Building Work
Cost more than 30 Cr.
Building : Work in Progress
S. No.क्र. सं. Project Name A/A & E/S Date of Start
Completion
Expected
Expenditure
Progress
Remarks View
1 Construction of Hospital at Jwalapuri, New Delhi 319.65 Cr.
06/12/2019
F.8(A)/(7)/DGHS/HC/2019/CD#112557057/Js3hfw-4017-4034
07/08/2020
13/08/2022
31/08/2024
167.76 Cr. (Oct'24)
0.00 (Oct'24)
Structure RCC work & masonry work completed. Sanitary installation work completed, façade work, development work & electrical work is in progress. Detail Report
Graph / Photo
2 Construction of Hospital at Hastsal, New Delhi 319.51 Cr.
06/12/2019
F.8(A)/(8)/DGHS/HC/2019/CD#112557060/js3hfw-3982-3998
17/06/2021
16/06/2023
30/06/2025
61.58 Cr. (Nov'24)
0.00 (Nov'24)
Structure work of main building completed. Stone cladding work, RCC work of water storage tank & front projection area, Structural steel work and other miscellaneous works are in progress. The overall progress of civil part is about to 68%. Detail Report
Graph / Photo
3 Providing Hiring of Inspection Vehicle for CE(Health 319.51 Cr.
06/12/2019
F.8(A)/(8)/DGHS/HC/2019/CD#112557060/js3hfw-3982-3998
--
--
--
19.84 Cr. (Aug'23)
0.00 (Aug'23)
Detail Report
Graph / Photo
4 Providing Vehicle for Inspection. 319.51 Cr.
06/12/2019
F.8(A)/(8)/DGHS/HC/2019/CD#112557060/js3hfw-3982-3998
--
--
--
35.85 Cr. (Nov'23)
0.00 (Nov'23)
Detail Report
Graph / Photo
5 Construction and Commissioning of Mohalla Clinics at various places in North-East Delhi under the Jurisdiction of PWD Sub- Division M-2221 (2nd call). 209.59 Cr.
27/11/2015
No. 8(83)/AS/(PGR)H&FM/2015/Vol.I/Pt File/1748-59 dated 17.11.2015 amounting to Rs.209.59 crore for 1000 nos. AAMC (Primary Health Centre)
25/01/2019
24/05/2019
30/09/2020
2.16 Cr. (Oct'21)
0.00 (Oct'21)
work in progress Detail Report
Graph / Photo
6 Construction of Mother & Child Block and Screening OPD Block at Dr. B.S.A. Hospital at Rohini, Sector-6, New Delhi 194.91 Cr.
09/05/2018
2(11)/pWD/-upgradation/Add. Beds/BSAH/2015 CD#000433373/2528-45 dt. 25.06.2018
06/03/2020
05/09/2021
31/08/2023
8.25 Cr. (Oct'24)
0.00 (Oct'24)
work in progress Detail Report
Graph / Photo
7 Construction of Mother and Child Block and Screening OPD Block at Dr. Baba Saheb Ambedkar Hospital at Rohini, Delhi, including Water Supply, Sanitary Installations, Electrical Installation, HVAC, Low side, Fire Alarm, and Fire Fighting System etc. 194.91 Cr.
25/06/2018
2(11)/PWD-Upgradation/Add. Beds/BSAH/2015 CD#000433373/2528-45
04/03/2020
03/09/2021
31/08/2024
68.64 Cr. (Nov'24)
0.00 (Nov'24)
work in progress Detail Report
Graph / Photo
8 C/o Trauma Centre and Utility Block at Sanjay Gandhi Memorial Hospital at Mangolpuri, Delhi, including Water Supply, Sanitary Installations, Electrical Installation, HVAC, Low side, Fire Alarm, and Fire Fighting System etc. 117.78 Cr.
22/06/2018
5/171/SGMH/TCSUB/CT/2016 CD# 112388502/2510-2527
04/09/2019
03/03/2021
31/05/2024
16.17 Cr. (Oct'24)
0.00 (Oct'24)

work in progress.

Detail Report
Graph / Photo
9 Construction of Pucca School Building (G+3) with Ancillary Facilities including internal water supply, sanitary installation, internal electrical installation and comprising with complete site development, RWHS, STP, Tubewell, Gen Set, PA System etc. at Ladpur Village, New Delhi (Package - 7) 101.63 Cr.

18/07/2021
17/07/2022
31/10/2023
6.06 Cr. (Oct'22)
2.00 % (Oct'22)

Work in progress.

Detail Report
Graph / Photo
10 Construction of 3 Nos. Pucca School Buildings (G+3) with Ancillary Facilities including internal water supply, sanitary installation, internal electrical installation and comprising with complete site development, RWHS, STP, Tubewell, Gen Set, PA System etc. at RPVV A-6, Paschim Vihar, Vasant Kunj and Ladpur Village, New Delhi (Package - 7). SH : Civil & Electrical work. 101.63 Cr.

18/07/2021
17/07/2022
31/07/2023
61.44 Cr. (Oct'24)
0.00 (Oct'24)

Work is in progress.

