at DDU Hospital, Hari Nagar, New Delhi (SH Operation of Lifts)

341.50


Detail Report
Graph / Photo
353 Providing and fixing road signage boards on various roads Under Sub Division I,II,III,IV,V PWD SWR-I New Delhi.

341.49
193.74 (Mar'24)

0.00 (Mar'24)

Detail Report
Graph / Photo
354 C/o 17 Nos. additional SPS class rooms & 3 no. staircase i/c internal & external water supply sanitary installation electrical installations development of site fire fighting system at Govt. Sarvodaya Vidyalay, Badarpur, Khadar (School ID 1104418) in District North-East (Zone-4) Delhi

340.93

sanction awaited


null
Detail Report
Graph / Photo
355 Resurfacing of Ring Road under Division CBMD M-321, New Delhi. 27/05/2023
26/06/2023
26/06/2023
339.88
103.77 (Nov'23)

0.00 (Nov'23)
M/s Chaudhary Construction Company Pvt. Ltd. In-progress
Detail Report
Graph / Photo
356 Replacement of damaged old 900mm Dia RCC pipe with Providing and Laying 1200mm dia RCC Pipe from Som Bazar Chowk to Mungeshpur drain at Najafgarh Nangloi Road. (Road ID -1230) 18/04/2022
14/10/2022
14/10/2022
339.47
396.39 (Nov'24)

0.00 (Nov'24)
Dilshad Khan
Detail Report
Graph / Photo
357 Strengthening/resurfacing of PWD roads by cold milling and recycling process of various roads under Sub Division East Road-III of Division East Road /(M-212), Delhi during 2023-24. 1. Chilla road from Chilla chowk to Chilla Village. 2. Peripheral Road from Chilla Chowk to kotla Village.

336.33


Detail Report
Graph / Photo
358 Micro Surfacing on Outer Ring Road from Vikas Puri to Meera Bagh

334.06
173.92 (Nov'23)

0.00 (Nov'23)

Detail Report
Graph / Photo
359 PROVIDING, INSTALLATION, TESTING AND COMMISSIONING OF CENTRAL AC PLANT IN ADMINISTRATIVE BLOCK, DELHI HIGHT COURT, NEW DELHI

332.99


Detail Report
Graph / Photo
360 Construction of Back to back U-turn near Aali Village Red-light and Single U-Turn for Sarita Vihar Colony to facilitate signal free and congestion free movement of traffic on Mathura Road under SER-2/22.(Road ID-961) 19/03/2022
18/06/2022
31/07/2024
331.52
130.57 (Mar'24)

0.00 (Mar'24)
Satyam Construction Company 50%
Work in Progress
Detail Report
Graph / Photo
361 Resurfacing of Link Road from Baba Lal Dayal Chowk to Gadhwali Chowk (Total Road Length- 0.6815 km) under Sub Division-I,SRD Project Division-II, PWD, New Delhi during 2022-23.

331.46


Detail Report
Graph / Photo
362 Resurfacing of Link Road from Baba Lal Dayal Chowk to Gadhwali Chowk (Total Road Length- 0.6815 km) under Sub Division-I,SRD Project Division-II, PWD, New Delhi during 2022-23.

331.46


Detail Report
Graph / Photo
363 Comprehensive Maintenance of RO Filtration Units in Ortho Block Hostels LNRDH Various Location in LNH 02/01/2023
01/01/2026
01/01/2026
327.30
307.36 (Oct'24)
63.00 %
0.00 (Oct'24)
M/s Vivek Associates

Work in progress


Work in progress

Detail Report
Graph / Photo
364 Street Scaping and beautification of Vikas marg No. 75A & 75B Vijay Chowk to Laxmi Nagar Red Light (SH: Civil, Electrical and Horticulture works)

326.12
260.58 (Sep'24)

0.00 (Sep'24)
K L ARORA CONSTRUCTIONS PVT LTD
Detail Report
Graph / Photo
365 Civil & Electrical Works. 30/03/2023
29/07/2023
29/07/2023
324.30
180.03 (Nov'24)

