C/o 48 Nos. (G+3) SPS Eq. classroom including 3 staircase, 1 lift and 1 toilet block in Mustafabad School , Delhi Including internal & external water supply, sanitary installations, electrical installations, development of site, Boundary Wall, UGR, RWH & Fire Fighting system etc.
Office Name
Education East & North East Maint Divn
History Sheet                 NIT Document
T.S. Amount
1456.64 Lacs
Dated
06/01/2023
Tender Amount
1058.78 Lacs
Dated
07/03/2023
Progress Details
Date of Start: 09/03/2023
Date of Completion: 01/02/2024
Expected Date of Completion: 31/12/2024
Actual Completion Date:
Contractor
M/s AMOCON
Payment
Civil:  482.51 Lacs (Oct 2024)
% Progress : % (Oct 2024)
Present Position
Civil :  02/07/2024
3rd Floor Level beam reinforcement work in progress, brick masonary at GF in progress The site approach is very narrow and no congested working space for material and labour at site.
Bottlenecks
Civil :  02/07/2024
3rd Floor Level beam reinforcement work in progress, brick masonary at GF in progress The site approach is very narrow and no congested working space for material and labour at site.