Detail Report
Graph / Photo
11 Setting up of 610 bedded semi permanent/temporary Hospital at CNBC. 97.09 Cr.
08/02/2021
12/Misc/Covid-19/2021/CD-112647590 dated 08.09.2021
23/09/2021
22/02/2022
31/12/2024
0.00 Cr. (Jun'23)
88.00 % (Jun'23)
Work stopped due to non availability of funds. Target date of completion will be decided after received of revised A/A & E/S. Detail Report
Graph / Photo
12 Upgradation/Renovation of one staff room in each of 951 schools (SH- Civil and Electrical works in Mangolpuri, Sultanpuri, Kirari, Shakurbasti and Mundka constituency Schools, Total 74 Nos. Schools of NWB-2) 83.39 Cr.
26/03/2018
F/10/Estate/Renovation of staff rooms/951 schools/DoE/945-50
--
--
--

Detail Report
Graph / Photo
13 Upgradation of staff rooms in 120 Schools under South West Building Maintenance Division, NCC Building, safdarjung Enclave, New Delhi.(SH- Civil, Electrical and furniture works). 83.38 Cr.
26/03/2018
F.16/estate/renovation of staff rooms/951 Schools/DOE/945-50 dated 26.03.2018 for Rs. 83,38,36,800/-
11/02/2019
10/06/2019
10/06/2019
5.40 Cr. (Jul'22)
0.00 (Jul'22)
WORK IN PROGRESS Detail Report
Graph / Photo
14 Construction of New block Forensic Science Laboratory, Rohini, New Delhi 59.06 Cr.
13/08/2019
3(148)/FSL/2016-17/1717-29 dt. 13.03.2019
06/03/2020
05/09/2021
30/09/2023
0.00 Cr. (Aug'23)
96.00 % (Aug'23)
96% Detail Report
Graph / Photo
15 Construction of Police Station and Multi storyed Staff Quarters at Paschim Vihar, Delhi. 51.20 Cr.
09/08/2019
14012/21/2019-UTP
--
--
--

Detail Report
Graph / Photo
16 Construction of Pucca School Building (G+3) with ancillary facilities including internal water supply, sanitary installation, electrical installation and development of site etc. at Vacant land of F1 & F2 Block Sunder Nagri, Delhi. 49.15 Cr.
14/09/2021
16/Estate/DoE/Const.160 Rooms/ Sunder Nagari/2091-95
17/10/2022
16/10/2023
31/07/2024
21.08 Cr. (Oct'24)
0.00 (Oct'24)
RCC work completed, stone work 98% completed, Some repair work is going on. The paint putty, fixing of doors & windows in progress and development work in progress and same will be completed by 31.07.2024. Detail Report
Graph / Photo
17 C/o 100 Nos. Equivalent SPS Classrooms in addition to Swimming Pool, Boundary Wall, 1 No. MP Hall, i/c Internal & External Water Supply, Sanitary Installation and Electrical Installation, RWH, UGT, Septic Tank, Development of site and Fire Fighting Systemetc. for New School Building at Naseerpur, New Delhi 45.51 Cr.
30/09/2021
F-16/Estate/DoE/Cont. of school bldg./925-30
12/02/2022
09/11/2022
30/06/2024
32.60 Cr. (Nov'24)
0.00 (Nov'24)
Initially site was encroached by local people. Encroachment on the major part of land was removed with help of education department and Delhi Police on 22.03.2022. Partly site handed over to the agency for boundary wall and building construction on 23.03.2022. Due to High Court stay order dated 30.08.2022, work was stopped in disputed area. SDM Dwarka issued his order on 21.03.2023. After which work also started in the area which was earlier under dispute. Both Blocks of school building have been completed. Work of swimming pool is in progress. Detail Report
Graph / Photo
18 Construction of Pucca School Buildings (G+3) with Ancillary Facilities including internal water supply, sanitary installation, internal electrical installation and development of site at Sector-16, Dwarka ,New Delhi. (SH: Civil and Electrical Composite Work). 38.45 Cr.
31/12/2019
F.16/Estate/Const. Pucca School Building/Sector-16/Dwarka/5769-71
18/07/2021
17/07/2022
31/12/2024
15.23 Cr. (Oct'24)
0.00 (Oct'24)
Initial Delay was due to delay in receiving local body approval. DUAC approval received on 19.09.2022. Building Plans approved by SE (Bldg.), MCD vide file No. 10106691 dt. 03.04.2023. All local body approval has been received. Structural drawing prepared & proof checking from DTU Delhi is completed. Architectural & Structural drawing is issued to the agency. Building work started on 19.05.2023. Foundation work completed. Superstructure work started, RCC slab for floor-2 level is under progress. RPE amounting to Rs.47.52 Cr. sent to DoE vide this office letter 23(49)/23/CE(Proj.)/PWD/ Estimate/501 dated: 21.03.2024 for accord of Revised A/A & E/S. Detail Report
Graph / Photo
19 C/o 68 Nos. (G+3) Equivalent SPS classrooms in SKV (Ravindra Thakur), East Vinod Nagar, Delhi (School ID 1002028) including 5 nos. staircase, 8 nos toilets, 1 no. lift & 25 nos Class rooms over existing (G+1) SPS structure with Prefabricated fibre reinforced sandwich panel with Light Gauged Steel Framed Structure including internal & external water supply, sanitary installations, electrical. 38.30 Cr.
27/09/2021
16/Estate/DoE/Const.132Rooms/SKV East Vinod Nagar/2327-31
27/03/2023
19/02/2024
31/07/2024
13.72 Cr. (Nov'24)
0.00 (Nov'24)
Block A Finishing work in progress and canopy structure work in progress. Block B Tile & granite work in progress along with plaster work back side of building. Development work in progress. Detail Report
Graph / Photo