0.00 (Nov'24)
Mohd Ahson Infra Private Limited
Detail Report
Graph / Photo
366 Comprehensive Maintenance of RO Filtration Units in Ward Block , Gynae Block , OPD Block , Emergency and OT Block in LNH 21/10/2022
20/10/2025
20/10/2025
322.38
313.00 (Oct'24)
71.00 %
0.00 (Oct'24)
M/s Vivek Associates

Work in progress


Work in progress

Detail Report
Graph / Photo
367 Civil & Electrical Work

316.48


Detail Report
Graph / Photo
368 Misc development of Parade ground works including Electrical works at New Police Line, Kingsway Camp, Delhi. (Civil and Electrical Work)

316.48


Detail Report
Graph / Photo
369 Misc development of Parade ground works including Electrical works at New Police Line, Kingsway Camp, Delhi. (Civil and Electrical Work)

316.48


Detail Report
Graph / Photo
370 Construction of Reinforced Cement Concrete Retaining Wall along IandFC drain from Kali Mata Mandir to FOB near Janak Cinema on Pankha Road (ID 2027) under Sub Division-21, Division- SWR-II, PWD, New Delhi. 03/07/2023
31/08/2023
31/08/2023
316.12
329.31 (Aug'24)

0.00 (Aug'24)
Surender Singh
Detail Report
Graph / Photo
371 RMO E and M Services at SRHC Hospital Narela Delhi during the year 2021-23

315.90
34.33 (Jan'24)

0.00 (Jan'24)

Detail Report
Graph / Photo
372 Improvement and Strengthening of Old G.T. Road from Yamuna bridge to Y Point Delhi.

314.25

A/A & E/S awaited
Detail Report
Graph / Photo
373 Covering of all open courtyard of (6 nos) Civil side and (8 nos) western side by providing and fixing of tubular frame/truss and covering with M.S. wire mess including provision of openable side shutter at Tis Hazari Court, Delhi. 23/03/2023
26/06/2023
26/06/2023
312.65
166.21 (Nov'23)

0.00 (Nov'23)
In-progress
Detail Report
Graph / Photo
374 Automated Housekeeping Service of MSO Building

308.94
240.02 (Aug'24)

0.00 (Aug'24)

Detail Report
Graph / Photo
375 1. RMO of Central AC Plant at A BlockGIPMER2. RMOof Central AC Plant B BlockGIPMERSH Operation and Comprehensive maintenance of Blue Star Make Central AC Plant 11/09/2019
10/09/2021
10/09/2021
306.35
130.70 (Mar'23)

0.00 (Mar'23)
Blue Star Limited work in progress and 2nd R/A paid to M/s Blue Star Ltd.
work in progress and 2nd R/A paid to M/s Blue Star Ltd.
Detail Report
Graph / Photo
376 Day to Day Maintenance & Operation of Electrical Installation LT Panel Boards, DG Sets, Sub-Station and Pumps i.e. Rain Water/Storm Water/Sewage dewatering on various Underpass/RUB under the jurisdiction of NESD-1.

306.01


Detail Report
Graph / Photo
377 Comprehensive Maintenance of RO Filtration Units 03/03/2023
02/03/2026
02/03/2026
305.87
200.05 (Oct'24)
57.00 %
0.00 (Oct'24)
M/s Vivek Associates

work in progress


work in progress

Detail Report
Graph / Photo
378 Repair and Rehabilitation of Sarita Vihar Flyover, Delhi. (SH: Repair of Box girder of entry and exit loop with carbon fiber lamination, Expansion Joints and Bearing) 14/01/2023
13/07/2023
30/09/2023
305.15
65.93 (May'24)

0.00 (May'24)

Work in Progress


null

Detail Report
Graph / Photo
379 Redevelopment of School Block/ Pass Section & two wheeler parking area, Delhi High Court, New Delhi. (SH: Civil & Electrical works).

304.12


Detail Report
Graph / Photo
380 Providing, running and maintaining Anti Smog Gun on hire basis at various locations 22/05/2023
21/05/2024
21/05/2024
303.86

Invalid Work in progress
Detail Report
Graph / Photo
381 Road Restoration work of Prathvi Singh Dagar Marg(Road ID-1175) under Sub Division -III, SWR-2, Division, PWD, New Delh. 05/09/2023
01/02/2024
01/02/2024
303.35

Pawan Kumar
Detail Report
Graph / Photo
382 (1) Operation, Routine, Preventive and Comprehensive Maintenance of upto and including 100 HP pump sets at various locations under PWD EMSD SW- II, Najafgarh, for clearing storm water drain & dewatering of PWD Roads of South West Delhi. (2) Operation, Routine, Preventive and Comprehensive Maintenance of upto and including 100 HP pump sets at various locations under PWD EMSD SW- III, R K Puram, for clearing storm water drain & dewatering of PWD Roads of South West Delhi. 17/04/2022
16/04/2024
16/04/2024
302.46
189.24 (Oct'24)

0.00 (Oct'24)
Ramesh Electric Works
Detail Report
Graph / Photo
383 EOR to Sports Complex, Opposite Nightingale Society, Vikaspuri, New Delhi.(SH:- Construction of Boundary wall, guard room at gate no.3, Repair and Renovation of Toilet Blocks, Providing chain link fencing at front side of visitors sitting area and colony side boundary wall in Sports complex, vikaspuri, New Delhi).

299.80
120.92 (Jul'23)

0.00 (Jul'23)

Detail Report
Graph / Photo
384 Strengthening of Najafgarh Phirni Road ID 1228 under Sub Division II of South West Road-II PWD New Delhi 10/09/2019
07/01/2020
07/01/2020
298.81
194.61 (Jul'20)

0.00 (Jul'20)
Invalid WORK IN PROGRESS
WORK IN PROGRESS
Detail Report
Graph / Photo
385 Installation of target system, bullet proofing and Anti ricochet treatment, ventilation and acoustical works) (Composite work Civil and Electrical) 07/02/2023
06/06/2023
31/08/2023
298.45
170.65 (Mar'24)

0.00 (Mar'24)
Work in Progress
Detail Report
Graph / Photo
386 Painting of Kerb Stone, railing, jersey barrier and central verge etc. of Sub-Division R-11, R-12, R-13 and R-14 for the occasion of Republic Day

298.11
50.45 (Sep'24)

0.00 (Sep'24)

Detail Report
Graph / Photo
387 Improvement and Strengthening of Zero Pusta Road (Zero Pusta to Bharampuri culvert), Gurudwara Road & Seelampur Road Delhi.

298.00

A/A & E/S awaited
Detail Report
Graph / Photo
388 Providing and installing LAN System

296.99


Detail Report
Graph / Photo
389 Running operation and comprehensive maintenance of online UPS, TVSS, APFF, PAC and Isolation transformer of different capacity installed at RGSS Hospital, Tahirpur, Delhi 26/01/2022
25/01/2024
25/01/2024
296.84
330.66 (Jul'24)

0.00 (Jul'24)
Invalid
Detail Report
Graph / Photo
390 Providing & fixing 80 mm thick Paver Block over Unpaved Shoulder Portion of Road in view of Anti Air Dust Pollution Measures for Rao Laxmi Chand Marg (ID 1174) under Sub Division 23 Division SWR-II, PWD, Delhi 14/04/2022
11/08/2022
11/08/2022
296.33
411.26 (Feb'23)

0.00 (Feb'23)
Bliss Associates
Detail Report
Graph / Photo
391 Lift 21/06/2011
15/11/2013
15/11/2013
295.04

Johnson Lifts Pvt. Ltd.

...


Detail Report
Graph / Photo
392 Construction of FOB in between Metro Pillar No. 299 to 298 at Miyawali, Udhyog Nagar, Rohtak Road (NH-10), New Delhi.(Civil and Electrical Work)

294.40
54.31 (Mar'24)

0.00 (Mar'24)

Detail Report
Graph / Photo
393 Construction of 21 nos. Aam Aadmi Mohalla Clinic (Primary Health Centres) at various places in the jurisdiction of Shahdara Circle, PWD, Delhi (Civil and Electrical Work). 28/02/2019
27/06/2019
31/03/2021
294.21
60.75 (Dec'23)

0.00 (Dec'23)
AASRA Martech Pvt.Ltd. Work in progress.
Detail Report
Graph / Photo
394 Construction of two storey Multipurpose Hall (SPS) at Sarvodaya Co-ed Vidyalaya, Shahpur Jat (School ID: 1925333) including internal and external water supply, sanitary installations, electric installations and fire fighting (Civil plus Elect. work). 09/08/2022
08/08/2023
08/08/2023
292.57
174.52 (Sep'24)

0.00 (Sep'24)
Nand gopal Gupta
Detail Report
Graph / Photo
395 Consultancy Services for Comprehensive Architectural Planning and Designing for Construction of Technical Campus at Village Bakkarwala Delhi 16/01/2022
15/10/2024
15/10/2024
288.00

Arcop Associates Pvt. Ltd. Preliminary Concept report submitted by Consultant has been submitted to DTTE vide letter dated 04.04.2022 for approval.
NIL
Detail Report
Graph / Photo
396 Civil and Electrical work. 04/05/2023
05/06/2023
05/06/2023
283.09
150.31 (Mar'24)

0.00 (Mar'24)
BHARDWAJ ENTERPRISES
Detail Report
Graph / Photo
397 Strengthening of RMC Road from Shaheed Bhagat Singh Marg to Chanchal park under Sub Division WR 14 Division WR 1 New Delhi during 2021-22 26/12/2022
25/02/2023
25/02/2023
282.98
380.05 (Jul'23)

0.00 (Jul'23)
RUDRA CONSTRUCTIONS
Detail Report
Graph / Photo
398 Supply and Installation of ESP Filter in existing AHUs for improvement in AQI at Delhi High Court, New Delhi

282.79


Detail Report
Graph / Photo
399 Supply and Installation of ESP Filter in existing AHU’s for improvement in AQI at Delhi High Court, New Delhi

282.79
155.81 (Oct'23)

0.00 (Oct'23)

Detail Report
Graph / Photo
400 Operation and Maintenance of EI and FANS Sub Station HVAC Works Fire Fighting and Wet Riser System Solar Water Heating System Cold Storage Lifts etc

282.78
68.48 (Oct'24)

0.00 (Oct'24)

Detail Report
Graph / Photo
401 (A) Renovation of E.I. and Other Electrical accessories works on 5th, 6th and 7th Floor at DGHS (HQ) Building , Karkardooma, Delhi.(B) Upgradation of Fire Fighting System at Directorate Health Services, Karkardooma, Delhi.(C) Replacement of old damaged/unserviceable Fire Alarm System at Directorate Health Services, F-17, Karkardooma, Delhi.(D)Replacement of existing 1 No. 15 Passenger lift and 2 Nos 10 Passenger lifts at Directorate General of Health Services, Karkardooma, Delhi. 30/08/2023
29/11/2023
29/11/2023
280.47

GLOBAL ENTERPRISES
Detail Report
Graph / Photo
402 Maintenance and Operation of E and M service at Residential and Non Residential Area at GTB Hospital, Complex, Shahdara Delhi

279.43


Detail Report
Graph / Photo
403 Strengthening of Road No. 30 under sub division NWR-24, Division NWR-2, Sainik Vihar, Delhi under PWD North Zone with hot recycling method after cold milling. 01/07/2023
30/10/2023
30/10/2023
279.38
340.84 (Oct'24)

0.00 (Oct'24)
A S INFRATECH
Detail Report
Graph / Photo
404 Renovation/Upgradation of the GST Office i/c A,B and C Wing at 4th Floor, Deptt. of Trade & Taxes Bldg. , IP Estate, New Delhi 06/10/2022
05/04/2023
30/09/2023
276.70

Work delayed due to not handing over site / electrical work
Detail Report
Graph / Photo
405 Renovation Upgradation of the GST Office I/c A B and C Wing at 4th Floor Deptt of Trade and Taxes Building I P Estate New Delhi RECALL

276.70
64.23 (Oct'24)

0.00 (Oct'24)

Detail Report
Graph / Photo
406 Strengthening of Road No. 42 under Sub Division NW R-24, Division NW R-2, Sainik Vihar, Delhi under PWD North Zone with Hot Recycling Method after cold miling.

272.83

work in progress
No bottleneck point
Detail Report
Graph / Photo
407 Construction of New road from Ring Road (Sarai Kale Khan) to Power Grid Corporation of India Limited under Sub-Division SER-13 of Division SER-1.

271.72
129.93 (Oct'24)

0.00 (Oct'24)

Detail Report
Graph / Photo
408 Construction of 12 Nos. Aam Admi Mohalla Clinic at various locations under South-East (Bldg)-M, Division, Hauz Khas, New Delhi during 2021-22. (Civil and Electrical works)

271.15
302.69 (Nov'24)

0.00 (Nov'24)

Detail Report
Graph / Photo
409 Supply, Installation, Testing and Commissioning of CCTV System in Guru Gobind Singh Indrasprastha University at Sec 16C, Dwarka, New Delhi. 24/07/2021
23/10/2021
31/12/2024
270.87
167.03 (Mar'23)

0.00 (Mar'23)
Work completed. Final bill yet to be paid.
Detail Report
Graph / Photo
410 Construction of store room 01 nos., Shed 2 nos. behind old building, Toe Wall in Park and Ramp for new Building Block, Renovation of all toilet and guard room, Fixing granite on stage

269.83
31.17 (May'23)

0.00 (May'23)

Detail Report
Graph / Photo
411 Operation of EI and Fans water supply fire fighting system fire alarm system electrical sub station and DG sets etc

268.16
44.79 (Oct'24)

0.00 (Oct'24)

Detail Report
Graph / Photo
412 Operation and comprehensive maintenance of FOB lifts and escalators and other electrical work at various FOBs and subways under AE E SD III R K Puram New Delhi 02/10/2022
01/10/2024
01/10/2024
267.51
154.11 (Mar'24)

0.00 (Mar'24)
Ramesh Electric Works
Detail Report
Graph / Photo
413 (1) RMO E& M Services at Various Locations at LNJP , Delhi.SH: Comprehensive Maintenance of RO/ Filtration Units in Surgical Block, NMB & Special Ward in LNH) (2) RMO E&M services various locations at GNEC, Delhi. (SH:- Provision of spares etc for Atsin make RO/Filtration Units). 02/01/2023
01/01/2026
01/01/2026
266.73
170.42 (Oct'24)
63.00 %
0.00 (Oct'24)
M/s Vivek Associates

work in progress


work in progress

Detail Report
Graph / Photo
414 Remodeling of old damaged Brick Masonry drain of Shani Bazar Road With new RCC Box Drain at Sultanpuri, Delhi.

264.96
161.20 (Aug'24)

0.00 (Aug'24)

Detail Report
Graph / Photo
415 Beautification Improvement of lift lobby and Corridor ic flooring wall dado and False ceiling from ground to 13th Floor in Trade and Taxes Building IP Estate New Delhi (Civil and Electrical Works)

263.87
105.93 (Sep'23)

0.00 (Sep'23)

Detail Report
Graph / Photo
416 Routine Maintenance & Operation of Storm Water Pump Sets, DG Set, Hiring of DG Sets, Desilting of Sumps & providing Inspection Vehicle in Rainy Season.

263.64
103.41 (Oct'24)

0.00 (Oct'24)

Detail Report
Graph / Photo
417 Regarding Establishing Migrant labour Facilitation Centre at West District, Labour Office, Karampura). (Civil Work and Electrical Work).

263.20
94.75 (Dec'23)

0.00 (Dec'23)

Detail Report
Graph / Photo
418 Regarding Establishing Migrant labour Facilitation Centre at West District, Labour Office, Karampura). (Civil Work and Electrical Work.

263.20
21.22 (Dec'23)

0.00 (Dec'23)

Detail Report
Graph / Photo
419 Beautification Upgradation of lift lobby and Corridor area ic flooring, Wall dado and False Ceiling from 1st Floor to 13th floor Civil and Electrical Work

259.34
184.12 (Sep'23)

0.00 (Sep'23)